Dear PM Experts,
I'm finding it difficult to find the place to enter the persons for work centers.
These persons are used in Order Operations (Go to Operations tab/Select the particular operation/Click Internal button at the button/Person No).
Please provide me with the complete path and guidance.
Cheers
Deepal

Yes Deepal
It is required to maintain the HR data for linkage.I thought you already have Master data in the system.
By the TCODE PA30 u need to maintain the personnel data before it is available for assigment.This is related to HR module
Regards
Jignesh

Similar Messages

  • Change log for work center data

    Hi,
    I was looking for the table where the change header document for the work center is stored.I was able to find a transation CR10 which shows the changes and also the database table CDHRD.
    When I am trying to view the changes that were made to the work center I find that the data does not exist in the tables.
      I was curious to know this as for some transaction the data is being logged in their respective change table but not for Work Center changes.
      Can anyone tell me as to why this is happening.
    What I think is that some changes to the configuration are required in order to log the changes in the database.
    Kindly help.
    Regards
    Varun

    Hi Wolfgang,
    Thanks for the information.
    However i have another question.
    The change table will have data only when it is activated in the configuration menu.
    However is there any other way by which we can capture the previous data for the work center e.g. the changed by field. I want that the names of the users who has changed the wrok center currently and the name of the person who previously made changes to it.
    See if you can help me on that.
    Regards
    Varun

  • Assigning HR persons to work center

    hello
    What is the diffrence between assigning HR persons to Work center and assigning HR persons to capacity of work center. And what is the impact of these 2 assignements to capacity planning in activities in PS?
    THX

    hello
    I have been still reading docs for this topics. Now yes you are right there are 2 places for adding HR to work center. As I have read there is a reason for this.
    If you add HR to work center you will add people to work center indirectly. Now I'm not sure yet if I should add HR work center to work center and then add people to capacity in addition. But I will check it soon.
    And the second way is to add people from HR to capacity directly.
    The benefit for this second way - directly to capacity - is you can use capacity of added to work center people as standard capacity of this work center.

  • Customization Setting for Work center creation

    Dear all,
    What is the Customization Setting for Work center creation? How to do it?

    Hi,
    Here are the few things you can check
    OP40 : WC category
    OP17 : Formula for WC
    Person responsible : Plant Maintenance and Customer Service >> Maintenance Plans, Work Centers, Task Lists and PRTs >>Work Centers >>Define Employees Responsible for Work Centers
    apart from above You can explore more in
    Plant Maintenance and Customer Service >> Maintenance Plans, Work Centers, Task Lists and PRTs >>Work Centers
    Riyaj

  • ALE/iDoc for Work Center data transfer

    Hello, community.
    I am working on several interfaces for the PP and PM modules using iDocs/ALE.
    One of the requirements is that only created and modified data must be distributed from R/3.
    For Work Centers, we are using basic type LOIWCS02 and message type LOIWCS. We are generating iDocs through transaction POIM, which has two transfer modes: Complete (data for all Work Centers etc.) and Change (only new and updated data).
    The Change Transfer Mode assumes you have set both Change Pointers and Change Documents for the objects to be transfered. Otherwise, it'll work just like the Complete Transfer Mode.
    Our PP consultant told me there is no configuration to generate Change Documents for Work Center data modifications.
    Can anybody give me other opinions? I'll resort to Z-table solutions only if I have no other options.

    Hi Danilo,
    Do you know what the process codes are for
    LOIWCS and LOIROU ?
    Appreciate your help.
    Thanks,
    Gopi.

  • User Exit or DB-Table for Work Center (CR01)

    Hi!
    I have an external software which must be triggered when the user changes a work center in SAP (transaction CR01,CR02). I was looking for an user exit to do what ever is necessary but I couldn't find one.
    So, does anybody know an user exit or BADI for work center?
    Also possible:
    The database table where work center are stored. So I could poll against this table and check if a work center was changed. I found the table SGOSHIST which log all modified objects in SAP. So this could maybe used to check for modified work center, I think.
    Thanks,
    Konrad

    > You can check the BADI definition from transaction SE18,
    > 'LTRM_WORK_CNTR_DTRM', this might be helpful,
    How can I check this BADI. If I use SE18, it doas not exist, buit if I try to create it, the system tells me that it already exists in the SAP Original System... and asks me if I want to create a copy of it! I don't know what to do at this point!
    > Work center details are avilable in CRHD table, you can
    > look for CR* from SE11 transaction,
    I know, but if you change the description of the work center, it is stored in CRTX. there are a lot of CR* tables. It would be helpful to have a table which is updated every time a work center is modified!
    Thanks,
    Konrad

  • Tables for routing (for work center)

    hi friends,
    I am doing report on routing but i did not get value for work center i got tables CRHD CRCA CRCO CRHH CRHS CRTX KAKO KAZY .
    i try to get result by using link with PLPO and PLKO.
    in TCode CA03 when i see the technical attributes it stors the dat ain structure PLPOD but i am unable to use it.
    kindly can anybody tell me how to work center.
    thanks & regards
    Bhupinder Singh Kaler

    Hi Bhupi kaler,
    try to link CRHD and PLKO with WERKS ( Plant ) field ane get the ARBPL ( Work center ).
    Best regards,
    raam

  • How to assign a person to work center

    Hi All,
    Can you please let me know how to assign a person to work center?
    Regards,
    Nima

    Dear Nima,
    what is the exact query
    Go to
    Spro > Production > Basic data > Wrok center > determine person responsible
    click new entries & create
    Go to CR01, Basic data tab & in the field person responsible press F4 you can get
    List created in the above Spro
    Regards
    Madhu

  • Standard IDOC for WORK CENTER Master

    Hi,
    Please suggest the standard IDOC for work center master.
    I have tried PWKC.Got  DUMP when executed.
    Tried on SAP-Market place for help.Suggested not to use PWLC.
    Please suggest alternative.

    Will you please explain in a bit detail if LOIWCS01 or LOIWCS02 are transaction (as i tried to execute) or programs or please explain how to use these.(I executed from command prompt and SE38 but didnt helped)

  • Table for work center..........

    Hi
    Is there any table for work center which shows available capacity v/s utilized capacity......Please revert with your valuable comments
    Rgds

    Hi,
    Check Table RC65L.
    Regards
    Kannan

  • Number Range for Work Center

    Hello All
          Am having a little concern regarding the number range for Work Center, kindly let me know where the number range for Work Center is maintained or from where it is picked up when we are using external no range assignment for Work Centers.
    Regards,
    J K Tharwani

    Thanks Sir for your reply,
            Actually the requirement is the client want that Equipment number must be the same as the Work Center Code, and Work Center code which i have decided is something like 0101001 & if i give the external no to the Equipment then the system doesnt take the same number instead it takes 101001 i.e. it ignores the initial "0" in the work center code. Actually I wanted to see the no range from where the work center numbering is being picked up, but later on i came to know that there is no such no range setting for work center instead it has contol from no range for object type. Shall look forward to your valuable inputs & guidance.
    Regards,
    J K Tharwani

  • CNR2-assign person to work center error: the cost center is deleted

    Hi guys,
    i have a problem with assigning a person to a work center using CNR2.
    i select the person and i add it but when i hit SAVE i get this warning message:
    "RP718: a segment could not be derived". the person will then be allocated to the work center BUT when i check in PA30 i can see that the persons cost center is DELETED :O.
    could you please help me with this? i tried a  lot of scenarios but i could still not find the answer.
    thanks,
    emi

    Hi
    Cost Center must be maintained for that person in HR master data. Please have your HR person look into this and maintain the data and try again. Cost center and Atype of that person would bring in actual costs (equivalent of hours) on the receiving objects when time sheet is being recorded.
    Regards,
    PSR

  • Capacity planning for Work Center

    I programmed time for a Work Center on internal activity, for 40 hr using 100% of one resource, the work center it has  a capacity of 8 hr each day, the activity gets a duration of 5 days and I indicated that it has to begin the first day of the next month.
    When I executed transaction CM01, I notice that the 40 hours are planned for the actual day and don´t respect the dates of the internal activity, I think it is a problem with the work center but do not find the error.
    Any suggestion where to look for?
    The data used for creating the Work Center on Capacities:
    - Capacity Category : 002 Person
    - Other formula: SAP008
    The data used for capacity:
    - Base unit of meas.:H
    - Start: 08:00:00
    - Finish: 17:00:00
    - Capacity utilization: 100
    - No. of indiv. cap.:1
    - Unit: H
    - Relevant to finite scheduling: active
    - Can be used by several operations: active
    - Long-term planning: active
    The data used for creating the Work Center on  Scheduling:
    - Capacity Category: 002 Person
    - Other formula: SAP004
    - Work dimension: Time
    - Work unit: H
    Best Regards...

    Hi,
    Please activate the capacity requirement in Capacity tab in CNR2.
    Thanks..

  • How to find the reporting for work center machine wise

    hi gurus
    My question is . In one work center machine capacity category 2 machines are used. Client is asking the report machine wise. i.e as 2 machines are available .What is the capacity utilisation for each machine.Provide me the information for this. Thanks in advance
    kalyan

    Hi Kalyan
    you have to make some settings in production order & work center first.
    In work center capacity header ,you have to make indiovidual capacities as 2.
    In the same capacity header screen by going through the menu Goto--->individual capacitities  define these different individual machines.
    In the production order operation detail screen goto " capacity reqmt assignment " assign the quantities for different work centers.
    Adfter this in the confirmation CO11N you have to fill the split field accordingly& confirm different wortk centers seoperatley.
    Then you can the report in the CO14 for diferent work centers.
    you try this.
    Regards
    YMREDDY

  • LSMW for Work center text

    Hi Experts,
    Im developing LSMW to upload the Work center text(TCode CA10).
    I did tried on Direct input -> program /SAPDMC/SAP_LSMW_IMPORT_TEXTS in LSMW. The uploading process was done successfully but it <u>can not</u> be used in Master Recipe assignment(TCode C202). Reason due to the direct input program doesn't has <u>Work center short text</u>. FYI, the Work center short text is entered during the Work center text creation via CA10 first screen.
    And i did tried on CA10 manually, work center text only <u>can be used</u> in TCode C202 when it is created <u>with short text key in at CA10 first screen</u>. While for the Work center text that created <u>without</u> short text key in, system will prompt <u>error</u> when i try to assign the Work center text into C202.
    Thus, i may need you advice. In LSMW other that direct input,is there any BAPI or IDOC available for the Work center text upload?
    Please comment.
    Thanks in advance.

    Hi SKK,
    Thanks for you reply.
    I did tried on FM SUBMISSION_PROCESSING, and found:
    It is being trigger online, whereby i need to key in the text manually.
    Since my requirement is mass upload, hence that is impossible for me to execute the FM to key in the text manually.
    Do you know there is any other FM/BAPI/IDOC that can perform the <u>Work center Short and Long text</u> in background mode?
    Please comment.

Maybe you are looking for

  • In ALV: Subtotals for every month, not for every day, possible?

    Hello, in my Alv-Grid I have a date column, which I want to use to generate subtotals. But I don't want to have a subtotal for every date, but for every month. Is there a method to accomplish this with subtotals? Thanks. Regards, Lars.

  • I am trying to do the iChat video chat

    I have been trying to do the video chat ever since i got the computer, and it seems that every time i try it, it will either not let me get on or once i get on and get a chat invitation it will sign me off. The very few times i have gotten it to work

  • Error message halfway through "Consolidate Library"

    I have iTunes version 9.0.3.15. I tried to consolidate my library by going to "File -> Library -> Organize Library ..." and ticked the "Consolidate Files" box. When I run this, it gets partway through my library until it says "Copying files failed. T

  • SQL Query - Report on multiple table

    Hi Experts Firstly, I am an amateur at generating SQL Queries! I am trying to create a Report of All Invoices/Credit Notes generated in a date range combined with all open Sales Orders. This is my attempt - I am getting all Sales Orders but only want

  • Group information lost after NW7.0 restart

    hi, I have created some groups in the netweaver 7 user user managerment console. and added some users to the groups, but when i restart the server ,the users is lost ,the groups come to empty. what's reason for this . how to resolve it. thanks