PIR and Production Orders

Hi all,
X product's strategy is 40 and it has 20 production orders, seen in MD04. In MD61 i have entered 40 PIR. In MD04 i want to see that 20 production orders and 40 planned orders after MRP run. But MRP run creates 20 planned orders. It creates PIR with VSF. I tried strategies 50 VSE and 10 LSF but it has no effects. How can i plan as told above?
Regards,
techmaster

Hi
There is no strategy with out considering Production orders.
strategy 11 will be used with out considering the stock.
refer below link
http://help.sap.com/saphelp_47x200/helpdata/en/cb/7f9b7043b711d189410000e829fbbd/frameset.htm
Regards,
srihari

Similar Messages

  • Open planned orders and production orders

    Hi friends,
    I have one issue with my client.
    Client has 1 lac materials in sap .Now he wants extract all materials open planned orders and open production orders with quantity and dates.
    Please tell me the process how i can extract the data from sap for above requirement.
    Thanks,
    Manoj

    Hi Manoj,
    For open planned order and production order select the respective box.
    But one suggestion. Try to convince client that this report will take a lot of time as you have mentioned 1 lac materials are there.
    You can exclude system status and get it with below screen as mentioned already.
    But my suggestion is to run the report at night when the system load is very less. Please create a background job one for planned order and another for production order. Then run it in midnight as per the customer requirement in background. You can automate the process by sending automatic mail to customer. Please refer the below link to trigger mail.
    Mail Trigger with TEXT file via JOB run
    Regards,
    Krishnendu.

  • How to compare sale order bom and production order bom.

    i would like to provide report with respect to comparation of sale order bom and production order bom, but i am not familiar with SD and PP, can anyone give me some clue? i only know sale order bom is created via 'CS61', afterwards run mrp to get production order, the process appears complicated, i needn't know the process detail, just want to know how to get sale order bom and relative production order bom. please guide me.

    Hi,
    Check Tcode:CS14 to SD/PP BOM's
    Chidambaram

  • Link between Purchase Order and Production Order

    Hi,
    Could some one tell me how i could get a relation ship between Purchase order and Production Order after a Good receipt is done. Coz after a GR is done I am not able to see the production order for a particular material in MD04 transaction.
    Thanks,
    Arul.

    Hi Arul ,
    i think u may not get the LINK b/w Production Order and PO , Bcos--->
    check the process --->
    RUN MRP , here System will generate the Production Plan and PRs( based on the avail.of that Raw Material).So PO will be generated by PRs.So I think there is no link b/w Production and Purchase .
    this is based on the my system settings and my knowledge.
    Regards
    Prabhu

  • Any stanard BAPI have both sales order and production order

    hi Experts,
    i need to Identify any standard BAPI have both sales order and production order. If such BAPI is not available, create 'Z' BAPI to do the same.it's my require ment?plz give me suggestion it's useful for my project. i will give good points.
    thanks and regards,
    bbm

    hi eswar,
    can you give me how to do? and what i can use import,export,table and sourcecode bcz i am new in BAPI side even now i am working in SAP XMII project.
    so plz guide me.
    thanks and regards,
    bbm

  • BOM and Production Order: Multiple Inputs to Multiple Outputs

    Dear All, My client's industry required BOM and Production Order must be Multiple Inputs to Multiple Outputs. We propose to create customization program to work on it but client do not want any customizations. Any suggestions? SAP B1 8.81 PL13 Thank you very much in advance. Best Regards, Vivian

    Hi,
    Please advice your requirement with an example. There is possibility to input multiple components to produce single finished product.
    Not sure you have checked with SAP help file. If not refer SAP help file and below blog.
    http://scn.sap.com/community/business-one/blog/2014/03/01/how-to-implement-production-in-default-sap-business-one
    Thanks & Regards,
    Nagarajan

  • Varaince settlement and costing sheet in REM and Production order

    for REM, repetetive manufacturing, what's the difference between REM and production order in terms of variance settlement and settlement profile design? what's the difference between process order and production order in terms of variance settlement and settlement profile design?
    for actual overhead(fixed and variable), can it be calculated automatically by costing sheet? user is very angry to input actual overhead by jounal entry. also how about plan scrap, how to define it in configuration? besides order confirmation, where can I input actual scrap?

    For variances, there is no difference between the 3 diferrent orders. The settlement profile can also be the same.  The real difference from a CO perspective concerns the calculation of WIP and the settlement rule.  Process orders and production orders normally use a full settlement rule (though periodic settlement is also possible) and WIP is calculated based on actual cost.  Repetitive orders only use periodic settlement and WIP is valued at target cost.
    From an overhead perspective, there is no difference between the 3 types of orders.  Overhead sheets are assigned through the costing variant and costs are applied through period-end process. 
    Plan scrap is maintained in master data, either in material master, routing (receipe for process orders), or bill of material.  Acttual scrap usually happens based on the quantity of components issued to the order during confirmation or by the amount of scrap reported during confirmation.  If you are backflushing components, as you normally would do for repetitive, then you can adjusted the consumed quantities by doing an additional goods issue to the order (movement type 261).
    thanks,

  • How BOM and routing is selected for Planned order and Production order?

    Hi,
    Can any1 plz tell me how BOM and routing is selected for a planned order and production order. ?

    Hello Mathisuthan,
    BOM and Routing selection for the planned order and production order through production version, If u have more than one BOM and more than one Routing then u can maintain this information as Production Version in the system.
    Production version you maintained
    MM01/MM02 -- MRP4--- Production version
    Or you can create Production Versions in Mass also with Transaction Code "C223"
    In the case no production version maintained/created  for the material, then system by default  will pick the first BOM and routing.
    I hope this information helpful to you.
    Regards
    Umesh Mali

  • Settlement of Cost Center And Production Order Variance

    Dear All
    I have just started to learn SAP Controlling. I am able to get hold of  some materials on Controlling. May I request the experenced forum memebers to please explain the following
    1. How data flows from FI to CO and PA
    2. When cost center and production orders are settled, how the variance are settled and which accounts/ modules get effected
    and a source where I can get some material on this topic. Your immediate replies  and valuable peice of advice will help me a lot
    Thanks
    Arvindh

    Dear All
    I have just started to learn SAP Controlling. I am able to get hold of  some materials on Controlling. May I request the experenced forum memebers to please explain the following
    1. How data flows from FI to CO and PA
    2. When cost center and production orders are settled, how the variance are settled and which accounts/ modules get effected
    and a source where I can get some material on this topic. Your immediate replies  and valuable peice of advice will help me a lot
    Thanks
    Arvindh

  • Relation between Sales order and Production order

    Hi,
    In Make to stock scenario how the relation between Sales order and production order are related.In which table we will get the related fields (expect AUFK,VBAK,AUFO).
    warm regards,
    Surendar reddy.

    The relation between sales order and prodution order  is as follows.
    Pass AUFNR to AFKO/AFPO  Get AUFPL.
    Pass AUFPL to AFVC Get BANFN.
    Pass BANFn to EBAN Get EBELN.
    Hope this works .
    Cheers,
    Lakshmi Prasanna Gandham

  • List of Sales order and production order

    I need the list of sales order and production order for the period 01.04.2006 to 31.12.2006

    Dear Nau,
    VA05 for list of sales orders and put Document date in Sales Order Data
    COIO Process order information System
    Regards,
    Rakesh
    Pls award points if you find the solution

  • Report on rawmaterials and production order

    Hi ,
    Is there a report which has a list of " issue of raw materials to a production order"?
    Or how to create a query for this?
    Thanks,
    Sai.

    Hi,
    Use T.code CO03 and enter production order number & hit enter,then Goto Menu GOTO-->Click on Doumented Goods Movements.
    Or
    Use T.code MCRE and enter plant and production order & Execute.
    click on switch drillwon ikon(F7) and you analyse by component.
    Thanks,
    Rau

  • Difference between process order and Production order

    Hi Experts,
    Can any buddy tell me the difference between process order and production order. Why process order is used for process industries. Why do we use recipe for it and routing for production order ?
    Regards,
    Amit

    Hi Amit
    There is a difference between production order and process order.
    Supposing a 10,000 lit tank is being manufactured in discrete manufacturing. You have to follow the necessary routing steps and can make by physically seeing its development stage by stage. For this type production you can have a production order.
    In case of process of order if some chemical in a reactor is loaded with intial temp of 30 C and need to be heated to 80 C then there is phase change. Hence we use Heating as an operation and the change of temp is phase. For such type of process we process order.
    Hope this is useful. Pl reward.
    Nanduri

  • Scheduling Parametrs for the Plant and Production Order Type

    hi SAP Gurus,
    Pls it is very urget
    Pls let me know how to maitain the Scheduling parameters for the combination of Plant and Production Order type.
    Pls provide me the Path also.....
    Points will be rewarded .....
    Ranjit Kumar

    hi Murthy,
    thanks for the solution... Problem resolved.
    Assigned points...
    Ranjit

  • Class for Purchase order item components and Production order components

    I'm looking for a some classes.   I'm very new to objects, so I could be searching for them incorrectly.
    The first class I'm looking for is a purchase order class that contains the item components.  I've looked at CL_PO_ITEM_HANDLE_MM and CL_PO_HEADER_HANDLE_MM.  I couldn't find components as a part of either of the classes.
    The second one I'm looking for is not as critical.  It is for the components for a production order.   I have a function module: BAPI_PRODORD_GET_DETAIL that gets the components for the order.  However, to take advantage of objects - I read somewhere - that if possible I should avoid calling a function module.
    Any help that you could give would be greatly appreciated.
    Thank you!
    Michelle

    Hello Michelle
    I do not think there are already classes available on ERP 6.0 for reading production order (yet I might be wrong...). However, regarding purchase order you are already on the right track.
    *& Report  ZUS_SDN_OO_READ_PO
    *& Thread: Class for Purchase order item components and Production order components
    *& <a class="jive_macro jive_macro_thread" href="" __jive_macro_name="thread" modifiedtitle="true" __default_attr="1206523"></a>
    "& NOTE: Coding adapted from BAPI_PO_GETDETAIL1
    REPORT  zus_sdn_oo_read_po.
    TYPE-POOLS: abap, mmpur.
    PARAMETER:
      p_ebeln   TYPE ebeln  DEFAULT '3000000045'.
    DATA: gs_document    TYPE mepo_document,
          go_po          TYPE REF TO cl_po_header_handle_mm,
          gs_header      TYPE mepoheader,
          gd_tcode       TYPE sy-tcode,
          gd_result      TYPE mmpur_bool.
    data: gt_items       type PURCHASE_ORDER_ITEMS,
          gs_itm         type PURCHASE_ORDER_ITEM,
          gs_item        type mepoitem.
    START-OF-SELECTION.
    *  prepare creation of PO instance
      gs_document-doc_type    = 'F'.
      gs_document-process     = mmpur_po_process.
      gs_document-trtyp       = 'A'.  " anz.  => display
      gs_document-doc_key(10) = p_ebeln.
    *  object creation and initialization
    **  l_ebeln = purchaseorder.
      CREATE OBJECT go_po.
      CALL METHOD go_po->po_initialize( im_document = gs_document ).
      CALL METHOD go_po->set_po_number( im_po_number = p_ebeln ).
      CALL METHOD go_po->set_state( cl_po_header_handle_mm=>c_available ).
    *  read purchase order from database
      gd_tcode = 'ME23N'.
      CALL METHOD go_po->po_read
        EXPORTING
          im_tcode     = gd_tcode
          im_trtyp     = gs_document-trtyp
          im_aktyp     = gs_document-trtyp
          im_po_number = p_ebeln
          im_document  = gs_document
        IMPORTING
          ex_result    = gd_result.
    *  there was a problem in reading the PO
      IF ( gd_result EQ mmpur_no ).
    **    l_messages = l_handler->get_list_for_bapi( ).
    **    PERFORM return TABLES l_messages return
    **                          poitem poschedule poaccount.
    **    CALL METHOD l_po->po_close( ).
      ELSE.
        gs_header = go_po->if_purchase_order_mm~get_data( ).
        WRITE: / gs_header-ebeln,
                 gs_header-bukrs,
                 gs_header-bsart,
                 gs_header-lifnr.
      ENDIF.
      gt_items = go_po->if_purchase_order_mm~get_items( ).
      LOOP AT gt_items INTO gs_itm.
        gs_item = gs_itm-item->get_data( ).
        write: / gs_item-ebelp,
                 gs_item-matnr,
                 gs_item-menge.
      ENDLOOP.
    END-OF-SELECTION.
    Regards
      Uwe

Maybe you are looking for

  • Customer service knolwedge is critical in order for me to consider giving you my money

    Dear Verizon, There's no substitution for a knowledgeable person. I have been experiencing sub standard internet service from my current provider, not Verizon. Being that I live in an area with very few choices for brand band service, one of them not

  • ISE Wired guest portal redirect even after authentication

    Hi I have configured both Wired and Wireless guest authentication via guest portal. Wireless is working fine, however the when trying with Wired, the redireciton page is keep getting even after user authenticated. I'm not seen the redirection authori

  • Can't view pdf

    I recently had to update Acrobat Reader. Now I can not open any PDF's in Safari that are linked to a website or email. I just get a black page. The problem seems so simple but can't seem to figure out a solution. Baffling!

  • How to trigger a event from simplet gui ?

    I have a very easy mainGUI whi extends JFrame           JPanel pnl = new JPanel(); Container guiFlate = getContentPane(); guiFlate.setLayout(new BorderLayout()); guiFlate.add(pnl, BorderLayout.CENTER); setSize(300, 300); setVisible(true); setBackgrou

  • What does AM do with Attribute Assertions

    Hi, I am sending Auth statement and atribute statement assertion to AM. AM is accepting the Auth assertion and creating the session, but I am not sure what it does it with Attribute assertion? I want to pass these attributes to next AM. How can I do