Plan order poblem while creation

Dear All
I have created Planned Independent Requriement in MD61.requirment type is VSF planning time in month
Then I run MRP in MD02, but it only showing ind requirment but not plan order against that.
Regards
Shrinivasan

Dear,
Mrp type X0 means the material is relevant for APO and its planning is to be done in APO and not R/3
So you will not get planned order in R/3.
Preferred MRP type is PD & VB
Please come back if any query.
Regards,
R.Brahmankar

Similar Messages

  • System status is closed (internal order) error while creation F110 proposal

    Dear All ,
    During creation of F110 proposal, the system checks the internal order status of open items. In case of the statu of internal order is CLSD, the stystem does not allow to create proposal . We change the statu of internal order as CLSD, because we do not want to post any expense posting to that internal order .
    Is there a way to create the proposal although internal order statu is CLSD ?
    Thanks,
    Best Regards
    Dash

    Hi,
    You have to re-open your order and create a proposal.
    Regards,
    Eli

  • Error In Service order Quotation while Creation Follow-up

    Hello All,
           In facing an error while creating a follow-up in service order Quotation in CRM WEBUI .
    Business Server Page (BSP) error
    Error as Follow
    What happened?
    Calling the BSP page was terminated due to an error.
    SAP Note
    The following error text was processed in the system:
          Message E PRC_MESSAGES_EXT 320 cannot be processed in plugin mode HTTP
    Exception Class     CX_SY_MESSAGE_IN_PLUGIN_MODE
    Error Name     
    Program     CL_BSP_WD_VIEW_MANAGER========CP
    Include     CL_BSP_WD_VIEW_MANAGER========CM002
    ABAP Class     CL_BSP_WD_VIEW_MANAGER
    Method     DO_REQUEST
    Line     43
    Long text     -
    Error type: Exception
    Your SAP Business Server Pages Team
    Thanks in advace.
    Regards,
    Kiran Posanapalli.

    Hello,
    I don't have an answer for you but maybe this helps you in finding one
    The message class PRC_MESSAGES_EXT is used for IPC error messages.
    Maybe you have errors in some IPC java user-exits?
    Hope this helps,
    Kind regards,
    Joost

  • Tcode CM25:BDC or function module to dispatch planned orders

    Hi all,
    Could you please suggest a BAPI/FM for CM25 -dispatching the planned orders.
    While i try BDC, it requires the line selection for dispatch,which does not get captured in recording.
    Can anyone throw light on this or suggest any alternative.
    thanks
    kiran
    Moderator message - Cross post locked
    Edited by: Rob Burbank on Oct 23, 2009 11:28 AM

    reposting it

  • Multiple number range for planned order

    Hi,
    I want maintain different number range for MRP related planned order and manual creation planned orders. I have checked OPPQ and OMI2 transaction but i could not get any clue to create different number range for same plant. Let me know is how we can create.
    Regards / US

    Hi Uma,
    number range is dependent on plant alone and I don't think there is an user exit or badi to change number range at planned order creation.
    I guess the alternative is an enhancement or using some other field to determine what planned orders are manual.
    regards,
    Edgar

  • Prod Version Slection during conversion of planned order to production orde

    Dear Experts,
    I have two BOM for a semi finished product. I have created two production version for the same. After MRP run, it created planned order for BOM1.  This is fine.
    My requirement is, when I convert the planned order to production order, it should ask for selection of production order as it ask while creating the production order using CO01. I know that I can select the alternate prodution version by reading the PP master data. Can system ask for selection of production order while converting the planned order to production order.
    Thanking You,
    Chetan

    Dear Chetan,
    If you have manual selection of production version set in OPL8 and if you have set the BOM selection method as 2 in
    MRP 4 view of the material master then,
    1.If you create a production order manually then the system displays the pop up to select a production version.
    2.If you are converting the planned order into a production order then it picks up the one which is
    present in the planned order.So obviously if 2 production versions are there with same lot size and
    validity dates,then the system picksup the first one only during MRP run.
    Even if it picks up the first prod.version in planned order,but while converting click on master data and
    change the production version if required.
    3.Otherwise what you can do is set the production version in MD61 itself ,so that its going to be
    considered during MRP run.
    Check out and revert back.
    Regards
    Mangalraj.S

  • VC while creation of Planned Order / Production Order

    Dear All,
    Can we Configure Planned Order or Production Order Just Like Sale Order.
    in CO01 / MD11,
    Is it Possible ? If Yes HOW?
    Thanks
    Regards
    Ravi

    Dear,
    It is not possible in standard SAP R/3. Because it is MTO scenario so you need to create sales order first then production order.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • BOM Selection Mandatory while creation of Production Order

    Hello Friends,
    I would like to know that is there any option other than production version which makes it mandatory to have valid BOM must for creation of Production order / coversion of planned order to Production order.
    I have tried with Production version option but it doesnt throw any error in case BOM with inactive status has been selected in it & also Production order gets created & released.
    Before going for user exit / enhancement option, I just wanted to ensure that it is not possible with standard SAP.
    Kindly share your views on the same.
    Your urgent replies will be highly appreciated.
    Regards,
    Tejas

    Hello Tejas,
    I think this is standard SAP Behaviour.
    Try with following exits:
    PPCO0018
    PPCO0012
    Also check out the following link:
    [How To Make BOM Mandatory while creating Production Order;
    Regards,
    Vinod

  • Planned order creation problem

    Hello everybody,
    When I am creating a planned order manually in MD11, I receive the message "Planned order xxxxx will be created".
    Then I receive a popup window telling me "Express document 'Update was terminated' ".
    But, when I am having a look in MD04 to see the planned order, I can't see it.
    It was still okay yesterday morning, but since yesterday afternoon, no more planned orders can be created manually. Do you have an idea about what can be the reason of this?
    It's just like if the order creation was delayed... But for how long, and waiting for what???
    Thanks in advance for your help.
    Regards,
    Rudy

    Hi,
    There is something issue with ur data while saving..hence it is not saving and throwing the message. so that while upadting data in table  is not acccepting.
    GOTO SM14->click on ALL UPDATEREQUESTS push button->U will find the reocrds,select ur userid and double click on it,now u can see the module name,select it and double click on it,now u will get one small dialog box,there u can find the abap editor symbol ,click on it..it will take u to the program where it has taken place
    Please refer this thread,
    Update was terminated
    Regards,
    R.Brahmankar

  • Prevent Planned orders creation in Sourcing Org

    Hi,
    We have a customer requirement as below:
    Supply Chain : Org1 <-- Org2 <--Org3
    Item Name: X
    Item X has demand in Org1 procured from Org 2 by Sourcing "Transfer From"
    Item X in Org2 has planned order demand which triggeres a Planned Order in Org2 and to be procured from Org 3 by sourcing type "Transfer From" and it will create a Planned Order in Org3 which has sourcing "Buy from" External supplier.
    Org1 : Sales Order -->Planned Order1 for Item X
    Org2: Planned Order Demand2 -->Planned Order2
    Org3: Planned ORder deamand3-->Planned Order3
    Planners are different for Org2 and Org3 wan to do releases indivudually on their own schedules.
    Planner in Org2 want to ensure Planned order3 in org3 not to be released earlier than ISO creation in Org2 for item X.
    How to prevent planned order creation in Org3 having transfer planned order from Org2 to org3 for ISO creation.
    Need your valuable inputs.
    Regards,
    Kumar Kancherla

    Hi Kumar
    If I understand your question, the requirement is not truely about Planned Order Creation but releasing a planned order in Org3 before ISO is recieved in Org2 from Org1?
    This is more of a business process issue than planning since plan will provide a replenishment suggestion when there is a requirement based on sourcing rule. I'm assuming that these 3 orgs are planned in single ASCP Plan.
    One way to enforce this business process is by using "Auto-Release within Time Fence". Since lead times for Item X will be longer in Org1 vs. Org2 and Org3, planned order in Org1 will be released first triggering Internal Req/ ISO between Org1 & Org2 first and then between Org2 & Org3. While this may be OK if you plan to implement all suggestions from ASCP without manual intervention, it may not be acceptable to some planners who may want to control the release process manually.
    You may try it out with a limited set of items initially before rolling it out for all item/ orgs.
    I re-iterate that this issue is more of a discipline that planners need to use their discretion and due diligence to collaborate with other planners to ensure that lower level supplies are released only after a firm demand is released from higher level.
    Please feel free to let me know of any further concerns in this respect.
    Thanks
    Navneet

  • Error while creating a Planned Order

    Hi SAP Experts,
    I have an error encountered while creating a Planned Order which is "Mode linkage problem with mode number".
    Diagnosis:
        An application program called an LCA routine and the following error occurred:
        An order has at least one condition with mode linkage with the same mode number. The activities of this condition must have compatible modes. The modes are compatible when each mode of one activity has a mode for the other activity with the same mode number. The first activity that violates the condition is given in the return code table in ABAP.
    Please enlighthen me what is this error and what should be done to this error.
    Thanks in advance,
    Raymond

    Check the PPM or PDS being used in the Planned Order.
    Most likely you have a Setup Activity followed by Produce Activity. However the Mode (i.e. Resource) used in the two activities are different. The same Mode needs to be used both in Setup and corresponding Produce activity.
    Hope this helps,
    somnath

  • Sales order need to be blocked for delivery while creation

    Hi experts,
                    My requirement is to block sales orders for delivery, for the selected distribution channels, and for selected countries while creation itself, so for this I came to known that a program MV45AFZZ include, here in this at which form can I write code to block SO for delivery. and is it enough to put a reason in the field LIFSK in VBAK table to block SO for delivery.
    Thanks in advance
    Regards
    SriNivas........

    Hi,
    You can use form routine USEREXIT_SAVE_DOCUMENT_PREAPRE of user exit MV45AFZZ to update the delivery block.
    MOVE '10' to vbak-lifsk.                    "13 is the reason for block in header"
    MOVE '10' to xvbak-lifsk.                  "13 is the reason for block in header"
    Use following code to update delivery block at item level
    MOVE '10' to vbep-lifsp.                      "13 is the reason for block in item schedule line"
    MOVE '10' to xvbep-lifsp.                    "13 is the reason for block in item schedule line"
    Regards
    Vinod

  • APO: RRP3 automate Production order creation from planned order ?

    Hi everyone ,
    I have got a business requirement in APO where in Open sale orders uploaded in R/3, needs to be converted to Planned order and subsequently to Production order in APO-PPDS tcode RRP3 at all stages. They want to automate this process rather than doing it
    manually.
    Can anyone tell how is this possible . Any BAPI or function module available to do this . Please help.
    Regards,
    Syed

    Hi,
    1.You need to run the heuristics Planning of standard lots SAP_PP_002  in /SAPAPO/CDPSB0 by specifying the time profile
       and  strategy profile, planning version and propagation range, product and location.
    2. Convert PPDS Planned Orders created to process orders thru /SAPAPO/RRP7 by specifying the product location start date of the order for production order creation.
    Out put of step 1- For sales order requirement, PPDS Planned orders gets created.
    Out put of step 2- PPDS Planned orders are converted to production orders.
    Thanks,
    nandha

  • Error while creating manual planned order in apo

    Dear expert
    While I am creating manual planned order i am getting error as message /sapapo/rrp251
    Every thing is correct BOM and PV's no error after consistency check and it getting succesfully transffered to APO and it is also visible in APO
    But while creating manual planned orders planned order are not getting generated  I am using BLock planning with PPDS
    Please help How to resolve it
    Regards
    Virender

    Hi
    The error message /SAPAPO/RRP251 - Error occurred while creating order means While creating an order, the system encountered problems, such as, for example, no available components or components that are available late, orders that could not be scheduled, and so on.
    I think system attempted to solve the availability problems by using alternative procurement options. This was not successful. The order could not be created. Check the exceptional situations in the planning protocol, under Goto -> Planning log, and deal with the causes of the exceptional situations if this is possible or necessary.
    Thanks
    Amol

  • Error while creating planned order in product view

    I am getting following error when I try to create planned order for a product in a Location  manually in product view using /SAPAPO/RRP5.
    Error occurred while creating order
    Message no. /SAPAPO/RRP251
    I checked the product and resource. Everything looks good.
    Block is available in the resource WMP1_2041_001 for characteristics specified in planned order.
    Product master and PDS look good.
    In the planning log, I see the following error message.
    Plan explosion failed for product LBRA1050-661 in location 2041
    Message no. /SAPAPO/RRP718
    I have not found SAP notes for above error.
    Can you pl let me know what this is due to?
    Thanks,
    Srini

    Srini,
    The message was created as a result of several notes, such as 1582997.  There are others.
    The implication is that you have an invalid source somewhere in your BOM.  Maybe a bad component part, maybe a bad transportation lane, maybe an invalid BOM, or maybe a bad PPM/PDS.
    If you can't find the problem using logical troubleshooting steps, have one of your programmers debug.  Have him put breakpoints in FM  /SAPAPO/RRP_PLORD_CREATE .  If you are particularly lucky, you will find a developer that understands German, because all the internal comments in this FM are in German.
    Best regards,
    DB49