Hi
I want Plan Order quantity in z report.
Please help how I will get from system.
I required table & field name.
Regards
ARK

Dear Ashish,
No
This is not possible
Once the plan order is deleted you can not get in any table and
Also once the plan order is partially converted to process order then only remaining qty will be stored in PLAF table
PLAF is only table for plan orders as plan orders are not confirmed receipts
Only in initial stage when plan order is created with the quantity then it appears in PLAF
Once you start converting partially then the remaining qty gets updated in PLAF
Regards
Madhu

Similar Messages

  • Original Planned order quantity

    Hi,
    I want to capture the planned order quantity. Since planned order quantity is dynamic, I cant able to capture the original planned order quantity.
    Eg: After running MRP, system gives a planned order 001 = 10,000 pcs.
    When I convert this planned order in to partial order. Partial order quantity = 1000
    Now system shows remaining planned order is 9000 pcs.
    In which table system will store the original planned order quantity of 10,000 pcs. I tried in planned order table PLAF. The field total planned order quantity (GSMNG) is dynamic. It shows the current planned order quantity only.
    Question:
    1. Is it possible to find original planned order quantity?
    2. If yes, then from which table we can see that.
    Regards / US

    MD05 info cannot be directly read from a table in a meaningful manner unless you have setup the same to be a transparent table. So to read the info you will have to use - BAPI_MATERIAL_MRP_LIST
    But I believe a better approach for your need would be to read the planned order & planned qty. from AFPO, add this to the value which you see in PLAF. This would give you the correct picture in your report, as MRP list keeps changing & you will not be able to have a reliable report if its based on MD05 data.
    Provide the above spec's to your developer & the report should be easily built.

  • Read planned order quantity

    Hi Experts,
    I wanted to know if is there any way to read the planned order quantity directly in a macro ?
    The scenario is that production is planned on 3 machines in production shop. When I refer to planning book, I get consolidated production of all the 3 machines (in KF Production Planned) but I want to use the production of individual machine & do some calculation in macro. Is there any BAPI / User Exit available to achieve this?
    Thanks in advance
    Regards
    Sandeep Patil

    You can use User exit macro to do this. Call BAPI_MOSRVAPS_GETLIST2 in this macro and you can get the planned order data. but this is complex developement and you need a good ABAP skill to do this.
    regards

  • Srap quantity should reduce planned order quantity

    Hi Gurus,
    I have a scenario here and i wanted to know if this can be technically achieved .
    1.We have IDOC flowing from legacy system and it consists of both good quantities produced and scrap quantities produced .
    2.Good quantity produced must be reported as a reporting point confirmation. Scrap quantity produced must be reported as reporting point scrap.  Scrap quantity produced must also reduce the planned order planned order quantity.
    3.Function module currently calls BAPI 'BAPI_REPMANCONF1_CREATE_MTS’ to post good Pieces Produced, can the same BAPI be used to call the scrap quantity and reduce the planned order ?
    I have tried 'BAPI_PLANNEDORDER_CHANGE’ to achieve this scenario but still the planned order quantity is not getting reduced.
    I want to know the feasibility to achieve this in technical or functional side .
    Kindly help me to solve this problem , rewards would be generous enough for people who solve my problem.
    Regards,
    PKP

    Hi Santosh,
    Yes, it's true, it would simplify a lot. Unfortunately it can't be done.
    These are high-end, high value and small life-cycle components and some packaging materials. Packaging materials are relatively easy to stock for one week or more but the other components should only be stocked to a minimum level.
    Moreover, suppliers of high-end components do not feel the need to respect scheduled delivery dates because they "own" the market, so we can't be sure when stock will be available. The high demand for this components also adds more uncertainty because there might be only (unplanned) partial deliveries during the week as of production is available and distributed for us and other supplier's vendors.
    Oh, and a production lot can really be of as low as 40 units in some cases.
    Well anyway, I've tried the ATP approach but immediately run into a problem. In the morning I might be assembling a component (A) for the afternoon and I have a delivery scheduled for the morning of another component (B). I can't plan the afternoon production of a product with both components. Even being 2-3 days, in some very frequent cases we should immediately start production as soon as components arrive.
    So ATP isn't very adequate even in the shortest time-frame to plan production in this scenario.
    Thanks a lot for your input Santosh, it was worth a shot. Right now I can't see an option other than copy SAP_PP_009 to a new heuristic that reduces planned orders to component availability or to use a very small maximum lot size for these short production runs.
    Regards,
    Edgar

  • Open Planned Order Quantity

    Hi Experts,
    for a particluar material I need the Open quantity of Planned orders for displaying in a custom report.
    Please suggest from which table or by logic can i fetch this quantity .
    Note: Not from any std report - i need table lable detail

    Hi
    Will this give the Open quantity of the Planned Order ( not converted ) ???
    in PLAF table only existing plan orders info will be there
    no productions orders
    Regards
    kumar

  • Planned Order Components Table

    I have a question. Is there a table that holds the components of a Planned Order?
    When I see the technical data of a component field in MD13 it tells me they are in MDPM, but this is a structure, not a table.
    that made me think that perhaps this is being fed directly from the BOM. But when I make a change to the BOM, the components in the planned order are not automatically updated.
    So they must be stored somewhere. Anyone knows which table it is?
    Otherwise, what FM can I use to fetch them?

    Fernando,
    You can get the components list of a planned order in RESB table for field PLNUM = Planned order number and BDART = SB.
    Regards,
    Prasobh

  • CIF blocked .. due to planned order quantity too small

    Hi,
    we facing the issue of whenever planned order generated after optimizer run. if the quantity of planned order < 1 i.e 0.8pcs . It will get stuck and won't cif to R3... any solution for this ..??
    thx  in advanced
    regards

    Hi
    Can you please clarify the following:
    1. Your Base Unit of Measure.
    2. Any Min/Max Lot and rounding values maintained in ECC/APO.
    3. PPM/Prod Version Lot sizes defined.
    4. What is your BOM base quantity?
    Also please elaborate the issue with proper examples, for us to help you better.
    Regards,
    Manjit
    Edited by: Manjit Pahal on Aug 7, 2008 2:00 PM

  • Planned order detail Table

    Hi,
    With a Combination of WORK CENTER and PLANT i need to extract all the respective PLANNED ORDERS, which is the corresponding table to query. Please help.
    Points Assured
    Regards,
    Prabu

    Hi....
    PLAF - Planned order table
    Tables related to work center:
    CHRD: Work center header.
    CRCO: Assign ment table
    TC24: Person respoancible for WC
    Others:
    PBIM: Independent Requirements for Materials
    MDTB:MRP Table
    RESB:Material Reservations
    Thanks,
    Naveen Inuganti.

  • Planned orders in tables

    Hi Experts
    I am working with SNP Tool. I want to know that where I can see my planned orders other then /n/sapapo/rrp3 or is there any table for planned orders storage.
    Please let me know if there is any table for planned order storage values.
    Regards
    guru

    There is no table for the planned order in APO like R/3 ( table PLAF ).
    You can see planned order in /SAPAPO/RRP2 also.
    If you want to read planned order data you need to use FM like
    BAPI_PBSRVAPS_GETDETAIL        Read Data from a Planning Book
    BAPI_MOSRVAPS_REQUESTLIST2     Request: Read Manufacturing Orders for Selection
    Manish

  • Decimal places in Planned order quantity

    Hi Experts,
    We are getting planned order(made from MRP) quantity as 43.24 KG. We dont want this. We want planned order in whole no. Like 43KG.
    How to achieve this,
    Regards,
    Santosh

    Hi Santosh,
    You can create rounding profiel for PO and contract release orders, but have to chk for planned orders...chk the below link may help :
    http://help.sap.com/saphelp_47x200/helpdata/en/67/c50d38c5a5c82ee10000009b38f842/frameset.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d28c844af11d182b40000e829fbfe/frameset.htm
    BR,
    Krishna

  • Ppds Planned order quantity is taken back to DP for analysis

    Hi Guru,
                Can any one explaine in step by step how i can release my order quantity from PPDS to DP to do my further analysis?
    Please it will be really great if any one can guide me.
    Thanks & Regards,
    Kumar.

    Kumar,
    Can you explain a little more what you are asking?
    DP is demand planning.  Here you are managing and deciding what your demand will be (predicting what you will sell is one of the more common outputs of DP)
    PPDS is detailed supply planning.  Here you are creating your supply elements, determining exactly how you actually intend to procure or build the product.  In this plan, you have the opportunity to take into consideration capacity, execution duration, and the availability of lower level materials. In many (but not all)  cases, the PPDS plan is built after the Demand plan has been turned into a final production demand forecast, and released to production for execution, prior to actually receiving the actual sales orders.  In some cases, companies also may create an intermediate supply plan, which would usually be at a simpler level of detail (SNP).
    Now you say you wish to 'release my order quantity from PPDS to DP' for some kind of analysis.  I am not sure what this means.  Supply and demand are two different things. 
    Companies that wish to, say, compare the demand plan to the supply plan typically don't do it in DP.  Some will write custom reports, others build custom infocubes in a BW and perform their analyses there.  It is definitely possible to extract supply elements (or just about any other type of data) into some kind of data structure, and place these elements into a DP planning book, if there is a business requirement.  This would definitely be non-standard, and would have to be designed and built from scratch.
    If you are looking for a transaction that will 'releases the order quantity from PPDS to DP', I don't believe it exists.  If you wish to pull data from PPDS or SNP or ERP into DP in general, I would say you should talk to your local BW and DP experts to see what they can design for you.
    Rgds,
    DB49

  • Sales order changes- table & field name

    Hi gurus,
    last week i created a sales order for 250 qty, and today i have changed the quantity from 250 to 200.
    from which table i can find out the old qty,updated qty and the changed date.
    cheers,
    Sumith

    Hi
    For  Changes to sales order  Check Table CDHDR & CDPO for Item Changes
    goto SE16 , enter the table & Give the Object values as the Sales order number
    you will get the change details
    Thanks & Regards
    Kishore

  • How to Pickup Serial Number from Production order through table field

    Hi Experts,
    I have SAP production order for Qty 5 and assigned 5 serial numbers .
    How to pick up the serial numbers technically
    what table, field I have to use
    Thanks
    Prabakaran K

    Hi,
    Please have a look to this thread:
    BAPI/RFC to get serial numbers for a production order
    Hope it helps,
    Kr,
    m.

  • Planned order quantity

    when i convert t o planeed order to purchase requistion
    the quantiy shows wrongly
    i checked with BOM quantiy data is correct
    why it is calculated wrongly

    Dear sir
    Thank you for the solution
    actually the quantity is 6,870 mm
    instead of that 6.780mm
    finally we found that for particular user ,they select decimal notation as x.xxx
    now we changed the decimal notation as x,xxx  in SU01
    now problem solved

  • User should not allow to exceed planned order qty

    Hello Experts
    In present case user can change the planned order qty when he converts it to a process order or purchase requisition.
    Is there any way to restrict the user, where user can not exceed the planned order quantity?
    Request to reply with a solution.
    Regards
    Pradipta Sahoo

    Hi Sahoo,
    I have two suggestion regarding the restriction of Changing the quantity while converting the Planned order into Process Order OR Pur Reqt. :
    1. First one is through the authorisation for the user, the suggestion given by our friends.
    2. You can use a User exit in the Planned Order Conversion transaction (CO40 / CO41/ MD04 etc). Where you can code to refer a Z- Table created with the User whom to be allowed.
    You can create a Z table and mention the user id for whom system should allow the change of Quantity during converion of planned order. So wheh the user is trying to convert the planned order system will fire the User exit and check if the user is available in the Z-table then it will allow him/her to modify the qty otherwise it will through an Error as required.
    Request you to take the help of the Abaper to invoke the userexit .
    I can suggest the third option too, but not sure whther it will work, you can try out.
    3. If you feel no user should be allowed to modify the quantity then I suggest you to create a Error message in the conversion tcode if the qty is being modified. You can try using a field exist.
    Regards
    radhak mk

Maybe you are looking for

  • [SOLVED] Windows 8.1, lost Arch boot loader, cannot reinstall or boot

    Hi all, Apologies but I am only posting as I have exhausted my (admittedly quite limited) knowledge and have spent hours trying to get it back up and running but nothing seems to work at all. This will probably be quite long, apologies if there is so

  • InDesign and printing full bleed with Epson

    I have been trying to print in full bleed from InDesign (CS6) on my Epson printer (Photo Stylus 1400). When I preview the artwork it looks fine just as I have set it up, but when I send to print the artwork is being cut off where its not supposed to.

  • Arrows in pages

    I am a chemistry teacher, and I am typing chemical equations H2+O2=H20 The equals sign to be an arrow. In office you can "insert>symbol" and their is an arrow (different than the object arrow) Where can I find this THANK YOU!

  • What means parameters tag ?

    Hi, I tried to understand what parameters means but after some time I give up. How can I access the form parameter. I tried to use get_parameter_atr buil in procedure but without success. Can anyone help me ? . Please let me know. Thank you, Vali GRI

  • 12 bit Image from a camera

    Hello, I'm acquiring some data from a x-ray detector. With each acquisition I obtain a column of the image that I want. The problem is that after n iteration I have a matrix of pixel values 192xN (with N=n.of iterations) see image attached for an exa