Planed costs on Simulation Version

Where can I see the planed costs on Simulation?
I have an escenario where the project is created as Simulation, and after this one is evaluated on duration and costs, the user transfer the simulation to an operative project, but I need to see the planed costs.

Hi ,
Go to trnsaction CNS41 Structure Overview report
Press The Push button DB Profile
Tick on Version data in Origin
here u can select the simulation versions for which u want to see the Project info with differentiated colors
by selection of Project planned cost field
Rgds

Similar Messages

  • Actual Cost on Simulation Version

    Hello
    I am creating simulation version thru CJV1. How do I plan and post actuals on that version ? I don't see that simulation version (proj defn) to do planning or to use it on PO in WBS drop down list.
    In short how do I simulation of cost on such proj versions. Once I transfer it to operative proj thru CJV4, I am able to do planning and post actual. What is the right way of using simulation versions?
    Thanks
    Sarang

    Ok got u. But then how do you paln costs on same i.e. commitment or activities labour cost etc
    Sarang

  • CJV4, WBS simulation version cost in COSS and COSP by cost element

    Hi PS expert.  (-:
    IN PS When we freeze a simulation version with CJV4,  (operative data to version), sap will create new object number in table VSCAUFV_CN for each network and VSPRPS_CN for each Wbs element related to the simulation Version.
    In our environment, SAP will add record in COSS and COSP for the new object number for Network but NOT FOR THE WBS.
    Is it standard to NOT record the cost in COSS and COSP for the simulation cost of the WBS (against the new object number?)
    That mean we will able to see the simulation cost by cost element for network, but NOT FOR WBS element.
    For the WBS, we only record the cost in RPSCO by cost category.
    Is there a way to active (with an exit ..classu2026bapi) the recording of the cost of the WBS by simulation version in COSS and COSP
    Thanks you very much for your help
    Sophie

    hi sophie,
    create separate network for each wbs in project.  see if this can solve your issue.
    vengaiah chowdary

  • Sales pricing from Project Simulation Version

    hi.
    Has anybody created sales pricing for the project using transaction DP 82? It does not create the sales pricing for the simulation version, even though I have provided the version key.
    The status of the simulation version of the project is CRTD. I am using the network cost planning in the simulation version of the project. Am I missing something here? I am hoping to get an answer from this community. Thanks for your help in advance.
    Regards
    Mey

    Hi
    The following are the prerequisites for the sucessful fuctioning of sales pricing for simulation versions of the project.
    1. A dynamic item processor profile (DIP profile) must have been maintained in the customer inquiry.and must be Customized for Project System.
    2.The same DIP profile must have been entered on the Sales B tab page of the item detail view in the SD order.
    3. A customer inquiry with at least one item that has to be maintained and assigned to a billing element must exist. The system determines the SD data for sales pricing from this inquiry item.
    4.You have planned costs (in concordance with cost elements) for your project version.
    If these prerequisites are met, i think it will work
    Reward if helpful
    Regards
    Murali

  • How to compare the simulation version

    Dear Experts,
    For Operative Projects we can create Simulation Versions (CJV1 / CJV4) & Project Version (CN72).
    We can compare different Project Versions with Operative Project (S_ALR_87013539 / 38).
    Similarly can we compare Simulation version with Operative Project?
    OR can we see plan cost report for simulation version?
    Please guide.
    Rajesh

    Hi,
    Simulation versions are not meant for comparison purpose. You can use Project versions for that, which are snapshots of project at that point of time.
    Simulation versions can be used to analyse 'what-if' conditions and for quotation ie pre-order analysis. Before receipt of sales order, you can create simulation project and do cost planning for quotation purpose. After receipt of sales order, this project can be made operative. In case of loss of project, you can delete simulation.
    Another case can be during execution you want to check "what happens if" kind of conditions. you can transfer operative project to simulation version, simulate reqd condition. If results are desirable, you can copy the simulation version onto current project or alternatively delete simulation.
    Regards

  • Simulation version WBS element

    Good morning,
    We need to load for the 0WBS element,  the simulation version (PS
    version , not CO version).
    Could you help me?
    Thank you

    Hi,
    check out this sap help...
    http://help.sap.com/saphelp_nw04/helpdata/en/b4/60073c0057f057e10000000a114084/frameset.htm
    CJ40 - Project Cost Planning By project and wbs

  • Simulation version Error - Message no. C2323

    Dear Experts,
    I'm trying to create simulation version from operative project.
    I'm getting the following error even though I have maintained settlement rule.
    Settlement rule contains errors and has not been saved
    Message no. C2323
    Diagnosis
    You use a strategy and/or default rule to automatically determine settlement rules for orders/networks.
    The system has determined a settlement rule for NWA #46 according to the defined strategy and/or default rule. However, when checking this settlement rule, an error appeared.
    This error may occur, for example, when you want to create a settlement rule for the superior WBS element, because due to a user status on the WBS element, this is not allowed.
    System Response
    The settlement rule is not saved due to the error.
    Procedure
    Maintain the settlement rule manually for NWA #46, and check the strategy and/or default rule used.
    Please help.
    Regards,
    VINOD.V

    below is the settlement strategy parameter for network
    Manual maintenance of settlement rule
    1   Automatic generation of settlement rule
    2   Generate settlement to WBS element
    3   Copy settlement rule of the WBS element
    4   Copy settlement rule of the project definition
    5   No settlement rule
    then assign strategy to PSP/PS1
    assign network settlement profile to network type as zps1,2,3,4&5
    so just configure the strategy according to suitability then run simulation.
    Regards,
    Sanjeev

  • Sales Order Costing using prod version

    Hi Guru,
    My client use MTO and have prod version 1000 & 2000.  When I create SO and choose prod.version 1000,  prod.order created using BOM/Routing in prod.version 1000, so the prod order cost plan.
    But in costing SO, prod version 2000 is use as base in qty structure, it's mean SO plan cost is based on prod version 2000, not 1000.
    How the logic of SO costing ? where config to be set in order to get SO costing based on prod version choosen.
    Reward will given to any input.
    Thanks

    You may want to have a look at OKK5 - Quantity structure determination.(QSD)
    Choose the Quantity Structure control and double click. Then click on the BOM application. In there, there is section for override alternative selection from material master. There is a check box for production version. whose help reads as
    This indicator shows that, when alternatives are selected automatically according to application, the production versions maintained in the material master record are used as selection criteria.
    Dependencies
    <b>In the MRP view of the material master, in the requirements explosion data, the indicator for selecting alternative BOMs is maintained.
    When you explode the  BOM, only the alternatives for which selection by production version (2) is defined are taken into account for selection.</b>

  • Hierarchical report to compare simulation version

    Hi,
    Which are the hierarchical report where simulation version can be compared?
    Thx

    Hi,
    In addition you can directly access from T Codes like CN41, CN41N, CNE5 etc.... Please see that "Version Data" is selected in the DB Profile.
    Regards,
    Arul.

  • Integration of Simulation versions of APO & R/3

    Hi,
    I want to integrate simulation versions of APO & R/3 so that data can flow between both systems.  Is it possible?  How to do it?
    If the answer is possible, how to create simulation version in R/3 and to integrate with the simulation version of APO?
    Please reply,
    Regards,
    R. Senthil Mareeswaran.

    Hi Senthil,
    APO & R/3 Integration can only be done with active version that is version 000. Integration using simulation version is not possible.
    Regards,
    SB.

  • Simulation version

    Hi,
    On simulation i have two questions
    1. What is the significance of simulation profile. Is it required to be assigned for the project (Through project profile) before carrying out the simulation?
    2.I am trying to create simulation version in CJV4 for the project. I have created the simulation profile and assigned it to my project profile. But when i try to create the simulation version i am getting the following error
    "When you want to run a report that uses the PSJ logical database, module pools are generated for runtime optimization and memory optimization. This module pool cannot be generated since therew is an error in the logical database. This error can only occur, if the SAPDBPSJ program was changed during the runtime of your prrogram".
    Can any body help me in this?
    Rajesh

    Hi,
    Simulation profile is not mandatory. The profile controls what texts get copied from operative project to simulation. If you dont give this profile, all texts get copied into simulation.
    I would be able to help if you tell me the error message number. I hope it is not dump. In that case goto ST22 and let me know the details.
    Regards

  • How much cost the edu version for teacher of flash professional?

    It is not clear.
    How much it cost the edu version for teacher of flash professional for cloud?
    Thank you.

    Creative Cloud Plans
    https://creative.adobe.com/#plans

  • Handle a Simulation Version in Background

    Hi Experts,
    we would like to modify some block data (in Heuristic fo Block maintenance) for a specified ressource BUT in a simulation version.
    To be more specific, when we go on /sapapo/cdpss0  and select a simulation version, the we click on Process in Graphic form, then select a specified ressource, click on SAP_CDPBP_03 and change some data for the block listed.
    We would like to do this in background (BAPI, MF, or others), as Batch Input doesn't seem to work for the /sapapo/cdpss0 transaction  in Graphic Form Processing.
    Is there any way to achieve that, or does the simulation functionnality only works in Transactionnal mode ?
    Thank's in advance !!!

    Hi Cousture,
    There are two ways of handling simulation version.  One in the active version and another in the inactive version.
    It is always recommendable to carry out simulation studies in active version in foreground only because once you
    adopt the changes into active version, if it is master data change, it will affect the data and users.
    That too, for graphical objects, if it is carried out in background, it leads to performance problems.
    Moreover, there is no sap std feature available for carrying out in background
    I checked the badi/bapi also and no such is available.
    Regards
    R. Senthil Mareeswaran.

  • DS board simulation version owner

    Hi All,
    Can some one tell me the reason for the DS board simulation version owner field not getting populated. We made some change in PB and saved them in a simulation version. When we tried to process the simulation version from /sapapo/cdpss0, its not allowing us to open it in edit mode. We have found that the field simulation version owner is blank. Any body have a hint about the potential reason for the filed not getting populated.
    Thanks in advance,
    Kalyan.

    Dear kalyana kothamasu,
    This is something strange!!
    Tell me one thing, when you execute the transaction for planning board, is there any user name on overall profile and work area.
    jsut check that.
    Means is there any user specific overall profile or user specific work area. check that.
    I think it should not affect as such, but nothing sure about APO where things can get affected......  as usual.
      Check these 2 things your issue should be solved.  since there is nothing custumisation for what you asked in the issue.
    Regards,
    Pravin Mukkawar

  • We need to copy planning..etc from simulation version 002 to version 000,

    Hi experts,
    Our simulation Version is 002 and Active Version is 000
    We need to copy planning..etc  from version 002 to version 000, how to do. Explain me  elaborate
    Regards,
    moon

    Hi Moon,
                   There are two things in Copy Version Management.
    1) Copy the master and transaction data from active to simulation version.
    Transaction - /SAPAPO/VERCOP in this you can not copy from Simulation to Active.
    2) Merge the Planning Versions.
    Transaction - /SAPAPO/VERMER in which you can copy the planning area keyfigures from simulation version to Active Version.
    Regards,
    Saurabh

Maybe you are looking for

  • Problems with creating a website adobe muse

    I have a big problem with adobe muse'm creating a website and goes all bn put the background color of the color and everything goes normal entries placed on the footer and header and there is when the problem occurs I have to fight for I look perfect

  • AE CC works but AE CC2014 hangs at media init - so does Media Encoder 2014

    OSX 10.9.4 AE CC works great -- AE CC2014 hangs at Initializing Media Core.  When it finally opens it says the quick time not installed.  I set all cache - adobe folders to read/write permissions.  I have only apple codex in Library/Quicktime.   My f

  • Using SOAP Sender adapter in PI 7.1

    Hi Guys, I've created a sync scenario with SOAP sender adapter, but I have troubles with calling it. I use following URL: http://<host>:50000/XISOAPAdapter/MessageServlet?channel=:BS_Bus_Sys:CC_SOAP_Test as I did in XI 3.0, but I'm getting error HTTP

  • Exit button not visible in standard applications

    Hi all, When we call a standard ESS application ( bank or address) from the detailed navigation, the exit button is not appearing in the application. However, when we open the same application from the area page, the exit button is appearing correctl

  • ITunes process is running; but I can't open the iTunes URL

    Is there help for this issue? Mark