Planned cost for int labour and non stockable material not visible

Hey gurus,
While creating an order with a material, ext service, non stock material, I am able to see the planned cost for materials in stock and ext services procured. But i'm not able to see the planned cost for non stock material and int labour. However i'm able to see the actual cost for all the items. I think I have missed some config. Please help.
Regards,
Abhishek

Hi,
As said by Pithan there is a problem in costing variant for planned cost which you have assigned to prder type at plant level.
Problem underlies within valuation variant assigned to costing variant.PM01 is your costing variant here.Check diiferent heads within valuation variant for this costing variant.There under activities tab what is calculation parameter you have selected.If it is blank you will not get any internal activity cost.You need to select at least one from dropdown like cost from previous period or avaerage cost etc.Then you will get planned cost for internal activities.SAmething applies to non stock material.
Check in OKP6 for all these and make sure that you have selected at least one cost calculation schema there for activities and material and external.
Regds,
atul

Similar Messages

  • BAPI KPF6 POST PLAN COST FOR INTERNAL ORDER AND COST ELEMENT

    Hi all gurus,
    I would like to use in a custom report a BAPI/Function Module that help me to simulate KPF6 in order to post planning costs for internal order and cost element (layout 1-401).
    So the input should be:
    1) Version
    2) period from
    3) periodo to
    4) year
    5) internal order n.
    6) cost element n.
    7) value
    I found a lot of BAPI but don't know the correct one and how to use it (example how to fill the input value).
    Can anyone help me on that?
    Kind Regards

    In additio  to the previous I found the BAPI_COSTACTPLN_POSTPRIMCOST but don't know if it's the correct one and how to use it (some example fitting the my case will be very appreciated).
    If the quoted BAPI is correct.
    I tested it filling all fields as following:
    HEADERINFO:
    CO_AREA=FFCA
    FISC_YEAR=2008
    PERIOD_FROM=001
    PERIOD_TO=012
    DOC_HDR_TX='blank'
    INDEXSTRUCTURE:
    OBJECT_INDEX=000001
    VALUE_INDEX=000004 (hope this point at Interna Order)
    ATTRIB_INDEX=000000
    COOBJECT:
    OBJECT_INDEX=000001
    ORDERID=ZO53-08IMZ
    TOTVALUE:
    VALUE_INDEX=000004
    COST_ELEM=3224048
    FIX_VALUE= 200,0000
    DIST_KEY_FIX_VAL=2
    The Return table is set to 0. Nothing happens.....I suspect something related to indexstructure or index is wrong..
    Could anyone help me on that?
    Kind Regards

  • Any FM to calculate planned costs for a Maintenance plan

    Hi all,
    Is there any FM to calculate planned costs for an Maintenance plan.
    I can use report RISTRA30(IP31). but i need to use for multiple multiple Mplans and different time frames. using SUBMIT to this report and getting data will lead to performance in my actual report.
    Please do provide any FM's or any other pointers for the same.
    warm regards,
    Sumanth

    Dear,
    In maintenance plan you can speciefy - order type,task list type,task list group & counter.
    when system automatically create service/maintenance order then system will determine plan cost, but for this you have to maintain planned price by t-code KP26.
    And then you can see report by IP31
    REGARDS,
    Kapil
    Edited by: Kapildev Farakte on Nov 17, 2009 10:38 AM

  • Planned costs for investment program

    I am having a problem configuring planned costs for inv program positions, which should reflect as the planned cost for the investment measure being created.
    Appropriation request is being used in the scenario to create measures automatically. these measures will require to have the same plan values as the position to which they are assigned.
    Please help.

    The Measure is the cost collector through which spending will be controlled & measured, which is a key integration object with IM.
    WBS Elements are the collectors associated with PS, whereas IO’s are cost collectors found in the CO module.
    The Measure is always assigned to the lowest program position within IM. Program Position is found on Investment Program Hierarchy at its lowest level which may relate to a capital project or project component.
    Hence accordingly the appropriation request serves as a tool to plan the spending and which is therefore upon approval becomes the Measure for the IO or WBS.

  • Planned cost for MTO

    Dear,
    Here in the company have the following situation:
    The system appropriates the planned cost for the production order when the process is MTO.
    Anyone know any way to settle the planned cost of the stock of free stuff and not the planning of the Order of production?
    thank,
    Sergio Navarrete

    Ajay,
    Here's an example:
    This material is the planned cost for the stock free: Process MTS.
    Standard Price 12,96
    In the same material (special stock) planned cost came with the Production Order Sales Order. MTO process.
    Standard Price 100,96
    Order 20232271
    So we can see that the cost calculated by the planned production order is very different from the planned cost of the same material for free stock.
    Question:
    You can make the system use the same cost of the planned free stock for stock of the particular process, such as material inventory value free, 12.96?
    thank,
    Sergio Navarrete

  • Planned cost for Results Analysis

    Dear Friends,
    SAP reads line items from COSS and COSP to determine the planned cost for result analysis.  What line items does it consider while summing up the planned cost.  I wish to reconcile the planned cost as considered in result analysis.
    I am considering the line items from COSS and COSP where
    Value type = 1 or 11
    Beltyp = 1
    Version = 0
    Business Transaction ????
    What values should I put for business transation ?    Or is there a SAP standard report which matches with the planned cost value of result analysis.
    Standard report S_ALR**** does not always match with the planned cost value in result analysis.  These reports read values from RPSCO table which is a summary table.  
    Regards
    Jayesh.

    After releasing production order all primary and secondary costs get attached to the order.
    You can see planned cost in Tcode:CO02>>>>Goto>>>>>>>Costs>>>Analysis>>>under cost trend layput.
    Yogesh Thorat

  • Planned cost for processing the component

    Hi All,
    How to see the planned cost for processing any component or finished product in SAP.
      I don't want actual cost for processing the component.
    Regards,
    Shailendra

    After releasing production order all primary and secondary costs get attached to the order.
    You can see planned cost in Tcode:CO02>>>>Goto>>>>>>>Costs>>>Analysis>>>under cost trend layput.
    Yogesh Thorat

  • Planned costs for production order

    Hi,
    I have a requirement where the actual costs and planned costs for a production order have to be displayed. I got the actual cost details from the table COEP.
    Please let me know if anyone knows the table which stores the Planned Costs / or any function modules which can be helpful.
    Thanks in advance.
    Neethu Mohan

    Hi ,
    Please refer the thread,
    How To get Planned Cost for a Production Order
    Best Regards.
    *Reward if it is helpful.

  • Function modules or BAPI for posting plan costs for WBS Element

    Hi all,
    Does anyone know, whether there exists a function module or BAPI for posting plan costs to a WBS Element? K_COSTS_PLAN_PS does not work, because RKP1 is not allowed.
    Greetings

    check
    BAPI_COSTACTPLN_POSTACTINPUT   Activity Input Planning: Posting                
    BAPI_COSTACTPLN_POSTACTOUTPUT  Activity/Price Planning: Posting                
    BAPI_COSTACTPLN_POSTKEYFIGURE  Stat. Key Figure Planning: Postings             
    BAPI_COSTACTPLN_POSTPRIMCOST   Primary Cost Planning: Postings                 
    BAPI_PDTRANSCO_POSTPRIMCOST    Transfer of Planning Data: Post Primary Costs   
    K40C                           CO Actual Postings, Manual                      
    BAPI_ACC_PRIMARY_COSTS_POST    Accounting: Post Primary Costs                  
    BAPI_COPAACTUALS_POSTCOSTDATA  BAPI Operating Concern: Post Costing-Based Actua
    BAPI_PRIM_COST_CHECK_AND_POST  Primary Costs: Formal Parameter Check           
    S@meer

  • Hello! My name is Vadim. I'm from Russia. I'd like to buy two iPhones 5, 64 GB: for my wife and myself. But I have a question to you. Will it work in Russia? How much will it cost for me? And how much will delivery cost to Russia? Thank you very much.

    Dear Sir or Madame,
    My name is Vadim. I'm from Russia. I'd like to buy two iPhones 5, 64 GB online, from your official website Apple: for my wife and myself. But I've a question to you. Will it (iPhone 5, 64 GB) work in Russia? How much will they cost for me? And how much will the delivery from America to Russia cost?
    Yours sincerely,
    Vadim Fedotov.

    iPhone 5 is not available unlocked in US  and
    Apple Store online does not ship outside the Country it operates
    You are best served waiting for the iPhone 5 to be announced in Russia
    through your Apple Approved carriers

  • Park document approach for all PO and Non u2013 PO based vendor Invvoices

    Hello Experts,
    I want to use park document approach for all PO and Non u2013 PO based vendor Invoices.SAP
    Allows park document facility for FB60 ( Non-Po Based vendor Invoice)but doesnt allow the
    Same functionality for MIRO ( Logistics Invoice Verfication).Can anyone suggest a wayout for Park
    Document functionality for MIRO
    Thanks and Regards
    Urmila

    Hi,
    Transaction MIR7 can be used to park PO-based invoice. The same can be posted through MIRO.
    Regards,

  • I would like to install the newest version of Acrobat Adobe into 6 computers. I wonder what tha will cost, for a month and to buy it directly? On one computer we have version 9, and that one we would like to uppgrade to the latest version?

    I would like to install the newest version of Acrobat Adobe into 6 computers. I wonder what tha will cost, for a month and to buy it directly? On one computer we have version 9, and that one we would like to uppgrade to the latest version?

    Hi Linafrick,
    To install Acrobat 11 on to 6 computers you can purchase Volume License.
    But since you want it for only a month you need to purchase Acrobat subscription.
    A single subscription is good for 2 computers and the same Adobe ID cannot be used to buy multiple subscription copies of Acrobat.
    You can however opt for Creative Cloud for Team license such that you can become the Admin and grant access to the 6 users who wish to install Acrobat on their machines.
    Feel free to reach our customer service via chat to know more information: Creative Cloud membership support
    Regards,
    Rave

  • Reg Excisable Material and non Excisable material. Billing and delivery....

    Dear Experts,
    Greetings!!!
    Here I am using TAXINN; my client is doing business excisable material and non excisable material.
    He received the order from his customer both excisable material and non excisable material in Single PO.
    At the time of delivery he needu2019s non- excisable and excisable material would be separate delivery documents.
    He is not ready to do manually selection in out bound delivery.
    In this process what should I need to configure.
    Please do need full.
    Prasad.

    Hi Laxmipathi Garu,
    Yes , we are not using trasportation group.
    I will follow as you suggested.
    I will copy the same routien, there i will write programme, when ever delivery is going to save, then system slpit two delivery documents, one for excisable material, second non excisable material.
    If i am doing wrong please you can correct me.
    Once i done this, let you know.
    Thanks,
    Prasad.

  • Validity and non-validity material

    hi frnds
    what is validity material and non-validity material ?
    regards

    Hi Santosh,
    Please go through this SAP help it may not give you Exact answer for your quiery but you can get some idea on Material validity.
    http://help.sap.com/saphelp_47x200/helpdata/en/f3/7c8fe6a39411d19daf0000e8323350/frameset.htm
    I hope it will help you,
    Regards,
    Murali.

  • Difference between stock and non stock material

    what is the difference between stock and non stock material. example of stock and non stock material?

    Hello,
    Stock Material
    Material that is constantly kept in stock .A stock material has a material master record and is managed on a value basis in a material stock account.
    Ex: Raw Material.
    Non-stock Material
    Material that is not held in stock because it is consumed immediately.
    Ex: Office Stationary.
    You need to create purchase order and accounting document for payment but the stock balance is always zero as it is issued out immediately to the various department.
    Prase

Maybe you are looking for

  • I was updating my iPhone 4 and it is now un ressponsive. What do I do?

    I was in the process of updating my iPhone 4 to iOS 5 and kept on getting three quarters of the way through to the 'Veryfying update with Apple' stage and then error code 3004 or 3200 would appear in iTunes. I kept on trying to update it and then aft

  • HT4938 New mac-mini server setup without keyboard and mouse

    Im trying to use the server app to setup my new mac mini server without mouse and keyboard, but the server is not listed. I have tried using its IP address with no username and the serial number as password but it won't connect. Any ideas?

  • Volume lowered after installing windows 8 pavilion g7

    Hi, I have Pavilion g7-1317cl Notebook PC After installing windows 8 the volume level lowered, i tried going to the speakers and then Enhacment and check the loudness equilizer and the volume got up alittle but still lower than normal, How to get it

  • Web dispatcher "Error : PSE file ,unable to use! "

    Hello, I has a SAP Netweaver kernel 7.01 with oracle database. I tried to config web dispatcher to support ssl by following the link below. [http://help.sap.com/saphelp_nw04s/helpdata/en/39/09a63d7af20450e10000000a114084/content.htm] I has done all s

  • Can I use Smiley Central Ap with Firefox 4? I have Mac OS X 10.6.7

    I have a MacBook Pro with Mac OS X 10.6.7. I have downloaded Firefox 4. I tried to download Smiley Central Ap, but was informed it only works with Firefox 3. How can I get Smiley Central to work on my Mac?