Planned Delivery Time and Transportation duration- Tlane and Means of Transportation

Dear Experts ,
I have question regarding lead time calculation my SNP
I have
Start Location : A
Destination location: B
I maintained Planned delivery time in ECC- material master as 10 days  and cifed to Tlane Product procurement as 10 days
and leave empty in the transportation duration empty so the total lead time is 10 days from start location A to destination location  B
now
I maintain 24 hours in Means of transport as transportation duration by truck
now the lead time is 11 days from start location A to destination location B
Now
i leave empty planned delivery time empty and maintain Means of transport duration as 48 hours
so the lead time is 2 days from A to B
does my understanding is correct or not advise please
Regards
Raj

Hi Raj,
Take a look of these notes. Specially SAP note 379006. This note explains how the system sets the times in ECC and APO. Basically, It recommends a BAdI in order to match the delivery date in ECC and APO (transit time). What I recommend is to set delivery time equal to 0 if this is possible in your company.. This is not an SAP recommendation, because the delivery date is a key master data in the purchasing process and making it equal to 0 could not be allowed.. Now, if its possible in your case, it is the easiest way to ensure consistency...
These are the notes:
379006
- Transport duration and planned delivery time in APO and R/3
441622
- Supplying-plant-dependent planned del. time/trans. time
624982
- Incorrect dates for RBA controlled stock transfer
Kind Regards,
Mariano

Similar Messages

  • Purchasing: Planned delivery time

    I have a material that are being purchased from 2 vendors.  one vendor delivers the material in 2 days.  the other takes 20 days.  In the material master, I have to maintain the planned delivery time.  As per the help info, I will need to maintain the average time here.  So, that would be 11 days.
    So, when I run MRP, 11 days will be taken as the planned delivery time.  My planning is not going to be accurate if I choose any of the vendors.
    Can anyone guide me how I can take care of this scenario?

    Raj,
    You maintain your planned delivery times for each vendor in your info records.
    You need to ensure you have flagged the <i>scheduling info record/agreem.</i> flag (Determine Planned Delivery Time) in transaction OPPQ.
    You also need to ensure that you have maintained source list entries for your vendors that are relevant for MRP.
    Now the MRP run will consider the planned delivery time in the info record and not the material master.
    Hope this helps.
    H Narayan

  • Planned delivery time not updating real time in apo

    Hi,
    I have a location product which is part of the active integration model.
    The location and product are both available in ECC and APO.
    When i change the value of Planned delivery time in ECC, the changes do not get transfered to APO even after RIMODINI.
    For e.g. the planned delivery time currently is 1 day and it is changed to 3 days, even after doing RIMODINI the changes are not reflected in APO.
    Kindly suggest if somebody has come across this issue earlier.
    Thanks & Regards.
    Santosh Joshi

    Hi Santosh,
    Please check by tcode CFM5 weather material is there in IM or not .
    Also check CFG1 log on R/3 and SLG1 or /SAPAPO/C3 or /SAPAPO/CQ in APO.
    Please confirm.
    Manish

  • Report with material number and planned delivery time

    Is there any standard report with material number and planned delivery time ?

    Hi,
    I do not know any standard report. Please try SE16 + MARC...
    BR
    Csaba

  • Planned Delivery Time is included Saturday. and Sunday?

    Dear Guru,
    Please kindly advice me about Planned Delivery Time in Days in the MRP View.
    Is it include Saturday and Sunday?
    If my calendar is not work on  Saturday and Sunday.
    Thank you very much.
    Saiya

    System calculates with help of factory calender. if you maintaned saturday and sun day as public holidays then system will not considered for planned delivery time.

  • Planned delivery time in Scheduling agreement and MRP

    Hello,
    Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
    Regards, jaana

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • Can i use the key figure total delivery time in days in rows and how is can

    Dear all,
              Can i use the key figure total delivery time in days in rows and how is can.but all the key figures r used in rows but i cannot use in column.i want bothin rows and in column  at a time ,can this is possible,and how.

    Hi,
      yes you can.You will have to use structure in the row.
    Right click on the row and create a new structure.
    In this structure you can add key figure.
    Maximum number of structure a query can have is two
    Please assign points if it helped you.
    Regards,
    Senoy

  • Req date for an activity based on planned delivery time of component

    Hi Experts
    I wish to create activities for purchase and install an equipment.
    The procurement activity is assigned with the component.
    the planned delivery time is specifed (ex: 100 days)
    Based on this value, can i get calculated the requirement date for the activity (Ex: today+100days) in stead of manual specification of date for the corresponding activity?
    warm regards
    ramSiva

    Hi Ahmed
    Thanks for your response. This seems to be good feature.
    However, i could not get the date corrected for my activity after applying this function.
    I have created an activity with normal duration 1day. For the same activity, i have assigned a compnent which has 100days planned del time.
    Then i have used 'Transfer Del time --> duration'. But no change.
    Could you suggest me right approach?
    warm regards
    ramSiva

  • TLD or Planned delivery Time

    Hi Experts,
    Normally we CIF planned delivery time from R/3 to Apo. Instead of planned delivery time, shall we use Transportation lead time offset to be maintained on the transporttaion line itself in APO?, which one is better?.is Both (TLD or PDT) are same.
    Regards,
    Madhu

    Hi
    As I mentioned it depends on your business case in which cases you want to create a TL.
    In our case we only create TL in intercompany planning scenario, in third party supplier we do not create TL and we directly user planned delivery time which is getting CIF from ECC system.
    I think both should able to server the respective purpose. Only one clue for you lead time defined TL will overwrite the planned delivery time in ECC during planning run
    Thanks
    Amol

  • MRP - Auto creation of del schedule lines based on planned delivery time

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Nirav,
    This subject has been discussed repeatedly in this and other forums.  I must assume that you overlooked the rules of engagement, which state that you should first search the forums and other public sites, before posting questions here.
    Standard SAP MRP cannot be made to generate multiple items in a Purchase requisition.  The functionality you seek is usually achieved when converting purchase reqs to Purchase orders, where many single purchase reqs can be adopted into a single Purchase order.
    You also might want to investigate use of Vendor Scheduling agreements.
    Best Regards,
    DB49

  • Planned Delivery time in case of Scheduling Agreement

    Hi All,
    Does system consider the planned delivery time in case of Scheduling Agreement for Vendor like in normal Purchase order and requisition?
    I am doing the MRP run, but system is taken planned delivery time into consideration. I have one material that is Inhouse produced material for plant X and Y Plant needs this material for further making of a finished goods.
    Y plant have scheduling agreement for STO from plant X. After MRP Run required Delivery date in plant X for Material is same as plant Y. but from Plant X to Y, it take 4 days to reach. So Ideally in Plant X this delivery date should be less than 4 days as plant Y.
    Please look into the issue and reply if you have some answers.
    Thanks
    Pavan

    Hope you have maintained different Planned Delivery times in plant X and Plant Y as per your requirement. For procurement in Plant Y the system would consider the planned delievry time maintained in Plant Y. If you want in-house production time to be considered with Basis date sheduling during MRP run in PLant X then enter the in-house production time approprietely. Else if ou want to consider the exact routing times then consider Lead time scheduling in plant X.
    If the above are maintained properly then you should get the desired result.
    Regards
    Ramanujan

  • System is not considering Planned Delivery time

    Dear Gurus,
    As iam planning for the month of January and running the MRP,schedulelines are getting generated but system is not condering Planned Delivery time maintained in the material master ie. 7days.Following is the example:
    I have a FERT-X with a component A-1PC in its BOM and its planned delvery time from vendor is 7 Days.If iam running the MRP on 13/12/2010 for FERT-X  100 PCS for January1,2011 then the schedule lines are getting generated for for component A is on 01/01/2011.But PDT is maintianed in material master is 7 days and same has been maintianed in vendor inforecord.But system is not considering it.
    Kindly help to resolve the issue.
    With Regards.

    I have one ROH which has two different vendors.
    Two scheduling Agreemnt with target qty 100000 kg each.
    Two different Vendor info record with Min. order qty maintained.V1-1000Kg,V2-6000Kg.
    One source list with two vendors and with respective scheduling agreement.
    Quota arrangement is there in which SOB is maintiained 50:50.
    I hv the requirement of 3084 kg of ROH.
    I run the MRP and two diiferent schedule lines are getting generated with 50:50 qty as mentioned in Quota arrangement.
    Not considering the minimum order qty maintiained in vendor info record.
    The above process is correct
    Only One doubt In Quota Arrangement?
    IS two schedule line is created after MRP run?
    Generally System will  select a vendor Whose Quota value is less
    quota rating   = quota base quantity + quota-allocated quantity/ quota
    Edited by: Sundaresan . E. V on Dec 14, 2010 3:26 PM

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • Planned delivery time issue

    Hello Experts,
    We have below requirement.
    Created sales order for a particular material. Planned delivery time is picked from info record for that material and PR has been created.
    We are converting PR into PO and the planned delivery time is fine. Now we are updating the ASN from vendor with some prior dates. In MD04, the same got updated. However the sales order still shows the old planned delivery time only. How to get the new planned delivery time  in the sales order based on the ASN updated in PO.
    Example:
    Material: A
    Planned delivery time is 10 in info record
    Created sales order. Planned delivery time in the sales order is 10. PR created with fixed vendor and planned delivery time is 10 days from the date of creation.
    Converted PO.
    Now we received the ASN from Vendor that the vendor will deliver this material in five days. So accordingly we are updating the ASN in PO with delivery date.
    In MD04, we could the new planned delivery time based on the ASN. However sales order delivery still shows the previouls delivery date only.
    How to get the new delivery date in the sales order based on the ASN update?
    Regards
    Bala

    This is not standard SAP logic. Required delivery date on the original line item stays as it was when you issued the order. Then you create a confirmation (ASN) that is relevant to MRP with the updated delivery date. Planning sees the new date and acts accordingly, and also in the order you can see both "old" and "new" (in the confirmation tab).

  • Planned Delivery Time of Schedule Line

    Dear Gurus,
    I have done the setting in SPRO >MM>PURCHASING>PP>PROCESSING TIME from 1 day to 0 day bt still  it is picking up one day for schedule lines.There is 0 days planned delivery time in VendorMaster,Material Master,Vendor info record.
    I hv run the MRP  on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    With Regards.

    I hv run the MRP on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    During MRP, System will do the backward scheduling... from FG reqmt to Raw material,
    Compare the order start date  of header material in plan order or in prdn order  with the reqmt date for  the schedule line material - Is any difference in days?

Maybe you are looking for

  • What external hard drive to you recommend to free up space on an old Macbook Pro?

    My Macbook Pro is approx. 5 years old. I have since gotten an imac, however would like to use my old Creative Suite 2 on the macbook. When I updated it to "Lion" - it denied access to my creative suite apps. I have since contacted Adobe, and they hav

  • BPE crash - Trying to remove work item and SXMB_MONI message that caused it

    Hi, I have a file to IDOC scenario with BPE.  We have had a large file that was picked up by XI in error, but the adapter engine did process the XML conversion successfully.  This message was sent to the BPE but due to the message size, the BPE crash

  • Can't create a book in iPhoto 11 (9.5)

    I am trying to create a new book in iPhoto, but when I select New>Book or Share>Create>Book, it opens the book editor (I guess you call it) with a frozen loading image, and that's it. I can't change from hard cover to softcover or wire bound, or sele

  • How to count the number of records retreived through a query?

    Dear All I want to find the total number of records retreived for a particular query . does BW provide any internal count function , which can solve my requirement?? if yes, please provide some details. Thanks. Regards, Pandurang.

  • IMAP Deleted Messages AND Unread Messages

    I've read quite a few threads about two seemingly persistent problems using Mail and IMAP servers: a) Messages deleted within Mail "reappear" in the client's in-box, and b) messages read (and marked as read -- no blue dot) "reappear" as unread messag