Planned Delivery Time from Material Master instead of PIRs

Hi SAP Gurus,
Do you know if there is a way to have MRP look at the Planned Delivery Time from the Material Master (MRP 2 tab) instead of the PIR?
We would like to create global PIRs with a PDT of 1 and have the Material Master PDT set to a different number (example 5).  So when MRP runs it will read 5 instead of 1.
Any additional information is appreciated.
Thank you
-nic

Hi Nicholas,
In Standard SAP will consider Planned delivery time maintained in Inforecord and than time maintained in Material master. Inforecord has higher priority than material master. When a requisition is manually created, the Planned Delivery date will always be taken from the material master.
For MRP you can make setting OMDT for your plant or MRP group to determine planned delivery time.
Deactive the flag 'Scheduling according to purchasing info record or agreement' in Customizing (Plant or MRP group). and test the same.
Regards,
R.Brahmankar

Similar Messages

  • Planned delivery time in material master

    Is planned delivery time in material master considering holidays ? I mean when I say 7 days, is it one week and 2 days or only one week ?

    Dear Balaji,
    If you push F1 when your mouse is set on that field you will see that help says that PDT is defined as calendar days. However, you can carry out some changes:
    http://www.sap-img.com/materials/planned-delivery-time-as-workdays.htm
    About meaning of PDT:
    http://www.sap-img.com/production/calculation-to-determine-the-delivery-date-and-release-date.htm
    In addition to that link, you can use safety time as well (with this setting you can pull back in time the requested availabilty date during MRP run). You can also use PDT in info records if you have several source of supple for one material.
    BR
    Csaba

  • Automatic updation of planned delivery time in material master.

    Dear all,
    Is it possible to update the Planned delivery time in the material master automatically by the system based on goods receipt date.
    what customisation needs to be done.
    Regards,
    Dayanand

    It is not dynamic field so you  can't retrive automatically.

  • Delivery to copy weights,volumes from material master,instead of sales ord

    hi,
    The weights/volumes get copied from the material master to the sales doc and from the sales doc to the delivery.
    We have a issue where proper weights/volumes are not known at the order entry. thus when the new weights etc are noted, they change it in the material master.
    could some one please let me know how to configure the system to take the values from the material master for these instead of the sales doc to get the weights/volumes.
    that is the delivery doc should get the weight and volume from the material master(changed values)
    Appreciate your help on this.
    Thanks & Regards,
    Keshini

    Hi Keshini
    So , lets assume that you have created a sales order for the material MAT1 and it has Net weight 5kg & Gross weight 6kg ,Now the sales order status is open you have not yet delivered that order and you have changed the Net weight 10kg & Gross weight 14kg. So you want to update that open sales order to Net weight 10kg & Gross weight 14kg. If that is the problem then just go to VA05 and give the material (MATNR) and check the box open sales orders then you will get the open sales orders then in the menu you select to carryout the net weight & gross weight there you can change .and then you can do delivery then the updation will take place in the Net weight & Gross weight also
    Regards
    Srinath

  • Planned delivery time in Scheduling agreement and MRP

    Hello,
    Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
    Regards, jaana

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • Planned delivery time in purchase agreement (contract)

    Hello,
    When I create a material contract for a material master without an existing info record, the system leaves the field "planned delivery time" blank. When there is already an inforecord for the material, the system copies the planned delivery time from the inforecord in the contract.
    Can anybody explain why? And how to prevent this?
    Thanks,
    Isabel

    Hi,
    If you enter planned delivery time in Info record, it automatically copied to contract.  Make the planned delivery time in info record as blank.  Or you can remove the planned delivery time in Contract when creating it
    ~Thanks!
    Rajesh

  • Planned delivery time in purchase agreement

    Hello,
    When I create a material contract for a material master without an existing info record, the system leaves the field "planned delivery time" blank. When there is already an inforecord for the material, the system copies the planned delivery time from the inforecord in the contract.
    Can anybody explain why? And how to prevent this?
    Thanks,
    Isabel

    deleted

  • User exit for copying planned delivery time

    Hi
    My requirement is to copy the value in field Planned delivery time from contract to planned delivery time field in MRP2 view in material master. Please let me know which user exit or enhancement may be used for the purpose.
    TIA.

    Hi
    Check BADI_MATERIAL_CHECK
    Regards
    Sanil

  • Planned delivery time & GR Processing time

    Hi all,
      I would require a clarification on this one,
    Scenario - After an MRP run, the Purchase Requisitions for materials are generated & the order release date is being calculated by subtracting only the planned delivery time from the requirement date. But to the best of my knowledge
    "Purchase Order release date = Requirement date - (Planned delivery date + GR Processing time)"
    Solution required - Is my understanding correct & if so, where should i make the changes to include the GR processing time for the computation of order release date. Is there any other field which i need to add to my PO release date computation. An early response in this regard would be highly appreciated.
    Regards,
    Vivek

    Hi,
    The order release date simply takes the requirement date and subtracts the planned delivery period (as you have indicated).
    But this has ALREADY taken the GRP time into account and so you don't nedd to (and shouldn't) add it in again.
    For example,
    Material A has a Planned delivery period of 10 days and a GRP time of 3 Days. The date that the production order is to be started is 30 July.
    The MRP run sees the requirement date as 30 July but it also sees the 3 days GRP and so it asks for the item to be delivered 3 days prior to this date (27th July).
    The planned delivery period is 10 days and so the PO will need to be created by the 17th July. 
    So the dates are correct and do not need any further changes.
    If you were to take the GRP time off again this would be wrong.
    Steve B

  • TLD or Planned delivery Time

    Hi Experts,
    Normally we CIF planned delivery time from R/3 to Apo. Instead of planned delivery time, shall we use Transportation lead time offset to be maintained on the transporttaion line itself in APO?, which one is better?.is Both (TLD or PDT) are same.
    Regards,
    Madhu

    Hi
    As I mentioned it depends on your business case in which cases you want to create a TL.
    In our case we only create TL in intercompany planning scenario, in third party supplier we do not create TL and we directly user planned delivery time which is getting CIF from ECC system.
    I think both should able to server the respective purpose. Only one clue for you lead time defined TL will overwrite the planned delivery time in ECC during planning run
    Thanks
    Amol

  • Calculating the planned delivery time in calendar days or working days

    Hi,
    It seems that there is a way to calculate the planned delivery time in calendar days instead of working days.
    When I use the "Planned delivery time calculation" (WPDTC), in Evaluation Options, I got the message :
    "Note that follow-on applications are currently interpreting the planned delivery time as calendar days.
    If they should be interpreting the planned delivery time as working days, you need to modify these applications. If the planned delivery time should be calculated in working days, there needs to be a factory calendar in Customizing with the calendar ID Country of vendor."
    When MRP create a PR -with MDBT, MD03 or MD01- I want my Planned delivery time to be in working days.
    I can't manage to make that "If the planned delivery time should be calculated in working days, there needs to be a factory calendar in Customizing with the calendar ID Country of vendor."
    I would appreciate your help.
    Thanks
    PYR

    Hi,
    I understand that it makes sense that vendors calendar has to be different (compared to my plant).
    But, I still don't understand why in the SAP help, they say "If the planned delivery time should be calculated in working days, there needs to be a factory calendar in Customizing with the calendar ID Country of vendor."
    It seems that planned delivery time may follow a calendar.
    Thanks,
    PYR

  • Consider planned delivery time field in MRP Areas

    Hi,
    I would like to know if the "Consider Planned Delivery Time" field in the MRP areas is taken into the scheduling of materials during MRP run? From the help documentation, it seems to be yes. Otherwise the system will take the Planned Delivery Time from the Plant level. May I ask how we can tick this field for all materials? We are currently in the process of activating the MRP areas in our system. Before, we didn't use the MRP areas but we think the need for it has arrived. Is there a mass maintenance tool to do this? Or do I have to use LSMW? Thanks!
    Regards,
    Chester

    Hello Chester
    If you flag the field "consider planned delivery time" the planned delivery time defined on the MRP area will be considered by MRP. You should tick it for all the materials if the value from the MRP area should be considered.
    Also, the report RMMDDIBE can be used for mass processing of MRP areas.
    BR
    Caetano

  • Planned delivery time Pickup from inforecord not material master data

    Hi,
    Currently the delivery dates of the orders are calculated with the delivery time which is marked in MM02. Since the purchasing integrates this information in the info record, we want the delivery date to be calculated with delivery time of the info record instead of calculating it with the data of MM02
    Please suggest any config.
    Thanks
    Shital D

    Hi,
    Try like this, ME21N, put the vendor, material , plant and other Org elements, hit enter, and check P.O what is the planned delivery time that you are seeing, also is the same PIR also appearing in the P.O when you scroll to the right?
    Also note.. that system might be picking 3, maybe saturday and sunday holiday is coming, check that too
    Regards
    Shailesh
    Edited by: Shailesh Rajan on Jul 7, 2011 7:00 PM

  • Udating material master with changed planned delivery time in contract

    Hi experts ,
    My question is while we are changing the planned delivery time in the contract we need to udate the same in the material master table . so how to update the material master table with new planned delivery time. Is there any FM exits to udate it and if it is then how to use it.
    thanks
    Anshuman

    Hi Madhu ,
    You are right we can use BAPI_MATERIAL_SAVEDATA but if we use it then we have to use BAPI_COMMIT also to make sure that all the changes are saved completly and if we do BAPI_COMMIT then it maye commit all the task which is in queue and it need to update later. So it is again a issue .
    Thanks
    Anshuman

  • Planned deliv. time in material and vendor master.

    Hi,
    in material and vendor master there is the field "Planned deliv. time".
    How are these hierarchical organized?
    Best regards

    Hi
    Planned Delivery Time are maintained in 3 places
    1)In Material Master,  MRP 2 View
    2)In Vendor Master, Purchasing Data View
    3) In Info Record, Purchasing Org View
    Actually, In Vendoe master what Pln.Del.Time you are giving is common for all the material supplied by the vendor....
    In Material Master, MRP View what you are maintaining....based on this thing only, the "Replinshment Lead Time" of MRP Planning is calculated...( RLT is nothing but PR Processing time + Planned delivery Time + GR Processing time)
    In Info Record What you are maintaining, it will be copied to PO
    Rewrd if useful
    Regards
    S.Baskaran

Maybe you are looking for