Planned delivery time in material master

Is planned delivery time in material master considering holidays ? I mean when I say 7 days, is it one week and 2 days or only one week ?

Dear Balaji,
If you push F1 when your mouse is set on that field you will see that help says that PDT is defined as calendar days. However, you can carry out some changes:
http://www.sap-img.com/materials/planned-delivery-time-as-workdays.htm
About meaning of PDT:
http://www.sap-img.com/production/calculation-to-determine-the-delivery-date-and-release-date.htm
In addition to that link, you can use safety time as well (with this setting you can pull back in time the requested availabilty date during MRP run). You can also use PDT in info records if you have several source of supple for one material.
BR
Csaba

Similar Messages

  • Automatic updation of planned delivery time in material master.

    Dear all,
    Is it possible to update the Planned delivery time in the material master automatically by the system based on goods receipt date.
    what customisation needs to be done.
    Regards,
    Dayanand

    It is not dynamic field so you  can't retrive automatically.

  • Planned Delivery Time from Material Master instead of PIRs

    Hi SAP Gurus,
    Do you know if there is a way to have MRP look at the Planned Delivery Time from the Material Master (MRP 2 tab) instead of the PIR?
    We would like to create global PIRs with a PDT of 1 and have the Material Master PDT set to a different number (example 5).  So when MRP runs it will read 5 instead of 1.
    Any additional information is appreciated.
    Thank you
    -nic

    Hi Nicholas,
    In Standard SAP will consider Planned delivery time maintained in Inforecord and than time maintained in Material master. Inforecord has higher priority than material master. When a requisition is manually created, the Planned Delivery date will always be taken from the material master.
    For MRP you can make setting OMDT for your plant or MRP group to determine planned delivery time.
    Deactive the flag 'Scheduling according to purchasing info record or agreement' in Customizing (Plant or MRP group). and test the same.
    Regards,
    R.Brahmankar

  • Planned delivery time in Scheduling agreement and MRP

    Hello,
    Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
    Regards, jaana

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • Udating material master with changed planned delivery time in contract

    Hi experts ,
    My question is while we are changing the planned delivery time in the contract we need to udate the same in the material master table . so how to update the material master table with new planned delivery time. Is there any FM exits to udate it and if it is then how to use it.
    thanks
    Anshuman

    Hi Madhu ,
    You are right we can use BAPI_MATERIAL_SAVEDATA but if we use it then we have to use BAPI_COMMIT also to make sure that all the changes are saved completly and if we do BAPI_COMMIT then it maye commit all the task which is in queue and it need to update later. So it is again a issue .
    Thanks
    Anshuman

  • Planned delivery time Pickup from inforecord not material master data

    Hi,
    Currently the delivery dates of the orders are calculated with the delivery time which is marked in MM02. Since the purchasing integrates this information in the info record, we want the delivery date to be calculated with delivery time of the info record instead of calculating it with the data of MM02
    Please suggest any config.
    Thanks
    Shital D

    Hi,
    Try like this, ME21N, put the vendor, material , plant and other Org elements, hit enter, and check P.O what is the planned delivery time that you are seeing, also is the same PIR also appearing in the P.O when you scroll to the right?
    Also note.. that system might be picking 3, maybe saturday and sunday holiday is coming, check that too
    Regards
    Shailesh
    Edited by: Shailesh Rajan on Jul 7, 2011 7:00 PM

  • Planned deliv. time in material and vendor master.

    Hi,
    in material and vendor master there is the field "Planned deliv. time".
    How are these hierarchical organized?
    Best regards

    Hi
    Planned Delivery Time are maintained in 3 places
    1)In Material Master,  MRP 2 View
    2)In Vendor Master, Purchasing Data View
    3) In Info Record, Purchasing Org View
    Actually, In Vendoe master what Pln.Del.Time you are giving is common for all the material supplied by the vendor....
    In Material Master, MRP View what you are maintaining....based on this thing only, the "Replinshment Lead Time" of MRP Planning is calculated...( RLT is nothing but PR Processing time + Planned delivery Time + GR Processing time)
    In Info Record What you are maintaining, it will be copied to PO
    Rewrd if useful
    Regards
    S.Baskaran

  • Report with material number and planned delivery time

    Is there any standard report with material number and planned delivery time ?

    Hi,
    I do not know any standard report. Please try SE16 + MARC...
    BR
    Csaba

  • Planned delivery time of an externally procured material

    Hello All
         I am having a scenario wherein some of the raw materials are send out for subcontracting & in return we get a semi-finished, if suppose we send raw materials for 500EA of SF then we get back initially 50EA after 10 days & then 50EA after every 7 days, the initial lot of 50EA we get in 10EA because the vendor has to setup the line for production at his end. How can i map this into the SAP system as in how shall i decide the planned delivery time of this SF.
           Please clarify the entire process as in how it shall be mapped in SAP. Your inputs are highly appreciated and required.
    Thanks in Advance
    Regards,
    J K Tharwani

    Thanks for your valuable inputs dear,
              I agree that in purchase order itself we can maitain delivery schedules manually as per the delivery given by subcontractor.       
              I am having a concern here, can't we simulate this in SAP so as Schedule lines are automatically created as per the order quantity & as per the delivery time for a given qty. Is there any functionality in SAP so that we can map this scenario as per the requirement, there would be definitely this provision in SAP, do throw some more light on this. Your valuable inputs & guidance are highly appreciated.
              Thanks again for your inputs.
    Regards,
    J K Tharwani

  • System is not considering Planned Delivery time

    Dear Gurus,
    As iam planning for the month of January and running the MRP,schedulelines are getting generated but system is not condering Planned Delivery time maintained in the material master ie. 7days.Following is the example:
    I have a FERT-X with a component A-1PC in its BOM and its planned delvery time from vendor is 7 Days.If iam running the MRP on 13/12/2010 for FERT-X  100 PCS for January1,2011 then the schedule lines are getting generated for for component A is on 01/01/2011.But PDT is maintianed in material master is 7 days and same has been maintianed in vendor inforecord.But system is not considering it.
    Kindly help to resolve the issue.
    With Regards.

    I have one ROH which has two different vendors.
    Two scheduling Agreemnt with target qty 100000 kg each.
    Two different Vendor info record with Min. order qty maintained.V1-1000Kg,V2-6000Kg.
    One source list with two vendors and with respective scheduling agreement.
    Quota arrangement is there in which SOB is maintiained 50:50.
    I hv the requirement of 3084 kg of ROH.
    I run the MRP and two diiferent schedule lines are getting generated with 50:50 qty as mentioned in Quota arrangement.
    Not considering the minimum order qty maintiained in vendor info record.
    The above process is correct
    Only One doubt In Quota Arrangement?
    IS two schedule line is created after MRP run?
    Generally System will  select a vendor Whose Quota value is less
    quota rating   = quota base quantity + quota-allocated quantity/ quota
    Edited by: Sundaresan . E. V on Dec 14, 2010 3:26 PM

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • How planned delivery time effects delivery creation?

    Dear All,
    Some time before, while placing order thro' CRM, we came across a typical error (hard error).
    "date (11/12/2011) lies afterthe end of validity calendar". 
    we could not place order in CRM but in SAP we could create save the order despite of same error but soft. However system didn't allow to create delivery for same order & same error message populated"
    Later it was found that it is because for material  " Planned Deliv. Time  maintained for say "X "days in material master MRP2 view" & was corrected.
    How planned delivery time effects delivery creation?
    For material even though planned delivery time was maintained as say for 500 days, sales order requested delivery date & delivery date in order schedule line got determined as order date (Considering avaliability of funds & material).
    i.e order date/req. delivery date/delivery date in schedule line are same as date on which order is placed.
    Regards
    Suhas W

    Hi,
    Extended your factory calender in SCA3.
    Regards,

  • Planned delivery time

    Hi,
    I have created a sale order on 1/7/2009 with a material which has planned delivery time of 4 days.
    Now when I go to the schedule lines screen I see that the delivery date corresponding to the confirmed quantity is 1/8/2009.
    Why is not SAP taking the 4 days into considerations while determining the delivery date?
    Please see below the screen shots:
    Scheduling configuration in material master:
    [http://i40.tinypic.com/14b2fyc.jpg]
    Schedule lines screen shot:
    [http://i44.tinypic.com/9pxkzc.jpg]
    Sincerely.
    Ketan

    Hi,
    You seems confused with planned delivery time in MRP 2 view of material master to Sales order delivery date.
    Material master Planned delivery time is for the material which is procured externally  through PR -- PO process.
    In Sales order the delivery date is with respect the ATP--Avalible to Promise.
    If the stock is avalible in the storage location on the date of Sales order creation, then system will consider the delivery date an the basis of confirmed qty in the sales order. You can check in CO09 for confirmed qty.
    rgds
    gsc

  • Planned Delivery Time of Schedule Line

    Dear Gurus,
    I have done the setting in SPRO >MM>PURCHASING>PP>PROCESSING TIME from 1 day to 0 day bt still  it is picking up one day for schedule lines.There is 0 days planned delivery time in VendorMaster,Material Master,Vendor info record.
    I hv run the MRP  on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    With Regards.

    I hv run the MRP on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    During MRP, System will do the backward scheduling... from FG reqmt to Raw material,
    Compare the order start date  of header material in plan order or in prdn order  with the reqmt date for  the schedule line material - Is any difference in days?

  • Schedule Agreement - Planned delivery time

    Can you still use planned delivery time when using Scheduling Agreements?  Or does this field need to be set to 0 for the delivery lines to get created properly when using JIT/FRC schedules?  If we cannot use Planned delivery time, is there another field that can be used to hold the Vendors lead time.  We want to take this into consideration when determining the end date of the Scheduling Agreement.

    Hi,
    the planned delivery time field on the material master is designed to be used when it cannot find the correct data from the info record. It should always contain the planned delivery time that should be applied if the vendor is not specified.
    the same field on the info record should contain the planned delivery period for the appropriate vendor.
    This field does not have to be 0 if you are using JIT etc.
    Steve B

Maybe you are looking for

  • Calendar doesn't sync: Zire 31 & Windows XP Pro

    Friends, this is similar to another posting but I couldn't understand the replies.  I got a new PC at work, installed my Palm software and successfully synced, except Calendar data did not transfer to/from Outlook.  There were some other oddities too

  • Org.apache.axis2.AxisFault: samples.quickstart.service.axiom.StockQuoteServ

    I am trying to run the axiom StockQuoteService sample as provided in the axis2-1.2 download. the AXIOMClient.java runs fine under tomcat 6.x and jre 6.x on my PC. After that I try to deploy the StockQuoteService.aar file on the tomcat running in a so

  • QuickTime doesn't support mpeg4

    My quicktime player tells me that it doesn't support mpeg4 when I try to play an mpeg4 on my home xp system. What should I do.

  • Footnotes in WAD

    Hi, Can we make footnotes in the WAD to be dynamic? The footnotes are pertinent to the applicable month and are maintained by the business user.   we want to make sure that we will be able to link the footnotes to the report and report period. Can we

  • Archived log on standby db

    I have created a psuedo standby. I want to know the latest sequence number of the redo that was applied on the standby. How to get that information? Thanks