Planned delivery time in Scheduling agreement and MRP

Hello,
Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
Regards, jaana

This can be customized in
SAP Customizing Implementation Guide
-> Production
--> Material Requirements Planning
---> Planning
> Procurement Proposals
> Define External Procurement
Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

Similar Messages

  • Planned Delivery Time is included Saturday. and Sunday?

    Dear Guru,
    Please kindly advice me about Planned Delivery Time in Days in the MRP View.
    Is it include Saturday and Sunday?
    If my calendar is not work on  Saturday and Sunday.
    Thank you very much.
    Saiya

    System calculates with help of factory calender. if you maintaned saturday and sun day as public holidays then system will not considered for planned delivery time.

  • Planned elivery time in scheduling agreement

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"".  System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) .r processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 11.07.2008
    Please Guide . How can i correct this.
    Regards
    Rahul Bhardwaj

    dear colleagues,
    please check in OPPQ , external procurement,  and set the flag 'scheduling'
    best regards

  • Planned Delivery Time of Schedule Line

    Dear Gurus,
    I have done the setting in SPRO >MM>PURCHASING>PP>PROCESSING TIME from 1 day to 0 day bt still  it is picking up one day for schedule lines.There is 0 days planned delivery time in VendorMaster,Material Master,Vendor info record.
    I hv run the MRP  on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    With Regards.

    I hv run the MRP on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    During MRP, System will do the backward scheduling... from FG reqmt to Raw material,
    Compare the order start date  of header material in plan order or in prdn order  with the reqmt date for  the schedule line material - Is any difference in days?

  • Planned delivery time in purchase agreement (contract)

    Hello,
    When I create a material contract for a material master without an existing info record, the system leaves the field "planned delivery time" blank. When there is already an inforecord for the material, the system copies the planned delivery time from the inforecord in the contract.
    Can anybody explain why? And how to prevent this?
    Thanks,
    Isabel

    Hi,
    If you enter planned delivery time in Info record, it automatically copied to contract.  Make the planned delivery time in info record as blank.  Or you can remove the planned delivery time in Contract when creating it
    ~Thanks!
    Rajesh

  • Planned delivery time in purchase agreement

    Hello,
    When I create a material contract for a material master without an existing info record, the system leaves the field "planned delivery time" blank. When there is already an inforecord for the material, the system copies the planned delivery time from the inforecord in the contract.
    Can anybody explain why? And how to prevent this?
    Thanks,
    Isabel

    deleted

  • Scheduling agreement and MRP

    Hi,
    do you agree with the following statement ?:
    "MRP cannot create automatically scheduling agreement but only schedule lines"
    Regards

    This is correct !
    Regards
    Bhavesh Mistry

  • Planned Delivery time in case of Scheduling Agreement

    Hi All,
    Does system consider the planned delivery time in case of Scheduling Agreement for Vendor like in normal Purchase order and requisition?
    I am doing the MRP run, but system is taken planned delivery time into consideration. I have one material that is Inhouse produced material for plant X and Y Plant needs this material for further making of a finished goods.
    Y plant have scheduling agreement for STO from plant X. After MRP Run required Delivery date in plant X for Material is same as plant Y. but from Plant X to Y, it take 4 days to reach. So Ideally in Plant X this delivery date should be less than 4 days as plant Y.
    Please look into the issue and reply if you have some answers.
    Thanks
    Pavan

    Hope you have maintained different Planned Delivery times in plant X and Plant Y as per your requirement. For procurement in Plant Y the system would consider the planned delievry time maintained in Plant Y. If you want in-house production time to be considered with Basis date sheduling during MRP run in PLant X then enter the in-house production time approprietely. Else if ou want to consider the exact routing times then consider Lead time scheduling in plant X.
    If the above are maintained properly then you should get the desired result.
    Regards
    Ramanujan

  • Planned Delivery Time from Material Master instead of PIRs

    Hi SAP Gurus,
    Do you know if there is a way to have MRP look at the Planned Delivery Time from the Material Master (MRP 2 tab) instead of the PIR?
    We would like to create global PIRs with a PDT of 1 and have the Material Master PDT set to a different number (example 5).  So when MRP runs it will read 5 instead of 1.
    Any additional information is appreciated.
    Thank you
    -nic

    Hi Nicholas,
    In Standard SAP will consider Planned delivery time maintained in Inforecord and than time maintained in Material master. Inforecord has higher priority than material master. When a requisition is manually created, the Planned Delivery date will always be taken from the material master.
    For MRP you can make setting OMDT for your plant or MRP group to determine planned delivery time.
    Deactive the flag 'Scheduling according to purchasing info record or agreement' in Customizing (Plant or MRP group). and test the same.
    Regards,
    R.Brahmankar

  • Effects of Planned delivery time

    Hi All,
    I have the following Scenario.
    The Scenario is I have agreed delivery time by the vendor by which he promises me to deliver the goods. So i need to make PO automatically cancel after that delivery grace period. What I did was i entered the Greed period of time in Planned delivery time of the article and vendor master but i find no effect taking place.
    If the case is so what is the exact use of planed delivery time in article and vendor masters.
    And how can i make PO cancel automatically after the Grace period expires so that i  cannot receive goods from the vendor.
    Please suggest me guys.
    Thanks in Advance.
    Regards,
    Madhan Raj. C

    Hi,
    I guess automatic cancel of PO after certain grace period does not exists in SAP.
    Planned delivery time is the time period given by vendor, stating that he will deliver goods no later than this date.
    Forum Folks can add more
    BR,
    Krishna

  • MRP - Auto creation of del schedule lines based on planned delivery time

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Nirav,
    This subject has been discussed repeatedly in this and other forums.  I must assume that you overlooked the rules of engagement, which state that you should first search the forums and other public sites, before posting questions here.
    Standard SAP MRP cannot be made to generate multiple items in a Purchase requisition.  The functionality you seek is usually achieved when converting purchase reqs to Purchase orders, where many single purchase reqs can be adopted into a single Purchase order.
    You also might want to investigate use of Vendor Scheduling agreements.
    Best Regards,
    DB49

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • Planned Delivery time not considered after MRP run for scheduling

    Dear All,
    After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.
    Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.
    Any idea as to what might have gone wrong?
    thx for your help in advance.
    Rgds,
    Ranjeet

    Hi,
    Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.
    Rgds,
    Ranjeet

  • Schedule Agreement - Planned delivery time

    Can you still use planned delivery time when using Scheduling Agreements?  Or does this field need to be set to 0 for the delivery lines to get created properly when using JIT/FRC schedules?  If we cannot use Planned delivery time, is there another field that can be used to hold the Vendors lead time.  We want to take this into consideration when determining the end date of the Scheduling Agreement.

    Hi,
    the planned delivery time field on the material master is designed to be used when it cannot find the correct data from the info record. It should always contain the planned delivery time that should be applied if the vendor is not specified.
    the same field on the info record should contain the planned delivery period for the appropriate vendor.
    This field does not have to be 0 if you are using JIT etc.
    Steve B

  • Order of delivery schedule line counter at schedule agreements from MRP run

    Currently we are using schedule agreements for our long term external suppliers, but we are facing a problem with the order of new delivery schedule lines created during MRP run.
    Because of master data settings like, lot size, rounding value, plan delivery time and planning time fence to set as firm new requirements, multiple schedule lines are created with no order for schedule line counter.
    Does anyone is aware of a BADI, user exit or customizing control to have this schedule line counter in order?
    Thank you
    Daniel Guillen
    IT
    Skyworks Inc.

    Hi,
    Pls put this query in SD fourms  and get immly help because this is technical fourms.
    Anil