Planned delivery time of an externally procured material

Hello All
     I am having a scenario wherein some of the raw materials are send out for subcontracting & in return we get a semi-finished, if suppose we send raw materials for 500EA of SF then we get back initially 50EA after 10 days & then 50EA after every 7 days, the initial lot of 50EA we get in 10EA because the vendor has to setup the line for production at his end. How can i map this into the SAP system as in how shall i decide the planned delivery time of this SF.
       Please clarify the entire process as in how it shall be mapped in SAP. Your inputs are highly appreciated and required.
Thanks in Advance
Regards,
J K Tharwani

Thanks for your valuable inputs dear,
          I agree that in purchase order itself we can maitain delivery schedules manually as per the delivery given by subcontractor.       
          I am having a concern here, can't we simulate this in SAP so as Schedule lines are automatically created as per the order quantity & as per the delivery time for a given qty. Is there any functionality in SAP so that we can map this scenario as per the requirement, there would be definitely this provision in SAP, do throw some more light on this. Your valuable inputs & guidance are highly appreciated.
          Thanks again for your inputs.
Regards,
J K Tharwani

Similar Messages

  • Planned delivery time Pickup from inforecord not material master data

    Hi,
    Currently the delivery dates of the orders are calculated with the delivery time which is marked in MM02. Since the purchasing integrates this information in the info record, we want the delivery date to be calculated with delivery time of the info record instead of calculating it with the data of MM02
    Please suggest any config.
    Thanks
    Shital D

    Hi,
    Try like this, ME21N, put the vendor, material , plant and other Org elements, hit enter, and check P.O what is the planned delivery time that you are seeing, also is the same PIR also appearing in the P.O when you scroll to the right?
    Also note.. that system might be picking 3, maybe saturday and sunday holiday is coming, check that too
    Regards
    Shailesh
    Edited by: Shailesh Rajan on Jul 7, 2011 7:00 PM

  • Capacity Planning for External Procurement Material

    Hi, I have the following requirements.
    MRP Scheduling is getting executed material level (material no, plant) with scheduling type 2 which means lead time scheduling using MD02 Transaction Code. This is works fine for the Inhouse Product. In order to achieve lead time the functional team has maintained the necessary routing/workcenter configs.
    The business needs the same functionality "Capacity requirements calculation" for the external procurement material. Business is willing to maintain routing/workcenter config.
    Currently standard program (MD02) is not considering the Capacity planning for the external Procurement material.
    Could you please suggest is it can be controlled through programming.
    Kindly suggest the function modules for Capacity Planning - materialwise, plantwise.
    Please suggest.
    Thanks
    Giri

    Hi Giri
        I think the requirement is not mentioned clearly. Capacity is required only if the material is assembled/produced in house.
    Anyway try this. Set the Procurement type to X in the MRP views in material master. You might have to define your custom material type so that it does not force the procurement type to F. Try the feature called "Quota arrangement". The idea is to define the material in such a way that it can be procured externally or produced in house. With quota arrangement you can say what % has to be bought and what % to be produced in house. If it is produced in house then you can have capacity requirements.
    Regards
    Pragnesh

  • MD02 - Capacity Requirement Plan for External Procurement Material

    Hi, I have the following requirements.
    MRP Scheduling is getting executed material level (material no, plant) with scheduling type 2 which means lead time scheduling using MD02 Transaction Code. This is works fine for the Inhouse Product. In order to achieve lead time the functional team has maintained the necessary routing/workcenter configs.
    The business needs the same functionality "Capacity requirements calculation" for the external procurement material. Business is willing to maintain routing/workcenter config.
    Currently standard program (MD02) is not considering the Capacity planning for the external Procurement material.
    Could you please suggest is it can be controlled through programming.
    Kindly suggest the function modules for Capacity Planning - materialwise, plantwise.
    Please suggest.
    Thanks
    Giri

    Hi Giri
        I think the requirement is not mentioned clearly. Capacity is required only if the material is assembled/produced in house.
    Anyway try this. Set the Procurement type to X in the MRP views in material master. You might have to define your custom material type so that it does not force the procurement type to F. Try the feature called "Quota arrangement". The idea is to define the material in such a way that it can be procured externally or produced in house. With quota arrangement you can say what % has to be bought and what % to be produced in house. If it is produced in house then you can have capacity requirements.
    Regards
    Pragnesh

  • Automatic updation of planned delivery time in material master.

    Dear all,
    Is it possible to update the Planned delivery time in the material master automatically by the system based on goods receipt date.
    what customisation needs to be done.
    Regards,
    Dayanand

    It is not dynamic field so you  can't retrive automatically.

  • Report with material number and planned delivery time

    Is there any standard report with material number and planned delivery time ?

    Hi,
    I do not know any standard report. Please try SE16 + MARC...
    BR
    Csaba

  • Udating material master with changed planned delivery time in contract

    Hi experts ,
    My question is while we are changing the planned delivery time in the contract we need to udate the same in the material master table . so how to update the material master table with new planned delivery time. Is there any FM exits to udate it and if it is then how to use it.
    thanks
    Anshuman

    Hi Madhu ,
    You are right we can use BAPI_MATERIAL_SAVEDATA but if we use it then we have to use BAPI_COMMIT also to make sure that all the changes are saved completly and if we do BAPI_COMMIT then it maye commit all the task which is in queue and it need to update later. So it is again a issue .
    Thanks
    Anshuman

  • Planned delivery time in material master

    Is planned delivery time in material master considering holidays ? I mean when I say 7 days, is it one week and 2 days or only one week ?

    Dear Balaji,
    If you push F1 when your mouse is set on that field you will see that help says that PDT is defined as calendar days. However, you can carry out some changes:
    http://www.sap-img.com/materials/planned-delivery-time-as-workdays.htm
    About meaning of PDT:
    http://www.sap-img.com/production/calculation-to-determine-the-delivery-date-and-release-date.htm
    In addition to that link, you can use safety time as well (with this setting you can pull back in time the requested availabilty date during MRP run). You can also use PDT in info records if you have several source of supple for one material.
    BR
    Csaba

  • Planned Delivery Time from Material Master instead of PIRs

    Hi SAP Gurus,
    Do you know if there is a way to have MRP look at the Planned Delivery Time from the Material Master (MRP 2 tab) instead of the PIR?
    We would like to create global PIRs with a PDT of 1 and have the Material Master PDT set to a different number (example 5).  So when MRP runs it will read 5 instead of 1.
    Any additional information is appreciated.
    Thank you
    -nic

    Hi Nicholas,
    In Standard SAP will consider Planned delivery time maintained in Inforecord and than time maintained in Material master. Inforecord has higher priority than material master. When a requisition is manually created, the Planned Delivery date will always be taken from the material master.
    For MRP you can make setting OMDT for your plant or MRP group to determine planned delivery time.
    Deactive the flag 'Scheduling according to purchasing info record or agreement' in Customizing (Plant or MRP group). and test the same.
    Regards,
    R.Brahmankar

  • Planned delivery time in Scheduling agreement and MRP

    Hello,
    Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
    Regards, jaana

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • Planned delivery time

    Hi,
    I have created a sale order on 1/7/2009 with a material which has planned delivery time of 4 days.
    Now when I go to the schedule lines screen I see that the delivery date corresponding to the confirmed quantity is 1/8/2009.
    Why is not SAP taking the 4 days into considerations while determining the delivery date?
    Please see below the screen shots:
    Scheduling configuration in material master:
    [http://i40.tinypic.com/14b2fyc.jpg]
    Schedule lines screen shot:
    [http://i44.tinypic.com/9pxkzc.jpg]
    Sincerely.
    Ketan

    Hi,
    You seems confused with planned delivery time in MRP 2 view of material master to Sales order delivery date.
    Material master Planned delivery time is for the material which is procured externally  through PR -- PO process.
    In Sales order the delivery date is with respect the ATP--Avalible to Promise.
    If the stock is avalible in the storage location on the date of Sales order creation, then system will consider the delivery date an the basis of confirmed qty in the sales order. You can check in CO09 for confirmed qty.
    rgds
    gsc

  • Planned Delivery time not considered after MRP run for scheduling

    Dear All,
    After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.
    Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.
    Any idea as to what might have gone wrong?
    thx for your help in advance.
    Rgds,
    Ranjeet

    Hi,
    Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.
    Rgds,
    Ranjeet

  • Planned delivery time field in sale order

    Dear All,
    During creation of  STO at item level under delivery TAB "planned delivery time" field is showing with edit mode, I want to activate this field for sale order creation / change also. Plz advice how I can do this.
    regards,
    sps.

    Dear SP
    This field is laready there in the MRP-2 of the material master. This is used to calculate the no. of days to procure a material/service externally. Why do you want to activate this in sales order.
    Thanks
    Shuktiz

  • Simoultaneous planned delivery time (MRP)

    Dear Experts,
    I would like to set my MRP for material purchases in order that I can have 2 different lead times, depending on the route (air/sea)
    For instance, if MRP can supply enough material with 1kg or less, then it should take a shorter lead time for it would be air freight than if the minimum necessary was more than 1 kg. (Actual freight lead times= air 60 days, sea 90 days)
    Best regards
    Marco Aramini

    Hello Marco
    It is possible to have different lead times for different vendors on MRP.
    On the customizing transaction OPPQ, choose the option "external procurement" and make sure that the flag "scheduling: info rec agreement" is set.
    With this setting, the planned delivery time is read from the info record or from the scheduling agreement.
    After that, you should create a quota arrangement for both vendors (see note 1508647 for details).
    On the quota arrangement, you can use the minimum and maximum size to define that the source will only be selected if the lot size is higher than 1KG or smaller than 1 kg.
    If have a more complex logic to select the vendor, you can use BAdI MD_MODIFY_SOURCE.
    BR
    Caetano

Maybe you are looking for