Planned Delivery Time of Schedule Line

Dear Gurus,
I have done the setting in SPRO >MM>PURCHASING>PP>PROCESSING TIME from 1 day to 0 day bt still  it is picking up one day for schedule lines.There is 0 days planned delivery time in VendorMaster,Material Master,Vendor info record.
I hv run the MRP  on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
With Regards.

I hv run the MRP on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
During MRP, System will do the backward scheduling... from FG reqmt to Raw material,
Compare the order start date  of header material in plan order or in prdn order  with the reqmt date for  the schedule line material - Is any difference in days?

Similar Messages

  • Planned delivery time in Scheduling agreement and MRP

    Hello,
    Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
    Regards, jaana

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • MRP - Auto creation of del schedule lines based on planned delivery time

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Nirav,
    This subject has been discussed repeatedly in this and other forums.  I must assume that you overlooked the rules of engagement, which state that you should first search the forums and other public sites, before posting questions here.
    Standard SAP MRP cannot be made to generate multiple items in a Purchase requisition.  The functionality you seek is usually achieved when converting purchase reqs to Purchase orders, where many single purchase reqs can be adopted into a single Purchase order.
    You also might want to investigate use of Vendor Scheduling agreements.
    Best Regards,
    DB49

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • Planned Delivery time not considered after MRP run for scheduling

    Dear All,
    After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.
    Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.
    Any idea as to what might have gone wrong?
    thx for your help in advance.
    Rgds,
    Ranjeet

    Hi,
    Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.
    Rgds,
    Ranjeet

  • Schedule Agreement - Planned delivery time

    Can you still use planned delivery time when using Scheduling Agreements?  Or does this field need to be set to 0 for the delivery lines to get created properly when using JIT/FRC schedules?  If we cannot use Planned delivery time, is there another field that can be used to hold the Vendors lead time.  We want to take this into consideration when determining the end date of the Scheduling Agreement.

    Hi,
    the planned delivery time field on the material master is designed to be used when it cannot find the correct data from the info record. It should always contain the planned delivery time that should be applied if the vendor is not specified.
    the same field on the info record should contain the planned delivery period for the appropriate vendor.
    This field does not have to be 0 if you are using JIT etc.
    Steve B

  • Planned Delivery time in case of Scheduling Agreement

    Hi All,
    Does system consider the planned delivery time in case of Scheduling Agreement for Vendor like in normal Purchase order and requisition?
    I am doing the MRP run, but system is taken planned delivery time into consideration. I have one material that is Inhouse produced material for plant X and Y Plant needs this material for further making of a finished goods.
    Y plant have scheduling agreement for STO from plant X. After MRP Run required Delivery date in plant X for Material is same as plant Y. but from Plant X to Y, it take 4 days to reach. So Ideally in Plant X this delivery date should be less than 4 days as plant Y.
    Please look into the issue and reply if you have some answers.
    Thanks
    Pavan

    Hope you have maintained different Planned Delivery times in plant X and Plant Y as per your requirement. For procurement in Plant Y the system would consider the planned delievry time maintained in Plant Y. If you want in-house production time to be considered with Basis date sheduling during MRP run in PLant X then enter the in-house production time approprietely. Else if ou want to consider the exact routing times then consider Lead time scheduling in plant X.
    If the above are maintained properly then you should get the desired result.
    Regards
    Ramanujan

  • System is not considering Planned Delivery time

    Dear Gurus,
    As iam planning for the month of January and running the MRP,schedulelines are getting generated but system is not condering Planned Delivery time maintained in the material master ie. 7days.Following is the example:
    I have a FERT-X with a component A-1PC in its BOM and its planned delvery time from vendor is 7 Days.If iam running the MRP on 13/12/2010 for FERT-X  100 PCS for January1,2011 then the schedule lines are getting generated for for component A is on 01/01/2011.But PDT is maintianed in material master is 7 days and same has been maintianed in vendor inforecord.But system is not considering it.
    Kindly help to resolve the issue.
    With Regards.

    I have one ROH which has two different vendors.
    Two scheduling Agreemnt with target qty 100000 kg each.
    Two different Vendor info record with Min. order qty maintained.V1-1000Kg,V2-6000Kg.
    One source list with two vendors and with respective scheduling agreement.
    Quota arrangement is there in which SOB is maintiained 50:50.
    I hv the requirement of 3084 kg of ROH.
    I run the MRP and two diiferent schedule lines are getting generated with 50:50 qty as mentioned in Quota arrangement.
    Not considering the minimum order qty maintiained in vendor info record.
    The above process is correct
    Only One doubt In Quota Arrangement?
    IS two schedule line is created after MRP run?
    Generally System will  select a vendor Whose Quota value is less
    quota rating   = quota base quantity + quota-allocated quantity/ quota
    Edited by: Sundaresan . E. V on Dec 14, 2010 3:26 PM

  • How planned delivery time effects delivery creation?

    Dear All,
    Some time before, while placing order thro' CRM, we came across a typical error (hard error).
    "date (11/12/2011) lies afterthe end of validity calendar". 
    we could not place order in CRM but in SAP we could create save the order despite of same error but soft. However system didn't allow to create delivery for same order & same error message populated"
    Later it was found that it is because for material  " Planned Deliv. Time  maintained for say "X "days in material master MRP2 view" & was corrected.
    How planned delivery time effects delivery creation?
    For material even though planned delivery time was maintained as say for 500 days, sales order requested delivery date & delivery date in order schedule line got determined as order date (Considering avaliability of funds & material).
    i.e order date/req. delivery date/delivery date in schedule line are same as date on which order is placed.
    Regards
    Suhas W

    Hi,
    Extended your factory calender in SCA3.
    Regards,

  • Planned delivery time

    Hi,
    I have created a sale order on 1/7/2009 with a material which has planned delivery time of 4 days.
    Now when I go to the schedule lines screen I see that the delivery date corresponding to the confirmed quantity is 1/8/2009.
    Why is not SAP taking the 4 days into considerations while determining the delivery date?
    Please see below the screen shots:
    Scheduling configuration in material master:
    [http://i40.tinypic.com/14b2fyc.jpg]
    Schedule lines screen shot:
    [http://i44.tinypic.com/9pxkzc.jpg]
    Sincerely.
    Ketan

    Hi,
    You seems confused with planned delivery time in MRP 2 view of material master to Sales order delivery date.
    Material master Planned delivery time is for the material which is procured externally  through PR -- PO process.
    In Sales order the delivery date is with respect the ATP--Avalible to Promise.
    If the stock is avalible in the storage location on the date of Sales order creation, then system will consider the delivery date an the basis of confirmed qty in the sales order. You can check in CO09 for confirmed qty.
    rgds
    gsc

  • URGENT-Plnned delivery time in schedule

    Hi gurus,
    I have maintained the planned delivery time in material master for which there is a schedule agreement. I have source list and quota for the same too.
    But the planned delivery time has no effect on the schedules created and schedule lines are created on same day as of required day.
    Suppose if required date is 10.04.08 and I have given planned delivery time as 5 then schedules must create on 05.04.08, Which I am not getting.
    Pls help me out as soon Possible if I have missed any Configaration or does it has no effect in Schedule agreement?
    Regards
    Shashi

    Hi,
    Have you added the planned delivery time to the material master after creating the scheduling agreement?
    If so, then this data is not copied to the scheduling agreement. You have to make the entry manually in the scheudling agreement. Also, creation of the delivery schedules does not get affected by the planned delivery time. The delivery scheduls should get generated as soon as the requirement is detected.
    Regards,
    Prashant

  • Planned elivery time in scheduling agreement

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"".  System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) .r processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 11.07.2008
    Please Guide . How can i correct this.
    Regards
    Rahul Bhardwaj

    dear colleagues,
    please check in OPPQ , external procurement,  and set the flag 'scheduling'
    best regards

  • Split delivery for each schedule line

    Hi,
    We have a requirement to split deliveries for each schedule line in the order.
    For example: I have an order with one line item which has 2 schedule lines. If the schedule line date on one is 01/29 & the other is on 01/31, and the delivery due list VL10A is run with a range 01/29 - 01/31, it picks both the schedule line & combines them into one delivery.
    Is there a way by which we can force them to create 2 different deliveries (as it would if the delivery due list was run for each day at a time).
    We created a data transfer routine (deliveries), and populating ZUKRL with schedule line date & that doesnt solve the problem since the routine is triggered once for each sales order line and not for schedule lines.
    SAP reverted back that this is standard SAP behaviour to cumulate all due schedule lines into one delivery, but I would like to know if anyone has any other solution ?
    Thanks in advance!

    First of all you have to use VL10E to create deliveries, since it creates one delivery item for each schedule line.
    Then play with your own delivery role copied from standard profile 0201:
    you can trigger 3 different flags to reach your goal:
    Cumul. Rule: Rule for calculation of quantity to be delivered
         There is a field that contains a cumulated quantity in delivery lists
         with item or schedule line views. The quantity at which the list line
         (document item or schedule line) is delivered is defined in this field
         when it is selected and the delivery process is started in the
         background. The value is a default and can be changed by manually
         processing the delivery list on the item or schedule line level.
    SplitSchedLine: Rule for creating one delivery item per schedule line
        In a delivery list in item view with multiple schedule lines, you can
        decide for the same document item whether you want to generate one
        delivery item per schedule line or whether you want to deliver the
        cumulated quantity of the last schedule lines selected.
    LimitSchedLine:  Allow constraints on schedule line level
         You can use this indicator to limit selection o
         delivery when
         o   Delivery due date and/or
         o   Planned goods issue date and/or
         o   Route schedule
         does not fall within selection range.
    This should help you to solve your problem.
    pls. reward points if helpful
    Regards
    Roberto

  • Planned delivery time of an externally procured material

    Hello All
         I am having a scenario wherein some of the raw materials are send out for subcontracting & in return we get a semi-finished, if suppose we send raw materials for 500EA of SF then we get back initially 50EA after 10 days & then 50EA after every 7 days, the initial lot of 50EA we get in 10EA because the vendor has to setup the line for production at his end. How can i map this into the SAP system as in how shall i decide the planned delivery time of this SF.
           Please clarify the entire process as in how it shall be mapped in SAP. Your inputs are highly appreciated and required.
    Thanks in Advance
    Regards,
    J K Tharwani

    Thanks for your valuable inputs dear,
              I agree that in purchase order itself we can maitain delivery schedules manually as per the delivery given by subcontractor.       
              I am having a concern here, can't we simulate this in SAP so as Schedule lines are automatically created as per the order quantity & as per the delivery time for a given qty. Is there any functionality in SAP so that we can map this scenario as per the requirement, there would be definitely this provision in SAP, do throw some more light on this. Your valuable inputs & guidance are highly appreciated.
              Thanks again for your inputs.
    Regards,
    J K Tharwani

  • Planned delivery time issue

    Hello Experts,
    We have below requirement.
    Created sales order for a particular material. Planned delivery time is picked from info record for that material and PR has been created.
    We are converting PR into PO and the planned delivery time is fine. Now we are updating the ASN from vendor with some prior dates. In MD04, the same got updated. However the sales order still shows the old planned delivery time only. How to get the new planned delivery time  in the sales order based on the ASN updated in PO.
    Example:
    Material: A
    Planned delivery time is 10 in info record
    Created sales order. Planned delivery time in the sales order is 10. PR created with fixed vendor and planned delivery time is 10 days from the date of creation.
    Converted PO.
    Now we received the ASN from Vendor that the vendor will deliver this material in five days. So accordingly we are updating the ASN in PO with delivery date.
    In MD04, we could the new planned delivery time based on the ASN. However sales order delivery still shows the previouls delivery date only.
    How to get the new delivery date in the sales order based on the ASN update?
    Regards
    Bala

    This is not standard SAP logic. Required delivery date on the original line item stays as it was when you issued the order. Then you create a confirmation (ASN) that is relevant to MRP with the updated delivery date. Planning sees the new date and acts accordingly, and also in the order you can see both "old" and "new" (in the confirmation tab).

Maybe you are looking for

  • Why can't I delete groups in my Address Book??

    I'm running Mac OS 10.7.4 on an early 2011 15" MBP. It's not a smart group and I don't use Microsoft Entourage.  I've tried the "delete" key (Fn + delete) and "Edit"->"Delete Group".  It gives me the prompt "Are you sure you want to delete the group

  • How to read a text file through pl/sql

    How to read a text file through pl/sql

  • 50gb free space on disk, but can't copy any more files onto disk.

    Hi, I use my 120gb iPod classic to store films and tv shows on (in disk mode). these occupy round 35gb of the hard disk space and my music takes up around 30gb also. But the problem is I cannot copy any more things into the iPod (not in iTunes) in wi

  • Send To throws error

    Hi, When I open the context menu for any resource in the KM folders and select Send To, it throws me an error. The stack trace is given below : com.sapportals.wdf.WdfException      at com.sap.ip.collaboration.gwui.api.GWUtils.formatMessageWDF(GWUtils

  • Redraw a JPanel during runtime

    Hi there, Im trying to redraw a whole JPanel during runtime. So basically I have this panel: public JPanel panel1 = new JPanel() {      public void paintComponent(Graphics g) {            super.paintComponent(g); }That panel is added to my JFrame dur