Planned delivery time Pickup from inforecord not material master data

Hi,
Currently the delivery dates of the orders are calculated with the delivery time which is marked in MM02. Since the purchasing integrates this information in the info record, we want the delivery date to be calculated with delivery time of the info record instead of calculating it with the data of MM02
Please suggest any config.
Thanks
Shital D

Hi,
Try like this, ME21N, put the vendor, material , plant and other Org elements, hit enter, and check P.O what is the planned delivery time that you are seeing, also is the same PIR also appearing in the P.O when you scroll to the right?
Also note.. that system might be picking 3, maybe saturday and sunday holiday is coming, check that too
Regards
Shailesh
Edited by: Shailesh Rajan on Jul 7, 2011 7:00 PM

Similar Messages

  • Planned delivery time in days is not updating

    Hi Experts,
    planned delivey time in days is not getting updated with BAPI_MATERIAL_SAVEDATA.
    The same type gr_pr_time is getting updated i have commmited it even though it is not reflecting the value.
    i have passed
    la_plantdatax-plnd_delry  =100.
    Please Help.
    Regards,
    Naresh
    Edited by: naresh.k.dasari on Feb 18, 2011 6:31 AM

    Hi,
    This question is not related to APO, i would suggest you to post the thread in ABAP forum.
    However can you check
    can you check whether la_plantdatax-plnd_delry field is 3 charcter or one character field.
    Generally it will be like below.
    la_plantdata-plnd_delry = 100
    la_plantdatax-plnd_delry = 'X
    Regards,
    Srini

  • Planned delivery time of an externally procured material

    Hello All
         I am having a scenario wherein some of the raw materials are send out for subcontracting & in return we get a semi-finished, if suppose we send raw materials for 500EA of SF then we get back initially 50EA after 10 days & then 50EA after every 7 days, the initial lot of 50EA we get in 10EA because the vendor has to setup the line for production at his end. How can i map this into the SAP system as in how shall i decide the planned delivery time of this SF.
           Please clarify the entire process as in how it shall be mapped in SAP. Your inputs are highly appreciated and required.
    Thanks in Advance
    Regards,
    J K Tharwani

    Thanks for your valuable inputs dear,
              I agree that in purchase order itself we can maitain delivery schedules manually as per the delivery given by subcontractor.       
              I am having a concern here, can't we simulate this in SAP so as Schedule lines are automatically created as per the order quantity & as per the delivery time for a given qty. Is there any functionality in SAP so that we can map this scenario as per the requirement, there would be definitely this provision in SAP, do throw some more light on this. Your valuable inputs & guidance are highly appreciated.
              Thanks again for your inputs.
    Regards,
    J K Tharwani

  • Planned Delivery Time from Material Master instead of PIRs

    Hi SAP Gurus,
    Do you know if there is a way to have MRP look at the Planned Delivery Time from the Material Master (MRP 2 tab) instead of the PIR?
    We would like to create global PIRs with a PDT of 1 and have the Material Master PDT set to a different number (example 5).  So when MRP runs it will read 5 instead of 1.
    Any additional information is appreciated.
    Thank you
    -nic

    Hi Nicholas,
    In Standard SAP will consider Planned delivery time maintained in Inforecord and than time maintained in Material master. Inforecord has higher priority than material master. When a requisition is manually created, the Planned Delivery date will always be taken from the material master.
    For MRP you can make setting OMDT for your plant or MRP group to determine planned delivery time.
    Deactive the flag 'Scheduling according to purchasing info record or agreement' in Customizing (Plant or MRP group). and test the same.
    Regards,
    R.Brahmankar

  • Value of planned delivery time in days not updating

    Hello Experts,
    i have created a material using BAPI_MATERIAL_SAVEDATA.
    IN Mrp2 VIEW
    PLANNED DELIVERY TIME IN DAys is not updating
    i have passed
    la_plantdata-plnd_delry =  P_PLND_DELRY.
    la_plantdatax-plnd_delry =  'x'.
    i have commited the work too but the field is not updated
    Please help.
    Thanks & Regards,
    Naresh

    Hi,
    This question is not related to APO, i would suggest you to post the thread in ABAP forum.
    However can you check
    can you check whether la_plantdatax-plnd_delry field is 3 charcter or one character field.
    Generally it will be like below.
    la_plantdata-plnd_delry = 100
    la_plantdatax-plnd_delry = 'X
    Regards,
    Srini

  • Effects of Planned delivery time

    Hi All,
    I have the following Scenario.
    The Scenario is I have agreed delivery time by the vendor by which he promises me to deliver the goods. So i need to make PO automatically cancel after that delivery grace period. What I did was i entered the Greed period of time in Planned delivery time of the article and vendor master but i find no effect taking place.
    If the case is so what is the exact use of planed delivery time in article and vendor masters.
    And how can i make PO cancel automatically after the Grace period expires so that i  cannot receive goods from the vendor.
    Please suggest me guys.
    Thanks in Advance.
    Regards,
    Madhan Raj. C

    Hi,
    I guess automatic cancel of PO after certain grace period does not exists in SAP.
    Planned delivery time is the time period given by vendor, stating that he will deliver goods no later than this date.
    Forum Folks can add more
    BR,
    Krishna

  • System is not considering Planned Delivery time

    Dear Gurus,
    As iam planning for the month of January and running the MRP,schedulelines are getting generated but system is not condering Planned Delivery time maintained in the material master ie. 7days.Following is the example:
    I have a FERT-X with a component A-1PC in its BOM and its planned delvery time from vendor is 7 Days.If iam running the MRP on 13/12/2010 for FERT-X  100 PCS for January1,2011 then the schedule lines are getting generated for for component A is on 01/01/2011.But PDT is maintianed in material master is 7 days and same has been maintianed in vendor inforecord.But system is not considering it.
    Kindly help to resolve the issue.
    With Regards.

    I have one ROH which has two different vendors.
    Two scheduling Agreemnt with target qty 100000 kg each.
    Two different Vendor info record with Min. order qty maintained.V1-1000Kg,V2-6000Kg.
    One source list with two vendors and with respective scheduling agreement.
    Quota arrangement is there in which SOB is maintiained 50:50.
    I hv the requirement of 3084 kg of ROH.
    I run the MRP and two diiferent schedule lines are getting generated with 50:50 qty as mentioned in Quota arrangement.
    Not considering the minimum order qty maintiained in vendor info record.
    The above process is correct
    Only One doubt In Quota Arrangement?
    IS two schedule line is created after MRP run?
    Generally System will  select a vendor Whose Quota value is less
    quota rating   = quota base quantity + quota-allocated quantity/ quota
    Edited by: Sundaresan . E. V on Dec 14, 2010 3:26 PM

  • Planned Delivery time not considered after MRP run for scheduling

    Dear All,
    After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.
    Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.
    Any idea as to what might have gone wrong?
    thx for your help in advance.
    Rgds,
    Ranjeet

    Hi,
    Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.
    Rgds,
    Ranjeet

  • Overruling of planned delivery time in inforecord

    Dear Experts,
    for certain materials we have defined planned delivery Times within the respective material info records.
    This is working as expected.
    However, in certain cases the real delivery time for a material could differ from the one stored in the inforecord (be shorter).
    Is it possible, that the end-user can overrule this planned delivery time during the PO creation, or do we have
    to maintain the info-record for this (keeping in mind, that only as an exception the delivery time should be overruled).
    Thanks for your Support on this and best regards.
    Jan

    Of-course they can change the planned delivery time at the time of PO creation.
    System will fetch the default planned delivery time and delivery date as per defined material master.
    But when you change the planned delivery time (in delivery tab), then system will calculate the delivery date automatically.
    If this will happen very exceptional, then no need to maintain in info record or material master. Just change the planned delivery time at the time PO creation, system will change the delivery date accordingly automatically.

  • Automatic updation of planned delivery time in material master.

    Dear all,
    Is it possible to update the Planned delivery time in the material master automatically by the system based on goods receipt date.
    what customisation needs to be done.
    Regards,
    Dayanand

    It is not dynamic field so you  can't retrive automatically.

  • Report with material number and planned delivery time

    Is there any standard report with material number and planned delivery time ?

    Hi,
    I do not know any standard report. Please try SE16 + MARC...
    BR
    Csaba

  • Planned delivery time not updating real time in apo

    Hi,
    I have a location product which is part of the active integration model.
    The location and product are both available in ECC and APO.
    When i change the value of Planned delivery time in ECC, the changes do not get transfered to APO even after RIMODINI.
    For e.g. the planned delivery time currently is 1 day and it is changed to 3 days, even after doing RIMODINI the changes are not reflected in APO.
    Kindly suggest if somebody has come across this issue earlier.
    Thanks & Regards.
    Santosh Joshi

    Hi Santosh,
    Please check by tcode CFM5 weather material is there in IM or not .
    Also check CFG1 log on R/3 and SLG1 or /SAPAPO/C3 or /SAPAPO/CQ in APO.
    Please confirm.
    Manish

  • Udating material master with changed planned delivery time in contract

    Hi experts ,
    My question is while we are changing the planned delivery time in the contract we need to udate the same in the material master table . so how to update the material master table with new planned delivery time. Is there any FM exits to udate it and if it is then how to use it.
    thanks
    Anshuman

    Hi Madhu ,
    You are right we can use BAPI_MATERIAL_SAVEDATA but if we use it then we have to use BAPI_COMMIT also to make sure that all the changes are saved completly and if we do BAPI_COMMIT then it maye commit all the task which is in queue and it need to update later. So it is again a issue .
    Thanks
    Anshuman

  • Planned delivery time in material master

    Is planned delivery time in material master considering holidays ? I mean when I say 7 days, is it one week and 2 days or only one week ?

    Dear Balaji,
    If you push F1 when your mouse is set on that field you will see that help says that PDT is defined as calendar days. However, you can carry out some changes:
    http://www.sap-img.com/materials/planned-delivery-time-as-workdays.htm
    About meaning of PDT:
    http://www.sap-img.com/production/calculation-to-determine-the-delivery-date-and-release-date.htm
    In addition to that link, you can use safety time as well (with this setting you can pull back in time the requested availabilty date during MRP run). You can also use PDT in info records if you have several source of supple for one material.
    BR
    Csaba

  • Delivery time calculation from purchase info records in MRP

    Hi experts.
    I am using MRP -manual reorder point planning . I have maintain the delivery lead time as 10 days . This material has a info-record for a vendor and a contract also. we maintain the delivery time for the supplier is 20 days in the info records. And a source list is also maintain for this material with reference to the contract and assigned as MRP relevant.
    We run  MRP of this material and create the PR directly.
    we run ME59N for automatic creation of PO also.
    what I see is the delivery time defined in the PR is consider as 10 days from the material master MRP view. But when we convert the PR to PO the delivery time is updated from the inforecord. but the delivery date in the PO line item is not update. It is showing the same delivery date as PR.
    Is it possible to update the delivery date bas eon the info record when we convert from PR to PO automatically?
    regards
    DP

    I don't know the answer to your question, but can point you in another direction; you can set the system up in such a way that already MRP (as per the way you have described that you work) will take into consideration the planned delivery from the Info record/Contract:
    In transaction OPPQ check the "Scheduling: Info Rec/Agreement" box!
    This will make MRP take the planned delivery time from the IR or Agreement, whenever the source (vendor) is identified during the MRP run.
    Regards,
    Mario