Planned elivery time in scheduling agreement

Hi experts
problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"".  System is only taking the G.R processing time.
I have mentioned the Planned delivery time in .
1) Scheduling agreement for 1 day.
2) In material master for one day.
3) In info record 1 day.
e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
a) Planned delivery time = 1 day . B) .r processing time = 3 days.
Now when i run the MRP on 4.07.2008.
Schedule line is generated on - 11.07.2008
Please Guide . How can i correct this.
Regards
Rahul Bhardwaj

dear colleagues,
please check in OPPQ , external procurement,  and set the flag 'scheduling'
best regards

Similar Messages

  • Planned delivery time in Scheduling agreement and MRP

    Hello,
    Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
    Regards, jaana

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • Unnecessary Purchasing Processing Time in scheduling agreement

    According to its business logic, the scheduling agreement is a document  that has  already been  released  by purchasing department,  and  its scheduling lines, that have been created by MRP  are valid for goods receipt without any need for additional purchasing  processing time. However, MRP scheduling incorrectly takes purchasing processing time into account (as defined in the IMG in plant parameters for external procurement - TCODE  OPPQ) when calculating planned availability date. Please advise how to correct this issue.
    Best Regards,
    Itzik Eshed

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • Concept of  just in time in Scheduling Agreements

    hi ,
        can any one pl help out the concept of   "JUST IN TIME "(JIT) , in Scheduling Agreements .

    hi,
    Schedule agreements allow you to have 2 different sets of schedule lines (VBEP-ABART).
    In Standard SAP you can have two sets of schedule lines. One Forecast & the other JIT(just in time)
    Forecast forwards the schedule lines to planning (seen in MD04) and JIT passes them to shipping (VL10).
    They can be identical or different. Typically these are used for component supplier customers (namely Automotive).
    The customer will provide you 4-10 weekly buckets (usually a  Monday date) of future forecast qtys. Also send you 1-2 weeks of individual FIRM ship dates - which are entered on the JIT.
    It comes down to the customer not knowing exactly what they need next week, but they don't want to suprise you with a large order qty, where your lead times are 5+ days. The forecasted qtys they sent last week should account for this. 
    (2) Cumulative Quantities are tracked and influence how the schedule agreement passes requirements to both forecasting and shipping.
    These qtys are sometimes requested by the customer on ASNs. Cumulative qtys reset at year end unless you've got a customer calendar or you've modified standard SAP userexits to not reset. 
    pls reward points if the answer is helpful
    REgards
    Murali

  • Planned Delivery Time of Schedule Line

    Dear Gurus,
    I have done the setting in SPRO >MM>PURCHASING>PP>PROCESSING TIME from 1 day to 0 day bt still  it is picking up one day for schedule lines.There is 0 days planned delivery time in VendorMaster,Material Master,Vendor info record.
    I hv run the MRP  on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    With Regards.

    I hv run the MRP on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    During MRP, System will do the backward scheduling... from FG reqmt to Raw material,
    Compare the order start date  of header material in plan order or in prdn order  with the reqmt date for  the schedule line material - Is any difference in days?

  • BAPI_SCHEDULE_MAINTAIN throws error for time- independent scheduling agreement

    Hi All,
    I get the below error while modifying a stock transport Scheduling agreement in UI5 using BAPI “BAPI_SCHEDULE_MAINTAIN”
    “Scheduling agreements with time-independent conditions are not supported”
    Found a note 1046794-
    "BAPI_SAG_CHANGE (and BAPI_SAG_CREATE) can only treat scheduling agreements with time-dependent conditions. Document conditions are not supported. Therefore, this kind of scheduling agreements cannot be processed. This is a missing functionality”
    To meet some finance requirements, we need to use time-independent conditions in the scheduling sgreement, in order for a custom condition type to be picked up.
    I'd appreciate any advice I can get about how to fix this functionality in the BAPI or alternatively how to link the pricing condition type to the Scheduling agreement document type?
    Thanks so much.

    Link between Time dependent / independent condition and Scheduling agreement document type is in configuration  under SPRO>MM>PURCHASING>SCHEDULING AGREEMENT>DEFINE DOCUMENT TYPES>SCROLL TO THE RIGHT here you find a check box Time-D.C.
    Thanks
    DD

  • Time-indepement Scheduling agreement with reference to contract

    I want to attach pricing procedure to scheduling agreement, so I change LPA SA from time-dependent to time-independent.
    But after the change, I can't reference contract to create SA. error message as below "Contr. release order only allowed for sch. agmts. w. time-dep. conditions".
    How shoud I do to attach pricing procedure and create SA with reference to contract at the same time?

    Hi,
    please see the notes
    160630  - Conditions in scheduling agreement with reference to contract
    1046794 - FAQ: BAPI for outline agreement, questions 1 and 5
    1034912 -  MEMASSSA - document conditions are deleted  
    456691 - FAQ: Price determination in purchasing, question 4
    Regards,
    Edit

  • Planned delivery time in purchase agreement (contract)

    Hello,
    When I create a material contract for a material master without an existing info record, the system leaves the field "planned delivery time" blank. When there is already an inforecord for the material, the system copies the planned delivery time from the inforecord in the contract.
    Can anybody explain why? And how to prevent this?
    Thanks,
    Isabel

    Hi,
    If you enter planned delivery time in Info record, it automatically copied to contract.  Make the planned delivery time in info record as blank.  Or you can remove the planned delivery time in Contract when creating it
    ~Thanks!
    Rajesh

  • Planned delivery time in purchase agreement

    Hello,
    When I create a material contract for a material master without an existing info record, the system leaves the field "planned delivery time" blank. When there is already an inforecord for the material, the system copies the planned delivery time from the inforecord in the contract.
    Can anybody explain why? And how to prevent this?
    Thanks,
    Isabel

    deleted

  • Delivery date is no use in scheduleing agreement.

    We are using scheduling agreement and automatic schduling line for purchasing.
    I already maintain delivery days =2 days and GR day=2days in scheduling agreement.
    after MRP running, I found the delivery days is no use.
    For example.
    requirement date:2009.04.17
    MRP result: scheduling line delivery date=2009.04.15 ( !only GR day=3 is in use)
                       I think the delivery date should be 2009.04.13
    I am using standard TB (daiy lot size and the setting for Scheduling Requirements date := delivery date)
    why is the delivery date  no use in MRP running?
    tks in advance.

    Hi
    If you have used GR processing time in scheduling agreement (example 2 days) if the requirement is on 25.04.2009, then proposed delivery date is for 23.04.2009. GR processing time reduces plans 2 worksday for processing and reduces 2 working days as per factory calender to propose delivery date.
    Planned delivery time will not be considered if the requirement date is more closer than the planned delivery time. You will see an exception message in MRP results for that.
    Regards
    Antony

  • Schedule line in Scheduling Agreement non modifiable

    Hi Friends,
    I'm creating Scheduling Agreement with VA31. The issue is that Schedule line category is coming as non-modifiable. Is it standard that in Scheduling Agreement, you can not overwrite default schedule line category? In customizing for Assign Schedule line categories, Manual schedule line categories are defined, but still I can not overwrite Schedule line category in VA31. Pl suggest what can be the reason. I don't have any ABAPer at my rescue.
    Thank you.

    Sgr,
    For Sch.Line Agreement for component suppliers,we cant change sch.line category as of normal sch.line agreement.
    Based on MRP for Delivery Schedule Types (Field available in Header Data under SALES view) and item category,sch.line category will be determined.
    MRP Indicator
    FORECAST
    JIT
    A
    L1
    CN
    B
    L1
    L1
    C
    BN
    L2
    D
    L1
    L2
    E
    CN
    CN
    However,To decide which type of delivery schedule is currently relevant for requirements and delivery, the system uses the JIT delivery schedule horizon and the material requirements planning indicator in the scheduling agreement header
    Try to change the MRP Indicator available in Header data to match your requirement.
    For more info,try this URL
    Scheduling Agreements for Component Suppliers (SD-SLS-OA) - SAP Library
    Regards
    Logan

  • Price determination date control in Scheduling agreement (ME33)

    <<Do not ask for or offer points>>
    Dear SAP chams,
    I have one doubt at the time of scheduling agreement creation. I am creating scheduling agreement trough t'code ME33. In the same, Select line item, go to item data, go to Additional data. Here the field Pr. Date Cat (Price Determination (Pricing) Date Control) contains the value "5" (i.e. GR date). I want to change this value. How can i change this determination ??...
    Helpful answers will surely be awarded by points.
    Thanks and regard,
    Tarpan Vadaliya
    Edited by: Matt on Feb 27, 2010 10:47 PM

    Hi
    Price determination category 5 cannot be change in scheduling agreement if your document type is time dependent. (See config spro>mm>purchasing>scheduling agreement>define document type. In that you will see a tick for time dependent condition)
    If the config tick is removed then you can change price determination to any other option.
    Regards
    Antony

  • Planned Delivery time in case of Scheduling Agreement

    Hi All,
    Does system consider the planned delivery time in case of Scheduling Agreement for Vendor like in normal Purchase order and requisition?
    I am doing the MRP run, but system is taken planned delivery time into consideration. I have one material that is Inhouse produced material for plant X and Y Plant needs this material for further making of a finished goods.
    Y plant have scheduling agreement for STO from plant X. After MRP Run required Delivery date in plant X for Material is same as plant Y. but from Plant X to Y, it take 4 days to reach. So Ideally in Plant X this delivery date should be less than 4 days as plant Y.
    Please look into the issue and reply if you have some answers.
    Thanks
    Pavan

    Hope you have maintained different Planned Delivery times in plant X and Plant Y as per your requirement. For procurement in Plant Y the system would consider the planned delievry time maintained in Plant Y. If you want in-house production time to be considered with Basis date sheduling during MRP run in PLant X then enter the in-house production time approprietely. Else if ou want to consider the exact routing times then consider Lead time scheduling in plant X.
    If the above are maintained properly then you should get the desired result.
    Regards
    Ramanujan

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • Schedule Agreement - Planned delivery time

    Can you still use planned delivery time when using Scheduling Agreements?  Or does this field need to be set to 0 for the delivery lines to get created properly when using JIT/FRC schedules?  If we cannot use Planned delivery time, is there another field that can be used to hold the Vendors lead time.  We want to take this into consideration when determining the end date of the Scheduling Agreement.

    Hi,
    the planned delivery time field on the material master is designed to be used when it cannot find the correct data from the info record. It should always contain the planned delivery time that should be applied if the vendor is not specified.
    the same field on the info record should contain the planned delivery period for the appropriate vendor.
    This field does not have to be 0 if you are using JIT etc.
    Steve B

Maybe you are looking for

  • Exchange rate differences posting failed due to manual journal entries

    when i run exchange rate differences and try to post the result, system shows "No matching recording found 'journal entry' (OJDT) (ODBC-2028) [message 131-183]" at the bottom panel ane the posting was failed. then i found the problem is actually from

  • Travel management: Input tax for each travel expense

    Dear forumers, I've got the following problem with input tax. I activated input tax for my country variant in Customizing IMG Global settings for each trip provision variant, second option "Input tax per trip expense type". I also put the tax code to

  • Duplex printing in Smartforms

    Hi, How do we use duplex mode printing in Smartfroms? I have tried "D" as print mode. Regards, Naba

  • Want to construct insert statement from all_tab_columns

    I am using Oracle 10GR2 and a new user for plsql I want to write a plsql block or SQL in order to insert some dummy data. I want to use the column list from all_tab_columns and want to construct insert statement EX: I am trying to construct SQL as be

  • A way can auto save an A4 page content to small brochure one

    Hey ALL i am now working on e-publishing ,the problem i meet now is most of customer handle in PDF which is let say A4 size per page , and an convertor need be created and installed on server side to auto convert those PDF to samll page ones , like a