Planned Goods Issue Date adds by 7 days

Hi,
I have an issue with GI date increasing by 7 days when we do picking by vl06p.
Delivery copies with the exact dates of the sale order but once the picking happens the GI date adds up to next 7 days. we  have route schedule active, but the Actual PGI was before the Route Schedule date,even then 7 days are added to GI date
please help

dear Varada,
      check in the material master whether the planned del time  and GR processing time is mentioned in MRP2 view.
May be because of that you are having 7 days difference.
Regards,
Sudhir

Similar Messages

  • New planned goods issue date during delivery creation due to changed route

    Hello All,
    I have defined 2 routes with different values for transit time and transporation lead times. I have configured routes such that in order creation - route A is determined and while delivery creation due to weight group - delivery B is determined.
    Now for Route A i have maintained transit time of 3 days and Transportation lead time of 4 days and for Route B it is 1 day each.
    Delivery scheduling is active for the order type.
    Now when i create the order with a delivery date of say 05/24/2010 then (route A with transit time of 3 days) is determined and the planned goods issue date of 05/21/2010 is in the order.
    Now while creating delivery (Route B which has transit time 1 day) is determined due to the weight group. But the planned goods issue date is still the same 05/21/2010 as in order.
    I am assuming that since the route B has a route of 1 day so the planned goods issue date should be re-determined to 05/23/2010? IS there no scheduling done during delivery creation even though route and subsequently transit time has changed?
    Please let me know the answer to this...
    Thanks
    Shobhit

    Hi ,
    You can use TA - MASS . Enter object type - BUS2032(for sales orders) on initial screen and select sales item data.
    Next screen enter selection fields like sales order no and items. After giving order no and item range , execute and enter all new values for any item data fields. After pressing button "carry out mass change", don't forget to press save button.

  • Actual goods issue date required to be equal to planned goods issue date

    Hi All,
    Can anybody tell me on what basis does the actual goods issue date get determined and what needs to be done if we want to restrict the actuall goods issue date to be equal to the planned goods issue date?
    Avinash

    Avinash,
    Can anybody tell me on what basis does the actual goods issue date get determined
    ???? It is the date that the goods are actually issued from stock, e.g. whatever the date was when the delivery was actually issued, that is the date that is normally written to this field in the delivery.
    what needs to be done if we want to restrict the actual goods issue date to be equal to the planned goods issue date
    That's a pretty restrictive criteria.  Basically, you are telling the warehouse that they are not able to issue the goods early or late.  In companies I have seen, that would constitute a lot of deliveries.  Hope your customers don't need the parts....
    Anyhow, the restriction would have to be against the goods issue transactions being used by the warehouse.  I don't believe there is any standard configuration that creates such a restriction, so it would require custom development.  If you pursue this restriction, make sure you leave yourself some kind of override.
    In many companies, this problem is handled through policy and procedure.  Warehouse manager simply creates a policy about early and late goods issues.  The system will track discrepancies in the case the policy is not followed.
    Best Regards,
    DB49

  • Planning Good Issue date and loading date

    Hi All,
    How I can get the planning Good issue date? I found that the loading date is the same as the planned Good issue date, what's the loading time?
    As what I understanding, loading date + loading time = Good issue date,  But I am not sure how to calculate the planned Good issue date.
    thanks,

    Hello Friend,
    It is determined in Shipping Point configuration.The path is as follows SPRO--> Enterprise Structure >Definition>Logistics Execution-->Define, copy, delete, check shipping point and go in detail the concerned shipping point.

  • Planned Goods Issue date

    Hi,
    We have the system set up as follows:
    When the user enters the delivery date, and then material, route determination occurs. If, for example, there is a lead time of two days on the route, the Goods Issue date is set to two date before the delivery date.
    The user can enter many items.
    If, for different reasons,  the lead time is only a day, the user has to drill down on each item multiple times to change the Goods issue date. We are looking for a quick way, something similiar to "Fast change of delivery date" to change the goods issue date.
    Please share your experineces or proposals on the above problem for the user.
    Thanks in advance,
    Finbarr

    Hi ,
    You can use TA - MASS . Enter object type - BUS2032(for sales orders) on initial screen and select sales item data.
    Next screen enter selection fields like sales order no and items. After giving order no and item range , execute and enter all new values for any item data fields. After pressing button "carry out mass change", don't forget to press save button.

  • Actual Goods Issue date and Planned Goods Issue date

    Dear All
    we are loading the january,08 sales  invoice from the legacy system to SAP system through BDC program.
    for this at the time of PGI we are using Actual GI date as month of January, 08 and keeping planned GI date as the system date and at the time of creating sales order, delivery, we are not changing the material available date, loading date, delivery date, at the item level and system taking automatically based on the current date
    when doing PGI system accepting and creating PGI document and billing also creating based on this delivery.
    But dose it give problem in Inventory managements and FI in future, then what would be the right procedure to uploading the back dated invoices in the system.
    Please give me solution for this issue, or what we are doing is the right procedure.
    Thanks In advance

    For those who might come across this note, the design issue was solved by incorporating Rule Groups.
    Problem:
    Need to have 2 different Date references for 0calday, based on the key figures. For example for Sales key figure date it would reference to Actual GI Date. But, for Intake key figure I needed the date reference to be Planned GI date.
    Solution-- applied to the transfer rules of the desired cube:
    1. In the starndard rule group delete the transfer rule for the appropriate key figures. in this case (sales key figure)
    2. In the same rule group map all time characteristics from the cube to Planned GI date from DSO
    3. Create a new rule group in the transfer rule between the DSO and the Info Cube
    4. In the new rule group, create a new rule for the appropriate key figure i.e. sales
    5. In the new rule group, Map the date/week/month/fiscal period to Actual GI date
    6. save/activate
    This solution eliminates the need for changing the data model, which makes everything almost transparent to the report users.
    Hope this helps someone.
    Edited by: Babak Shafiei on Dec 12, 2008 5:23 PM
    Edited by: Babak Shafiei on Dec 12, 2008 5:24 PM

  • Good Issue date in the Sales order should 1 day difference from the MBDAT

    For the particular customer, i want to have difference of 1 day in between the material availability date & good issue date in the schedule line. As per standard i can't made any changes in route and shipping point. Suppose material availability date in sales order is 22.09.2010 than my good issue date should be 23.09.2010 in the sales order. Any body having any idea how can we handle this case and what are things we need consider impact of this change.
    Regards,
    Srinivas.

    Hi,
    I think you can easily enable this in Route scheduling /Delivery scheduling. You have to maintain the load time and pick/pack time as the total of 8hours. If this is done, then after material availability date, one more day will be added and the final day will be considered as GI date.
    If you dont want to do this, you only have to enable this by Z by using a user exit where you can add one day to the MBDAT and update that in GI date.

  • Proposed goods issue date, material availability date

    Dear All,
    where to configure the goods issue date & material availability date.
    regards,
    Murugan

    Hi,
    For determining the dates, you have to put the availability checking group in the Salesorg/plant view of material master.
    After that you have to put the number of days(planned delivery time,GR processing time) in the MRP2 view
    of material master and if the stock is not availble then the system will determine dates based on these number of days.
    You can also select the default delivery date by putting the number of days in the configuration of sales document type VOV8.
    Reward points if it helps.
    Regards
    Karan

  • Calculation of goods issue date in scheduling agreements with routes

    Hello together,
    i have a problem with the calculation of goods issue date in scheduling agreements when we use route, because the system ignore the days of transit.
    Example:
    We had customized the route 4711 with a transit time of 3 days. This route would be related to a scheduling agreement. But this setting has no influence to the calculation of the goods issue date for the schedules. The same happens with loading date and so on.
    Can anyone give me a tip, which setting is additional necessary?
    Regards
    Andreas Walter

    Hi,
    check the following settings
    1, Route determination Path : IMG>sales and distribution>Basic function>Routes>Route determination
    2, Activate the route Determination for your sales document type in following path :IMG>sales and distribution>Basic function>Routes>Route Schedule Determination-->Schedule with route schedule for sales document type
    3, Maintain Delivery scheduling and transportation scheduling in the following path:IMG>sales and distribution>Basic function>Delivery scheduling and transportation scheduling>Maintain Duration
    Regards
    Senya

  • Goods issue dates are different in sales order & delivery

    Hi,
    We have a situation where in sales order schedule line tab goods issue date is 21.30.2011
    but in delivery the planned GI date is 28.03.2011.
    There are two line item in the sales order & in both the line items all the dates are same.
    Same route is there in sales order & delivery.
    In delivery Item category avalability check Off is Y(Do not check avail. when reporting results of pick.request)
    All the dates(delivery,loading,Transportation planning) are different .
    waiting for responce.
    Thanks In advence
    Susrikant

    goods issue date is 21.30.2011
    What was the Actual GI date in delivery??  This should be the same as schedule line date.
    thanks
    G. Lakshmipathi

  • Calculation of goods issue date in sales order with routes

    Hello Gurus,
    This is my first post on SCN, I'm excited to share a new little problem I have.
    I have configured my routes determination as per our requirements.  For example, I have one route configured in 0VTC such that the transit duration is 1 hour.
    When I create a sales order, I enter that route (1 hour transit.dur) under shipping on the line item.  Then I set a delivery date sometime in the future to test out my config.  Looking at the shipping "Goods Issue Date", I see that the date is 2 hours earlier than my delivery date.  It's supposed to be 1 hour.
    I looked through many forums and found no help on this.  My factory calendar is configured such that all days, including weekends and holidays are production days.
    Please advise at your earliest.
    Thanks,
    Mido

    Hi TW Typewriter,
    Yes, I am changing the date in the "schedule lines" tab for the sales order to a date next week, say May 23, 2014.  When I click on the display "Shipping" info, I see:
    1) Delivery date: 05/23/2014 - 00:00
    2) GI Date: 05/22/2014 - 22:00:00
    The expectation is to have the GI date 23:00:00 since my config for the route on the sales order is for 1 hr of transit time only.
    See attached

  • Want to change Del Date and Goods Issue date in Delivery scdl tab of PO

    Hi Gurus,
    I am in a situation wherein i need to change the Goods Issue date in Delivery schedule tab of Purchase Order and make it equivalent to Delivery date in the same tab.
    Currently the Goods issue date that is taken by default will always be one day after the Delivery date.
    Where is the control for this???
    Regards,
    Trishul

    Hi Jürgen,
    Thanks for your response. You are right. The Process is STO.
    The delivery has not been created as yet.  Everything is happening while creating the PO. The settings are such that the delivery date will be taken by the system automatically by doing the Availability check and simultaneously the goods issue date will be updated. But it will be one day later to the delivery date. But i want this to be same.
    Incase if i change the Goods Issue date manually, this is the message i get "Goods issue cannot be carried out in the past"
    Message no. V1062
    Please let me know if i am not clear.
    Regards,
    Trishul
    Edited by: Trishul Das on Mar 17, 2009 4:09 PM

  • Goods issue date and goods receipt date

    Hi Guys,
                 i was asked to display STO list.They asked me add goods issue date and goods Report date in the o/p columns.So any body can tell me what are the fields for goods issue and goods Receipt date's.?can u guys tell me the Tr code for these fields .?
    Thanks,
    Gopi.

    Hi there,
    I already solve it by myself.
    Actually is i call the initialization twice:
    Company.GetBusinessObject(SAPbobsCOM.BoObjectTypes.oInventoryGenEntry)
    Thats what make this problem happened.
    Sorry.
    Best Regards,
    danny

  • Need to Post Components in Production Order in MB1A through BAPI as Planned Good Issue

    Hi ,
    I have created a Program to upload data s for MB1A through BDC , it works fine, but for huge data s it takes more time.  alternatively created one more Program which updates through BAPI Function Module  "BAPI_GOODSMVT_CREATE".  It works fine , but one issue noted, after posting through Function Module , components are posted as Unplanned Goods Issue.   I need to post the components as " Planned Goods Issue" instead of "Unplanned Goods Issue " . This can viewed through Tcode : C003
    Below are the  inputs passed for BAPI Function Moduel
    **&------Header Contents of bapi Upload-------------------&*
    header-pstng_date = sy-datum.                                              " Posting date
    header-doc_date    = sy-datum.                                             " Document Date
    header-header_txt  = '000001002280'.                                     " Header text
    header-pr_uname   = sy-uname.                                            " User Name
    header-ref_doc_no  = '000001002280'.                                    " Header Ref. Doc. No.
    CONCATENATE sy-uname sy-uzeit c_method INTO  header-ref_doc_no_long SEPARATED BY '-'.  " Refer  Text
    *Item Data
    wa_item-material   = '000000000010000800'.                             "Material
    wa_item-plant      = '3910'.                                              "Plant
    wa_item-stge_loc   = 'WIP'.                                            "Storage Location
    wa_item-move_type  = '261'.                                            "Movement Type
    wa_item-entry_qnt  = '1'.                                                  "Quantity
    wa_item-entry_uom  = 'PC'.                                              "Unit
    *wa_item-res_item  =  1.                                                  "Reservation Item
    *wa_item-reserv_no =                                                      " Reservation Number
    wa_item-batch      = '0000011027'.                                    "Batch No
    *wa_item-mvt_ind   = 'F'.                                                  "Movement Indicator
    *wa_item-stck_type = 'F'.                                                 "Stock Type
    wa_item-orderid    = '000001002260'.                                 "Order ID
    wa_item-prod_date  = SY-DATUM.
    *wa_item-GL_Account = '610000'.                                     "GL Account
    *TRANSLATE wa_item-batch TO UPPER CASE.
    *APPEND wa_item TO it_item.
    c_code = '03'.
    CALL FUNCTION 'BAPI_GOODSMVT_CREATE'
    EXPORTING
    goodsmvt_header       = header
    goodsmvt_code         = c_code
    TABLES
    goodsmvt_item         = it_item
    goodsmvt_serialnumber = it_sno
    return                = return.
    CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'
    EXPORTING
          wait = 'X'.
        commit work and wait.
    Even i tried to pass "Movement Indicator , GL Account etc" , Still not able to fix the issue. Can anyone suggest how to post the Production Order components as "Planned Goods Issue".  I am not sure any other values to be password.
    BR,
    Murali

    I have made something like your :
    * Alimtentation de la BAPI de mouvement de stock MM.
    move : sy-datum        to ls_header-pstng_date ,
            sy-datum        to ls_header-doc_date ,
    * Indique le code mouvement
            '03'            to lw_code.      " 03 normalement, mais je veux que ca plante
    loop at lt_ltap
          into ls_ltap.
       move : ls_ltap-matnr   to ls_item-material ,
              ls_ltap-werks   to ls_item-plant ,
              ls_ltap-lgort   to ls_item-stge_loc ,
              '261'           to ls_item-move_type ,
              ls_ltap-vsolm   to ls_item-entry_qnt ,
              ls_ltap-meins   to ls_item-entry_uom ,
              i_ltak_vb-benum to ls_item-orderid ,
              i_ltak_vb-rsnum to ls_item-reserv_no ,
              ls_ltap-rspos   to ls_item-res_item ,
              ls_ltap-rsart   to ls_item-res_type.
       append ls_item to lt_item.
       clear  ls_item.
    endloop.
    I have to put the reservation number to have it works.
    Fred

  • Incorrect goods issue date

    Hi All,
    When we run availabilty check, the goods issue date falls on non-working days. We have used Enhancement APOSC002 in APO system to populate shipping calender.
    Any suggestions please.
    Thanks,
    Krishna

    > I have maintained goods issue date in delivery and am creating an invoice for the same delivery, when an idoc is getting triggered am not getting goods issue date in invoice idoc the qualifier would be 035..has anyone come across this issue, all the help will be highly appreciated and rewarded..
    Maybe, you can use custom function exit to transfer date to Idoc? Have you looked at this note:  [Note 127178 - Questions about user exits in IDoc INVOIC01 (FI)|https://service.sap.com/sap/support/notes/127178]
    Regards,
    Jakub

Maybe you are looking for