Planned order and purchase req

Hi,
I have created a planned order and a pur req for a product in APO
The ava date for the plnd order is 28.02.2011 and same for the Pur req
The GR processing time was earlier 3 days when the proposals were generated . Now I  see that the user has changed to 1 day in R/3
So there is a diff in the ava date for the planned order and the pu req in APO and R/3
In APO it is 28.02.2011 and in R/3 it is 26.02.2011.
I am able to see this in the CCR
Does this mean that the proposals on getting CIFF'ed to R/3, have picked the new GR processing time from R/3 and adopted the new availablity date in R/3
for this to happen, is a BOM explosion required again or just the CIF of the proposals to R/3 will do or anything  else is influencing this activity?
kindly explain
Thanks,
SS
Edited by: SAPSriman on Feb 24, 2011 10:45 PM

Thanks.  SS

Similar Messages

  • Planned order and Purchase requistion both is generating in MRP

    Dear All,
    At the time of MRP explosion for Finished material, system is generating Planned order and purchase requistion, both,  for detailed material, (e.g. the BOM is a single level BOM). Whereas, I want to generate Purchase requistion for all. I am not getting that for which logic it generating Planned order as well as purchase requisition.
    Pl. explain.
    Thanks,
    Prasun.

    Hi Prasun
    The procurement proposal indicator dependes on the procurement type assigned in material master. If you assign prod Type F it will automatically generate PR. If the procurement type is E or X the system will generate plan order .
    This configured in Plan order type LA means it should be for in house production E.
    There are two ways of solving this. If you want always PR for FERT. Assign Proc type F in material master MRP view. It will always generate PR for that particular material.
    Or
    You can run MRP with planning mode 3 create PR in front screen.
    Regards
    J . Saravan

  • Sufficient stock but MRP create planned order and purchase requisition .

    Hi Expert,
    After MRP run planned order and purchase requisition created . but the problem is for child material sufficient is there but still PR and plnd order is created .
    MRP type PD, LOT size EX,Strategy group 10, for testing purpose I made safety stock 0, min lot size 0 , max lot size 0.
    I cant find the cause why MRP create PR and Pland order for the material which has sufficient stock. Please help.

    Dear Anirban
    could you check the following master data value:
    Lot size -> MB Monthly ( only for test)
    Rounding value -> null
    Strategy 40 MTS.
    You can try with this setting in order to figure out what is the problem.
    You can check also orizzon planning and re-scheduling (set to 999).
    Let me know if i have been useful for you
    Daniele

  • Block Plan Order and Purchase Requisition in Sales order creation.

    Please tell me, how to block Plan Order and Purchase Requisition while creating Sales Order. When we create a sales order, plan order and purchase requisitions are also created by their own, please tell me, how can we block them while creating sales order. Please do let me know as soon as possible.

    hi,
    generally thy wil not be created automatically.
    may be som configuration or exit is used in ur system.
    check in debugging mode while saving ur salesorder.

  • Differemce between  PROCESS ORDER,PLANNED ORDER AND PURCHASE ORDER??

    what is th edifference between PROCESS ORDER,PLANNED ORDER AND PURCHASE ORDER ??? can any one explain with some examples?
    n.bhardwaj
    [email protected]

    Process Order:
    Process order / Production order are activities within a business, where the production planning team team creates to absorb costs / evaluate costs / and check against planned figures. There would integration between MM/FI/PP to create such orders and process.
    Planned Order:
    A request created in the planning run for a plant to trigger the procurement of a plant material for a certain quantity for a specific date.
    Purchase Order:
    A request or instruction from a purchasing organization to a vendor (external supplier) or a plant to deliver a quantity of material or to perform services at a certain point in time.
    Regards
    AK

  • Link between Planned Order and Purchase Requisition

    Hi All,
    Is it possible to track a MRP planned order from the Purchase Requisition to which it was converted (using MD04 or MD14)?
    And is it possible to track a purchase requisition based on a planned order?
    Is there a clear connection - in DB tables - between MRP planned orders and different Purchasing documents - RFQ, PR, PO?
    Thanks in advance,
    Eytan.

    Hi Eytan,
    see some corrections for your understanding
    So, although it is not possible to track that connection, once you delete the PR that was previously created for the Planned Order, that same planned order becomes available again, and again you can convert it into a PR.
    not possible to come again same planned order once you deleted purchase requisition, system will create new planned order during after next MRP run for this requirement
    pls reward points and close this thread.
    Regards,
    Sankaran

  • Is there a link between ASCP released planned order and purchase requisition?

    Hi,
    i'm new to EBS. would like to know is there some kind of link on table level between a released planned order with purchase requisition?
    thanks

    Hi,
    As explained by Abhishek, we do not maintain any link between the PLANNED ORDER from which a requisition is created and the actual requisition.
    The simple reason being... in general, businesses run the plans on a daily basis and each time the plan is run, the previous data is overwritten... so there is no point in retaining the information of the planned order from which you are creating the requisition.
    Hope that helps.
    Regards,
    Mohan Balaji
    NOTE: Please mark the post as Helpful or Answered if the update has really helped you. This would also bring the thread to logical conclusion and will be helpful for the viewers.

  • Firmed planned order and purchase requisition

    Hi gurus,
    could anyone explain firmed planned order and firmed purchase requisition, please based on the following detail questions.
    1.when planned order was converted into PR, we call it firmed PR, right?
    2.when manually change a PR and save it, we call it firmed PR, right?
    3.are these the only 2 ways to firm PR? if not, what else?
    4. how to firm planned order?
    5. in MRP, the on-order stock is defined as "composed of fixed and firm receipt elements (PO, firm planned orders, firm purchase requisitions), while in MD04, we always see all the PR created by MRP running, are these newly created PR firmed automatically?
    Thanks,
    cookie

    HI,
    Check the link
    http://help.sap.com/saphelp_45B/helpdata/en/f4/7d2ca444af11d182b40000e829fbfe/frameset.htm
    Regards
    KK

  • Tracing Planned Order from Purchase Req.

    I want to find the Table - field relationship to trace a Planned order from Purchase Requisition.
    Once we convert planned order to purchase requisition, system deletes planned order in MD04.
    Is it possible to find out which planned order had been used to create purchase requisiton.

    Hi Raj,
    Generally Peggeed requirement is nothing but it represents the Higer level material. For example if raw material purchase requisition for 100 nos, then it is a Pegged Requiremet of the Assembly or the FERT. Simple its a dependent requiremnt for FERT or SFG.
    MD09 is used to find out the Pegged Requirement. If you give the Purchase Requisitiion of the Raw material, then system will tell you the pegged requirement i.e. the production order order to which the purchase requisition belongs to.
    Pegged requirement may be a Sales Order,Reservation,Production Order,Project,Network,WBS etc.
    Select one MRP element in MD04 screen and if you select pegged requirements system will show you these elements created for any higher level material or not.
    Note :Once a GR is done to PO, there is no more pegging possible for the PO, as it is in Inventory. Pegging is possible as long as it is an open order (PO, PR etc.)
    Apart from above case If you have other requirment you to devlope your own.
    Regards,
    Ram

  • Planned Order and Purchase Requisition for total Plan

    HI
    As per my client requirement whenever i am giving a plan in Demand Management in MD61 say for quantity 100. System should create purchase requisition for quantity 40 and Planned Order of 60.
    Please let me know if it is possible.
    Regards,
    Anand

    HI
    Thanks a lot. Its working with quota arrangement.
    Regards,
    Anand.

  • Planned order to Purchase Req. Conversion

    Hi,
    I have a planned order dated June. When will this be converted to a Purchase Requisition?? based on Planned delivery time and GR processing time?? Kindly clarify
    TIA
    Sabitha

    Hi,
    What program is running in background to convert the planned order to PR? Check the criteria specified in this program for this conversion.
    If its a custom program, discuss with your abaper on the program logic. If it is a std. program, then let us know the program.
    Also go to MD04 & try manually converting the planned order to PR, if system allows the same, then the issue is with the program.
    Another option is run MRP with Create PR field with option 2. Once the planned order falls within the planned opening date, system converts the planned order to PR automatically.
    Hope the above clarifies.
    Regards,
    Vivek

  • Planned order to purchase requistion

    Dear gurus,
                     I have configured the purchase requsition number ranges.While running MRP and while making manual purchase requistions i am getting the correct number range.but my pblm is while converting planned order to purchase requistion.i am getting the different number range.i checked in omi3.it is client specific number range.My requirement is in corresponding plant if i convert planned order to purchase req i should get the same number range as of mrp generated prs in that plant.
          Gurus please through some light
                                                      -guna

    Hi,
    Goto tcode OPPQ , select your plant .
    Select the number range field. Here you can find pur. req.
    Check this no range by selecting display icon.
    If the no range is different goto tcode OMI2 (for planning run)not OMI3 (manual), change your no range.
    Now run mrp & check the no. range.
    Regards,
    Dharma

  • The relationship between production order and purchase requistion After running MPS

    Dear Experts:
         I met a issue . My users want to know the relationship between production order and purchase requistion . In my company we create production order and  purchase req. by  running MRP. our operations are:
    1. T-CODE: MD41  create planned order .
    2. T-CODE: CO41 convert planned order to production order .
    3. T-CODE: MD15 convert planned order to purchase Requisition.
      but I can't  find the  relation of them. would you like to give me some advices? thank you very much.

    Hello
    On the standard MTS process there is no link between the requirement (STO) and the replenishment element (production order).
    See the below extraction from note 12955:
    There is no index that the system could use to determine which issue element (sales order, planning, reservation, dependent requirement, ...) is covered by a certain receipt element (purchase order, production order, purchase requisition, planned order, stock level ...).
    A production order, for example, can be created to cover several different requirements, even when you are using lot sizing procedure EX.
    You can use transaction MD09 or MD04to determine the pegged requirements, but they are calculated dynamically and there is not fixed link between requirement and receipt.
    BR
    Caetano

  • Planned orders to Purchase Requisitions and orders

    Hi,
            Just wondering if this is possible. I heard this from a client and want to confirm if it's true.
    The client owns the technology and has contractors manufacture the product.
    A planned order is generated by the client and based on the type of contractor, some of them are converted to Purchase orders and others to Purchase requisitions.
    Is this possible? I was thinking, planned orders ans purchase requisitions are completely different entities. Planned orders are for internal manufacturing which are subsequently changed to Production orders and purchase requisitions are for external procurement that would be converted to Purchase orders.
    But converting the Planned orders to Purchase Requisitions and orders is what I could not digest.
    Is there any possibility of this case?
    Thanks.

    Hi,
    We can create planned orders & convert them into purchase requisition or into production order.
    In the material master ,mrp2 view give the procurment type as 'X', for both internal & external procurement.
    Also include purchasing view for this material.
    When you run mrp using md02, a planned order will be created for the rquirement (Eg:say 100 nos given using t.code md61).
    Use t.code md04 to view the stock/requirement list.
    Here double click the planned order, you can see tabs such as convert into purchase requisition, into production order, into process order.
    Click convert into pur req & enter 50 Nos. Then a pur req will be created which can be further converted into pur order.
    Again come to md04 screen.
    You can see a planned order & pur req for 50 nos.
    This planned order can be converted into production order & 50 nos can be produced internally.
    Hope this clears your doubt.
    Regards,
    Senthilkumar SD

  • Planned orders to Purchase Requisitions and Purchase Orders

    Hi,
            Just wondering if this is possible. I heard this from a client and want to confirm if it's true.
    The client owns the technology and has contractors manufacture the product.
    A planned order is generated by the client and based on the type of contractor, some of them are converted to Purchase orders and others to Purchase requisitions.
    Is this possible? I was thinking, planned orders ans purchase requisitions are completely different entities. Planned orders are for internal manufacturing which are subsequently changed to Production orders and purchase requisitions are for external procurement that would be converted to Purchase orders.
    But converting the Planned orders to Purchase Requisitions and orders is what I could not digest.
    Is there any possibility of this case?
    Thanks.

    Hi,
    We can create planned orders & convert them into purchase requisition or into production order.
    In the material master ,mrp2 view give the procurment type as 'X', for both internal & external procurement.
    Also include purchasing view for this material.
    When you run mrp using md02, a planned order will be created for the rquirement (Eg:say 100 nos given using t.code md61).
    Use t.code md04 to view the stock/requirement list.
    Here double click the planned order, you can see tabs such as convert into purchase requisition, into production order, into process order.
    Click convert into pur req & enter 50 Nos. Then a pur req will be created which can be further converted into pur order.
    Again come to md04 screen.
    You can see a planned order & pur req for 50 nos.
    This planned order can be converted into production order & 50 nos can be produced internally.
    Hope this clears your doubt.
    Regards,
    Senthilkumar SD

Maybe you are looking for