Planned Order Components Table
I have a question. Is there a table that holds the components of a Planned Order?
When I see the technical data of a component field in MD13 it tells me they are in MDPM, but this is a structure, not a table.
that made me think that perhaps this is being fed directly from the BOM. But when I make a change to the BOM, the components in the planned order are not automatically updated.
So they must be stored somewhere. Anyone knows which table it is?
Otherwise, what FM can I use to fetch them?
Fernando,
You can get the components list of a planned order in RESB table for field PLNUM = Planned order number and BDART = SB.
Regards,
Prasobh
Similar Messages
-
Reg. Mass update of Planned order components
HI all,
I have a requirement wherein I will come to know the raw material consumption from storage location only at the time of production.
Now what I am doing is before doing confirmation I am updating the storage location for particular component in the planned order change mode - md12.I am doing this because the production confirmation is happening at External system and transferred via IDOC to SAP.So I cant add the sloc at that time.
I am doing the changes to planned order one by one. On an average I am doing this for say 50 Planned orders which is time consuming
Is there any option available in SAP to do mass change to the planned order components.
Regards,
MBN.Hi MBN,
You can use the LSMW, BDC program or FM MD_PLDORD_CHANGE_COMP_ITEMS to update the storage location in planned order components.
Regards,
R.Brahmankar -
Hi,
With a Combination of WORK CENTER and PLANT i need to extract all the respective PLANNED ORDERS, which is the corresponding table to query. Please help.
Points Assured
Regards,
PrabuHi....
PLAF - Planned order table
Tables related to work center:
CHRD: Work center header.
CRCO: Assign ment table
TC24: Person respoancible for WC
Others:
PBIM: Independent Requirements for Materials
MDTB:MRP Table
RESB:Material Reservations
Thanks,
Naveen Inuganti. -
Hi Experts
I am working with SNP Tool. I want to know that where I can see my planned orders other then /n/sapapo/rrp3 or is there any table for planned orders storage.
Please let me know if there is any table for planned order storage values.
Regards
guruThere is no table for the planned order in APO like R/3 ( table PLAF ).
You can see planned order in /SAPAPO/RRP2 also.
If you want to read planned order data you need to use FM like
BAPI_PBSRVAPS_GETDETAIL Read Data from a Planning Book
BAPI_MOSRVAPS_REQUESTLIST2 Request: Read Manufacturing Orders for Selection
Manish -
Plan Order Quantity Table & Field
Hi
I want Plan Order quantity in z report.
Please help how I will get from system.
I required table & field name.
Regards
ARKDear Ashish,
No
This is not possible
Once the plan order is deleted you can not get in any table and
Also once the plan order is partially converted to process order then only remaining qty will be stored in PLAF table
PLAF is only table for plan orders as plan orders are not confirmed receipts
Only in initial stage when plan order is created with the quantity then it appears in PLAF
Once you start converting partially then the remaining qty gets updated in PLAF
Regards
Madhu -
Change Planned order components
When we change a component in a planned order that is different from the manufacturing BOM, is there a way to distinguish what component was changed.
Hi Ramesh,
There is no transaction available to compare Production Order component list to BOM Component list. You need to create a Z report for yourself.
If it is just comparing 2 BOM's then you can use transaction CS14.
Hope this helps...
Regards,
Prasobh -
Reservation against planned order
Hi...
I have one issue with reservation against planned order.
We have REM & after MRP run generates planned order with order type PE.When i check planned order in table PLAF.
I found reservation no. & same has been passed to RESB , I got the reservation details but it is not allowed for goods movement XWAOK field in RESB. So no question of goods movement through MB1B with movement type 311.
My question is that is there any customization related to above scenario so that reservation is allowed for goods movement?
Regards
TusharDear ,
In REM , you will recieve reservation against planned order .But GI always happens during GR or after GR along with back flashing .I do not think so you can issue material against reservation as like normal PP Order reseravation in the production order .
1.Goto -SPRO->production-> Rep Manufacturing->Define Rem MAnufaturing profile(OSP2) --->Control data, in the Control data 1 tab select the "GI back flush at GR posting".
2.Check in the REM profile assigned in MRP view of material Master (MM03)
Based on this above set up , you can make Goods Issue for Planned order in REM .If you deselect that option execute material staging transaction code is MF60 and then go for REM backflush. In materil staging the components issue is carried out for the planned order.After that you can execute the REM backflush in MFBF
In rem scenarion components placed on the production lines anonomously (without ref to planned order)...you cannot issue materials like in production orders scenario. if you want to have track on the good issues before the GR then use the pull list concept...there will be no movement type but you will have track on quantities issued to header parts/production lines not to planned orders.
Hope this clarifies your doubt .
Regards
JH -
Planned order numbers- reached maximum number
Hai,
We reached the maximum limit on Planned Order numbers (table PLAF). anyone had this situation before and if so how did you resolve it?
Thanks in advance,
SonaliHI
Go to T code SNRO then give NO range object PLAF and maintain the new NO Range for the object
Hope this will help u
Regards
Anupam Sharma -
Activities to be avoided during Planned Order conversion
Hi,
I would like to know whether we need to avoid any other activities during production order creation by converting the Planned Order. Actually we faced a issue that one component is missing in the Production Order that is created by converting the planned order. When we check the BOM explosion and BOM components details, everything is ok, moreover backflushing is enabled for the missed component.
So i would like to know does we need to avoid any other activites during convertion of a planned order to a Production Order to avoid missing comonent in the Production Order. If yes, please mention what activities need to be avoided so that both produciton order and planned order components matches.
Thanks in advanceHi,
Check your BOM and its components valid from date. For the missing component may not be valid on the day when you have created the planned order. If you want to select the BOM again, in the order you can read the master data, then the system will reexplode the BOM and it will copy the latest components.
If some BOM component is not copied in the planned order or production order, the reason is that particular material may not be valid on that particular day. Please check and correct the same.
Regards,
V. Suresh -
Migration of Planned Orders from one SAP system to another one
Hi,
A quick help needed.
We are migrating SAP data from one SAP system to other due to business split. Regarding PP data, can Planned orders be migrated as it is from one SAP System to another? What is the impact if we do so?
Appreciate your response.
Kind Regards,
tanujihi ,
As suggested , you can propose to migrate only Firmed Planned orders from SAP to SAP system .
How to acheive it ?
You can use below BAPI to extract details of planned order from Table PLAF and upload in TARGET SYSTEM
BAPI_PLANNEDORDER_CREATE
Please note newly created Planned order in Target system would not have BOM EXPLOSION and Scheduling .
If need , Make a BDC recording as a add on step to explode Bom and Schedule by clicking those icons in Planned order .
Technical Team can do this . -
Mass T-code Of Planned Order Deletion
Dear All
Is there any mass T-code For Deletion of bulk planned order. An PIR.
Rgds
Pankaj AgarwalHi,
You can use function to execute one or more actions for a large number of planned orders simultaneously. This is possible both within the SAP System and over an interface from an external assembly control system.
Features
SAP supplies the function module MD_SET_ACTION_PLAF for action control.
This function module includes the following actions:
Explode BOM
Explode BOM, check availability
Check availability, only explode BOM in the case of a requirement
Check availability, do not explode BOM
Reset availability
Change planned order data
Schedule planned order
<b>Delete planned order</b>
Confirm planned order (in repetitive manufacturing)
Firm planned order data
Firm planned order components
Print component overview
This is in the foll link...
http://help.sap.com/saphelp_470/helpdata/en/f4/7d3f9344af11d182b40000e829fbfe/frameset.htm
Use T.code md75 to delete PIR.
Regards,
Senthilkumar SD -
Planned order scheduling mass update
Hello all,
Is there a way I can change the scheduling dates for the planned orders collectively. (not MD16) ?
ThankyouHi,
check the following
Mass Changes of Planned Orders (Action Control)
Use
You can use this function to execute one or more actions for a large number of planned orders simultaneously. This is possible both within the SAP System and over an interface from an external assembly control system.
Features
SAP supplies the function module MD_SET_ACTION_PLAF for action control.
This function module includes the following actions:
Explode BOM
Explode BOM, check availability
Check availability, only explode BOM in the case of a requirement
Check availability, do not explode BOM
Reset availability
Change planned order data
Schedule planned order
Delete planned order
Confirm planned order (in repetitive manufacturing)
Firm planned order data
Firm planned order components
Print component overview
In connection with an action, you can always change planned order data, for example; order quantity, dates or production version.
The function module also enables you to program further customer-specific actions.
You can execute the actions for several planned orders simultaneously.
You can create action chains, that means, have the system execute several actions in a single operation.
Activities
Define your own actions and program a report that includes these actions. As an example of this, the transaction MDAC Execute action for planned order (MRP ® Planned order ® Execute action) is available.
In this example action, you can use actions only for individual planned orders. Nor can you form action chains, only simple action transitions are possible.
Determine an action key and action controls in Customizing for MRP in the IMG activities Define action key and Define action control. An action key describes the actions that can be executed for a planned order. Action controls determine which actions are allowed and in which sequence they are to be executed.
Assign the key for the respective action control to the materials in the material master (MRP 4 view).
Regards,
nandha -
A Query for shortfall quantitiy of components in a Planned Order
Hello,
I'm trying to create a query to report committed quantity, required quantity and shortfall quantity of components for a planned order related to a WBS.
When I run MDVP for a specific planned order I see values in FLMNG field.
But when I check the reservation of that planned order in RESB table FLMNG table is empty while other fields for required quantity and committed quantity are filled.
So I ran ST05 for MDVP and figured out that system is using a table called RESVDB( I cannot remember the exact table name) but result the is same.
Does system fill the FLMNG field only in the structure of MDVP with substraction of committed and required quantities and never updates it in reservation tables? If it does update tables where can I find this field?
And also, to get the same result with MDVP, is using these fields in RESVDB the right way?
Thanks,
ArdaHello Arda
The system design is explained on the following note:
423538 - MDVP: Missing part list in collective availability check
The following information is provided on this note:
For dependent requirements of a planned order, the system generally updates no
missing part indicators using the availability check in the corresponding
dependent requirements record of table RESB. SAP does not plan to implement
changes in the system design of the R/3 standard system that allow processing
the missing part indicator from the availability check.
BR
Caetano -
What is the table to get the all planned orders related to a sale order
Hi,
May i know what is the table to get the all planned orders related to a sale order. My scenario is make to order scenario. we can get my out put final product by completing the nearly 916 planned orders.(Like major assemble,sub assemble). From this scenario i want the total orders related to a sale order. ( The planned orders from sale order to sale order will change. i.e 1 sale order will have 916 planned orders and one sale orders will generate 920 like that will chage when running mrp.). Now i want to pick the total planned orders for a sale order in a report. please guide me.
Regards,
Mastan.Hi,
Use the table PLAF... in this table pass the sale order no in the filed KDAUF and then execute...issue here is once the planned orders are converted production orders, these planned orders are deleted from the system....so you will not able to see them.....
Thanks
Kumar -
Define start date in SNP interactive table of planned order
hi,
does anyone know how to control the start date and the scheduling of planned order created in the SNP interactive table?Hi Arieh,
For SNP Pl.Order the standard SAP APO behavior is to control the availability date (End date).
To control Start date you have to convert SNP Pl.Order in PP/DS Pl.Order. Then in the PPT1, production periodic view you can change by start date if you change the strategy to Forwards.
Regards, Marius
Maybe you are looking for
-
In a single program how to lookup different EJB from different application
Hi, I have deployed two applications app1 and app2 on oc4j. There is a stateless session bean in a1 called ejb1. And there is also a stateless session bean ejb2 in app2. I write a test jsp in app1 to lookup ejb1 and ejb2 as an application client. So
-
Dear Sir/ Madam, I am very sorry for my foolish... I got a message from bank that they'll charge me HK$788, I was found out that I gave my Iphone to my 5 yrs old son for playing games, download some kind of free games only. But unluckly, He pl
-
Can my Apple TV 3 play music through an AirPlay speaker while I mirror my iPhone to the Apple TV?
-
Hi all , where BDC_OK fields will store in which table . and also how to reslove the screen resolution in bdc session method . Regards , Kiran .
-
Set Sound Alert Default on iPhone 4s
I keep losing the ringtone operation for incoming/outgoing mail and texts. How can I set and lock them into default? ~~F r a n k