Planned Order delivery date

When you run MS04/MS05 and system throws out the Planned order with the order start and order finish date. Can you tell me from how system calculates this order start and order finish dates??

hi,
I agreee with you...the source list is just checked for the validation of the periods...
As per my knowledge the periods are calculated based on the RLT(replenishment lead time)...ie. the total time from Planned del. time + GR processing time + Purchasing processing time...
Also sometimes if req. you can also take safety stock days ie. the days for which the extra stock is used in case of late deliveries...
Hope it answers your query...
Regards
Priyanka.P

Similar Messages

  • Req. delivery date and plan order finish date relationship

    Dear Experts,
    I have a question on setting the req. delivery date and plan order finish date relationship. Now, I want the plan order finish date is one day before the req. delivery date, is it possible to set it in configuration? Please advised! Many thanks!
    Regards,
    Matt Yim

    Matt,
    Please use a schedule margin key(SMK) in the material master MPR2 view which has float after production defined as 1day.
    If there are no SMK with that defination then you can define you own in customisation and assign the same in the material master. (SPRO--->Production ->MRP->Planning ->Scheduling and Capacity Parameters->Define Floats).
    Regards,
    Prasobh

  • MRP Planned order finish Date calculation (Planned delivery + GR Proc.time)

    Dear Gurus,
    Currently in our system, when MRP runs, Planned orders are created and the order finish date is calculate based on Purchasing processing time OMEW + Planned Delivery time from Material Master + GR processing time from material Master.
    My business requirement is that,  system has to take only Planned Delivery time + GR Processing time and exculde Purchasing PRocessing time.
    I cant make it Purchasing Processing time as ZERO - because this is used for other Purchase orders and KPI will be affected for procurement department
    Now we are going to Automate the Purchase orders for Materials - if outline agreement exist.
    How to make system settings for a MRP run, the Planned order finish date - should consider only Planned delivery time from Material master + GR Processing Time ( it should exculed Purchasing PRocessing time). Is it posssible? if not by any user exit, ABAP coding should be done?
    gurus please advice!
    BADI : MD_PLDORD_CHANGE - is this can be used?
    Please advice
    Regards
    RS
    Edited by: RS on May 18, 2010 10:22 AM
    Edited by: RS on May 18, 2010 10:33 AM
    Edited by: RS on May 18, 2010 1:34 PM

    Let me check, if I can find a way to paste /afs/md04 (AFS Envirnoment) screen shot . But in the mean time following are the
    details
    IHPT  - 12 days
    GRPT - 0 days
    SMK  - 000 (Op Period, Float After Prod., Float Before Prod.,Release Per. - 0 days)
    Thanks,

  • MRP and purchase order delivery date

    Hello
    Question about MRP
    we would like that the MRP run takes into account purchase order with a delivery date in the future
    Say the MRP run 10th of Oct we want that all purchase orders open with a delivery date in the future takes into account the quantity that needs to be ordered TODAY
    EXAMPLE
    Minimum stock 5
    Wse stock 0
    Purchase order delivery date D+1 10
    Lead time is 5 days
    So if you run MRP the systems proposes 5 to order today but they do not want  to order 5 because there is a coming purchase order D+1 of 10
    Does anyone knows how the pruchase order of 10 is taken into account in the MRP run ?

    Unfortunately, one of the weakness of SAP MRP is if a purchase order and/or production order is late, MRP will tell you to order it again instead of expediting.
    We have overcome this and other issues with our own economical planning enhancements. If you are interested you can contact me with your contact information

  • Purchase order Delivery date based on PO doc no and PO item no

    hi all
    we have a  requirement to bring Purchase order delivery date in to our report .
    it is in EKET Table - field EINDT.
    Is it possible to get this PO Delivery date in to our data source 2lis_02_itm which has PO Doc no(EBELN) and PO item.no (EBELP).
    In EKET Table the primary key is based on 3 fields. PO Doc no(EBELN), PO Itm.no(EBLEP) and delivery schedule line counter (ETENR).
    In EKET Table the data is like
    PO.NO/PO itm no/ schline counter/delivery date
    1000/10/1/1-1-2011
    1000/10/2/5-1-2011
    1000/20/1/2-2-2011
    1000/20/2/2-2-2011
    1000/20/3/5-2-2011
    so on...
    IF i enhance my datasource and populate the delivery date based on EBELN and EBELP we get only 1 delivery date for all the different schedule lines which is wrong.
    I know there is a separate datasource for schedule line data for purchasing BUT IS IT POSSIBLE TO GET the delivery date based on the different schedules by using some ABAP CODE, SINCE in our datasource 2lis_02_itm we dont have ETENR( SCHEDULE LINE COUNTER FIELD).
    if we use the standard data source  (2lis_02_SCL )it is not fair to pull all that data since we only need 1 field from it.
    Please suggest
    Thanks & Regards.
    Krishna

    Hi Krishna,
    Even though you plan to write some ABAP code or do any processing for a combination of PO document no. and Item no. you will always get multiple records with different schedule line items and it is really impossible to take the delivery date without knowing schedule line item no.
    And even when you said PO delivery date, it is actually means delivery date of any of the schedule line only. If you want to write some ABAP logic then you will have to decide like whether you want to display the First line item date or the last line item date etc. But which is again not a good idea.
    I think you can go for schedule line extractor.
    Regards,
    Durgesh.

  • SNP planned order availability date difference between APO and ECC

    Hi,
    I have observed that SNP Planned order availability date is not matching between APO and ECC. Details are as follows.
    I ran SNP Optimizer with bucket offset of 0.5. After publishing the optimizer created planned orders to ECC, only start date is matching.
    Example:
    I am using PDS as a source of supply.
    Fixed production activity in SNP PDS is 1 day.
    GR processing time: 3 day
    After running optimizer planned order is created with dates explained below.
    Start date/time: 09.05.2011 00:00:00
    End date/time: 12.05.2011 23:59:59
    Availability date: 16.05.2011 00:00:00
    Because of bucket offset defined as 0.5 optimizer planned order availability is start of next monday.
    After publishing this planned order to ECC dates on the planned order is as follows.
    Start date: 09.05.2011
    End date: 09.05.2011
    Availability date: 12.05.2011
    I have not maintained any scheduling margin key in ECC. Also if I dont define the GR processing time, planned dates between APO and ECC always match. Can anyone explain the impact of GR time on the availability date.
    Regards,
    Venkat

    Hi Venkadesh,
    What's "state stamp"? Do you mean different time zone?
    note : 645597  mentioned by Nandha is very helpful:
    In standard, CCR will use duedate - "the available date of the output product".
    Nandha's words "In SAP APO, if the receipt date of the primary product deviates from the
    end date of the last activity of the order, the receipt date
    always identifies this as inconsistent. You cannot rectify
    inconsistencies of this type by using CCR."
    I guess in your PDS or PPM, the output product is not assigned to the End of the last activity. Someone changed it?
    Please CIF the PDS or PPM again.
    If you really want to apply a note, please use note 815509 as you're using planned order,
    and system will use order end  date in CCR instead.
    GR time is always considered. BR/Tiemin

  • Whats the fieldname and table name for purchase order delivery date

    hi all,
        whats the fieldname and table name for purchase order delivery date
      thanks and regrads

    EKET-EINDT is the delivery date according to the schedule lines.
    for example the line item has 100 qty.
    it is sent in three schedules (40, 40, 20).
    Then EKET will have 3 records for one PO Line item.
    The final delievry data is the EKET-EINDT for the 3rd schedule line item.
    Regards,
    Ravi

  • Planned order start date & finish date

    Dear All ,
    I am running MRP for finished material ,
    But i am getting Planned order start date & finish date are coming same (todays date ). But when i am converting the order then proper scheduled dates are coming .
    Why for the Planned order the scheduled dates are not coming ?
    Regards

    Hi Venky,
    Pls try to understand how MRP works
    After MRP planned orders are created for the requirement(in house)
    In the planned order stage -basic dates are deteremined
    For the determintaion of basic dates system check the in house production time/replenishment lead time maintained in the material master
    For your requirement you maintain lot size dependent in house production data in the work scheduling view & check
    You have to key in data in set up time,processing time ,base qty etc
    Hope it is clear
    Rgds,
    SVP

  • SNP Planned Order start date in past

    Hi
    After SNP run, for the past requirements it is giving avaiablilty data as today but the planned order start date is in past. Now this order fails in CIF as the production version in R/3 is valid from today.
    In the strategy profile we have backward+reverse with infinite scheduling. In this case the start date should be todays date for past requrirements... am I correct?
    Regards
    Abhishek Rai

    Hello Abhishek,
    We are also facing the same issue. Did you find any solution to this issue?
    We are on SCM 7.0 with EHP1.
    Thanks,
    Mangesh

  • Copy Sales Order delivery date to Delivery Order delivery date

    Hi,
    Is there a way to create a FMS to copy the sales order delivery date to delivery order delivery date?
    Thanks
    Fabian

    Hi Fabian,
    I am not sure whether I have understood your requirement correctly.
    CopyTo also works for creating a delivery document from more than one sales order as base documents and base ref is available in line table than in parent table.
    The work around could be to create a UDF in marketing documents & update this UDF in sales order using FMS or using SBO stored procedure.
    Now, once after sales order is copied to delivery the UDF value is available in delivery and u can create one another FMS to get the UDF value into Delivery's Delivery Date.
    Hope this helps.
    Best Regards
    Satish

  • How to make Sales Order Delivery Date show 30days after Posting Date

    I have problem programming the SBO 2005A- Sales Order Delivery Date automatically add 30 days based on Posting Date, in VB.Net.
    Has someone tried it before ?

    Sorry i did not describe clearly.
    I was developing vb.net with SAPBuiCom (UI API).
    When Sales Order screen and the Delivery Date was empty. In my program i need to auto insert the Delivery Date field with 30days after the Posting Date.
    And when user change the posting date, the delivery date will auto refresh.
    KC

  • Requisition, Sales Order & Delivery Data

    Requisition, Sales Order & Delivery Data
    Hi,
    Please answer the following as best as possible:
    1. What are the main TRANSACTIONS for Requisitions, Sales Orders & Deliveries?
    2. What are the main TABLES for Requisitions, Sales Orders & Deliveries?
    3. How are Requisitions, Sales Orders & Deliveries related to each other?
       Simplified Table Mapping?
    Please help.
    Thank You,
    John

    Hi John,
    See the General SD flow is enquiry - quotation- sales order - Delivery - Billing
    Transactions
    Enquiry - VA11/VA12/VA13
    Quotation - VA21/VA22/VA23
    Sales Order - VA01/VA02/VA03
    Delivery - VL01N/ VL02N/VL03N
    Billing - VF01/VF02/VF03
    Tables
    Enquiry - VBAK , VBAP
    Quotation - VBAK , VBAP
    Sales Order - VBAK , VBAP
    Delivery - LIKP, LIPS
    Billing - VBRK, VBRP
    to know more about the tables refer sapgenie.com
    Thanks
    Ashok

  • Planned order start date is in the past

    Hi Experts,
    I am running MRP with lead time scheduling (2) at my production plant. The planned orders are generated against the requirements but the start date of the planned order is in the past. I have not mentioned anywhere in the configuration allowing the scheduling in past. I cross checked plant parameters, MRP group, settings for determining basic dates & scheduling parameters and every where start in the past check is blank.
    Since the planned order basic dates are calculated based on in house production time in material master, I maintained the lot dependant times in work scheduling view (Set up & processing time with base qty). But system is not considering this in MRP run. But its considering the lot independant inhouse prod time maintained in work scheduling view in MRP.
    Is there any other check to be maintained or system limitations? Your expert view on this please.
    Appreciate an early reply.
    Thanks & Regards
    Prathib

    Check OPU5
    S Anil

  • Purchase order delivery date is same as creation date

    Hi,
    For one of the plant.when PO is created manually  delivery date is taking  same as creation date.why it so.
    Can any one provide the reason.
    There are no Personal settings in Purchase order
    for the material the data maintained as follows :
    MRP2 :
    Planned delivery time is 24 days
    GR processing time is 5  days
    Purchase info record :
    Planned delivery time is 24 days
    SPRO-Plant parameters
    Purchase Processing time 1 day
    Regards,
    somiraghu

    Hi ,
    System calculate the delivery date by the sumation of planned delivery time with your creation date. In the material master the planned delivery time for that plant may be zero ,.tht may be the region behind  the system is showing the creation date as the delivery date.
    Pls check your Material in Material Master for that plant...
    Regards

  • Which Factory Calendar is used to determine the Sales Order delivery date

    Hi ,
    There is Factory calendar assigned to sales Org and shipping point as well.
    I want to know which Factory calendar is used to determine the promise date on sales order acknowledgement and which one is used to determine the delivery date?
    Appreciate your help/inputs.
    Regards,
    Ram

    Ramy,
    I am not sure what you mean by 'promise date'.  For a given sales order item confirmation schedule, the system calculates the following dates:
    Delivery Date
    Goods Issue date
    Loading Date
    Material Availability date
    Transportation planning date.
    These dates are dependent upon what you have configured, and what your master data is.  If you have transportation scheduling turned on (IMG>SD>Basic Functions>Delivery scheduling and transportation scheduling), then the durations are:
    Route duration (transit), - affected by factory calendar assigned to the route (0VTC, that's a zero)
    Picking time, packing time, Transportation planning time, and Loading time- affected by the factory calendar assigned to the shipping point (OVLZ, not a zero)
    In addition, the Material availability date will be affected by the calendar assigned to the plant (WB03).  The calculated dates may also differ on a given order schedule line, based on whether the sales order is backward scheduled or forward scheduled.  This is particularly important when the calendars all have different holiday schedules.
    Standard SAP help on the matter, with a couple of nice pictures.
    http://help.sap.com/saphelp_erp60/helpdata/en/dd/5607e7545a11d1a7020000e829fd11/frameset.htm
    Rgds,
    DB49
    Edited by: Dogboy49 on Feb 16, 2010 5:08 AM

Maybe you are looking for

  • How to transfer files from Pc to mobiles?

    HI, How to transfer files from Pc to mobiles? what are the Methods to do transferring files. Sri

  • Profit Center Accounting - BFOK_AB

    Dear expert, could you explain me how the table BFOK_AB is taken into consideration for the calculation of the vendor balances to transfer to PCA? I'm interested also to understand the relation between tables BFOK_AB and BFOK_A. Many thanks for your

  • How to set up Batch Management and stock determination ?

    Our client deals in various food articles and wish to use batch management and shelf life functionality. Details are While doing the goods receipt, batch no. as supplied by vendor will be entered. There is no requirement of batch no. generation. Thus

  • Getting ext. DVD to play

    The CD/DVD drive in this machine died and so in haste I replaced it with a HPDVD1040 external drive. My mac sees the drive. Will play and burn cd's, but when I try to play a dvd it gives me an error code of -70012 and comment that a valid dvd drive c

  • Problems with the secondary click after updating to 10.7.4

    Hi there, since my update to 10.7.4 on my MacBook Air I have a problem with the secondary click. I configured it to "click on right side", but some times and espacially after wake-up my MBA the secondary click is not working. So I have to switch to t