Planned order numbers- reached maximum number

Hai,
We reached the maximum limit on Planned Order numbers (table PLAF). anyone had this situation before and if so how did you resolve it?
Thanks in advance,
Sonali

HI
Go to T code SNRO then give NO range object PLAF and maintain the new NO Range for the object
Hope this will help u
Regards
Anupam Sharma

Similar Messages

  • Problem with reached maximum number of connections to database

    Dear Experts,
    Our Production system was not responding properly last week.
    The below was the reply from the Basis team.
    "It seems that we have again problem with reached maximum number of connections to database. We have extended this number to 100 this year and now it seems that it’s not enough again. It seems that something is running on Production, which takes over too many connections."
    They have increased the number to 200 as a work around.
    Do we have any means to find out, which component or application is causing the issue.
    Please advise me if any better way is available to correct the issue.
    Please see the below trace.
    From default trace:
    ======
    Caused by: com.sap.engine.services.dbpool.exceptions.BaseSQLException: ResourceException occurred in method ConnectionFactoryImpl.getConnection(): javax.resource.R
    esourceException: (Failed in component: dbpool, BC-JAS-TRH) Cannot create connection. Possible reasons: 1)Maximum allowed connections to DB or EIS is reached. You
    can apply CSN Note 719778 in order to check and resolve connection leaks. 2) Configuration to DB/EIS is wrong or DB/EIS is temporary unreachable. 3) Connections ar
    e not enough for current load.
            at com.sap.engine.services.dbpool.cci.ConnectionFactoryImpl.getConnection(ConnectionFactoryImpl.java:60)
            at com.sap.security.core.persistence.datasource.imp.J2EEConnectionPool.getConnection(J2EEConnectionPool.java:205)
            ... 61 more
    Caused by: javax.resource.ResourceException: (Failed in component: dbpool, BC-JAS-TRH) Cannot create connection. Possible reasons: 1)Maximum allowed connections to
    DB or EIS is reached. You can apply CSN Note 719778 in order to check and resolve connection leaks. 2) Configuration to DB/EIS is wrong or DB/EIS is temporary unr
    eachable. 3) Connections are not enough for current load.
            at com.sap.engine.services.connector.jca.ConnectionHashSet.match(ConnectionHashSet.java:230)
            at com.sap.engine.services.connector.jca.ConnectionManagerImpl.allocateConnection(ConnectionManagerImpl.java:343)
            at com.sap.engine.services.connector.jca.ShareableConnectionManager.allocateConnection(ShareableConnectionManager.java:54)
            at com.sap.engine.services.dbpool.cci.ConnectionFactoryImpl.getConnection(ConnectionFactoryImpl.java:52)
            ... 62 more
    Caused by: com.sap.engine.services.dbpool.exceptions.BaseResourceException: SQLException is thrown by the pooled connection: com.sap.sql.log.OpenSQLException: No c
    onnection to data source SAPEPPDB available. All 100 pooled connections are in use and 70 connection requests are currently waiting. The connection pool size might
    need to be adjusted.
            at com.sap.engine.services.dbpool.spi.ManagedConnectionFactoryImpl.createManagedConnection(ManagedConnectionFactoryImpl.java:192)
            at com.sap.engine.services.connector.jca.ConnectionHashSet.match(ConnectionHashSet.java:221)
            ... 65 more
    Caused by: com.sap.sql.log.OpenSQLException: No connection to data source SAPEPPDB available. All 100 pooled connections are in use and 70 connection requests are
    currently waiting. The connection pool size might need to be adjusted.
    ======
    Thanks and Kind Regards,
    Jelbin

    Stop all instances(including DB) and start again, Hope it should work.
    It may happened that jar has not been synchronized with the database and may be version mismatch with the java.
    719778 - Data Source fails to return connection
    1650472 - Transactions are interrupted due to database connection periodically failing to establish
    1138877 - How to Deploy External Drivers JDBC/JMS Adapters
    Change the connection pool so that it can connect to DB as per the note 719778
    Regards
    Vijay Kalluri

  • Confirmation number reaches maximum number

    Hi,
    In my client production system, we are getting close to the limit in terms of QM Confirmation Number for Inspection Characteristic (table QAMV-RUECKMELNR).
    We have standard SAP number range configuration 1 - 99,999,999 for object QMERKRUECK and actual number is <10%
    To resolve the isse, we are planning to archive old inspection lots.
    But my question is how the confirmation number behaves after archiving a set of  inspection lots, we may face the situation where the confirmation number holds two inpsection lots ( one is archived & other is new)?
    What will happen when the system start number with 1 and we would have duplicated numbers in table QAMV.
    Please advise with details steps for archiving inspection lots and how the confirmation number reset to 1 and its consequences etc.,
    Thanks a lot and best regards,
    Nagesam

    Thanks you Sujit,
    You are saying to create new number range for inspection lots ( QCC3 ) and assign origin & type,  please calrify if I am wrong. Please find my exact issue and help to fix...
    In my production system.....
    QMERKRUECK  range is...
    00000001 to 99999999 and the current number is already 91245679
    and QLOSE intervals are below..
    000000000001 to 009999999999
    040000000000 to 049999999999
    070000000000 to 079999999999
    and the flag for 'No interval rolling ' is NOT checked, so the number range will be automatically resets to 1, once reaches to the upper limit
    Issue : Warning message ' Internal number assignment for object QMERKRUECK (numbers are in critical area)" is showing while creating inspection lots using QA01.
    What could be the best solution to fix this?
    1. Archive old inspection lots ( on specific criteria ) ? Later, once the confirmation numbers reaches to 99999999, it will reset to 1. In this case...do we get the situation where the confirmation number holds both archived inspection lot and active ( newly created) inspection lot ? Do we have any business impacts?
    2. How creating new nuber ranges for inspection lots fix the confirmation number range issue? Please clarify if I am missing anything.
    Thanks in advance,
    Nag

  • Cant add new iCloud because my device iphone reached maximum number

    I am giving my iphone 4s to a friend but cannot add a new iCloud account. Why there is a limited number? This mean that he cannot use the iphone? I find this not good and why Apple don't specify this matter when you apply the first time?

    Welcome to the Apple Community.
    Unfortunately once all the 3 iCloud accounts have been created on your device, you cannot create any more regardless of what you do. You will need to re-use one of the accounts that you have already created or create your new account on another iOS device or Mac computer.

  • Maximum number of files reached

    I keep getting a message on my phone that you've reached maximum number of files. Please remove applications and/or files to clear space. When I hit button for help it says to got to www.vzw.com/baplus to find: -FAQs/help -manage contacts -contact support. When I go into my verizon and my device (with my phone number) I get a backup assistance list of another phone on my plan. It shows their number in the upper left corner on the back up assistance. I cannot get to my backup assistance numbers to manage.

        Thanks for trying to get to your information already, BrutusgoBucks. Please make sure that when you're visiting www.vzw.com/baplus, log into My Verizon as your mobile number. Going to My Verizon and logging in with the account number will result in seeing the main number registered to that user name instead of your information, even if you select your number later in the page. If you've never created a My Verizon account for your line, no worries! It's easy. Just select register instead of sign in and create an account for your specific line. That way you'll be able to view your line's content on Backup Assistant Plus and the media center.
    Thank you
    JenniferH_VZW
    Please follow us on Twitter @vzwsupport

  • GUI connection error MAXIMUM NUMBER OF CONNECTION HANDLES REACHED

    Dear Experts
    while logging on to GUI7.10 I am getting following error
    MAXIMUM NUMBER OF CONNECTION HANDLES REACHED'
    'MAXIMUM NUMBER OF HANDLES REACHED'. 'NO MORE MEMORY IS AVAILABLE'.
    'DO YOU WANT TO SEE DETAILED ERROR DESCRIPTION?'
    When i click on yes to the question above, i get the following:
    'COMPONENT = DPTM'
    'RELEASE = 7.10'
    'VERSION = 10'
    'RETURN CODE= -16'
    'Counter = 3
    This error is not allowing me work.
    Does anyone have a solution?

    Hi,
    I am having the same issue. Did you resolve the issue.
    Please let me know
    Regards

  • Maximum Number of Authorizations

    Once again my Digital Editions account has reached maximum number of authorizations. Every time my e-reader has a problem and I need to reset it, Digital Editions needs to re-authorize. Who and how do I contact to have this reset?

    Hi,
    You can get your authorization reset for Digital Editions and your Reader  by opening Web case with Adobe as they do not support Adobe Digital Editions on Phone line.
    In order to create Web case you need to do following.
    1) Go to : http://www.adobe.com/support/digitaleditions
    2) Click on "Submit a web case"
    I hop this will help you..
    Now if you are facing problem like whenever you open Digital Editions or Connect Reader it is asking to authorize then do folowing
    Solution ) Create a new user account with administrative privilages and then launch Digital Editions with the same.
    I hope this will help you
    Regards
    Rizwan

  • Report for PO's/Pr's/Planned orders with exception code

    Hi all,
    Is there any report which lists out Purchase Orders/Purchase requisitions/Planned orders for a specific exception message number?
    For example when MRP is run some times the finish date for a planned order may be in past (exception message number 07). I would like to get a list of all the planned orders with exception message number 07. Similarly i would like to get PO's/PR's for a specific exception code.
    Any help is highly appreciated.
    Thanks,
    Avani.

    Hi Neetha,
    You can use the Collective access tab on the MD06 T-Code, don't enter a material number, only the plant number and MRP Controller number.  Then click on the tab marked Exception Groups, check box  number 7 and execute the report.  This will give you a list of all materials with exception group 7.  If you need it as a report. Once the report comes up you can click on MRP List on the tool bar at the top of the page and then click print.  This will format it so you can download it into excel by clicking on the Local File Button.  When the box comes up click on spreadsheet and save it to your hard drive as an excel spreadsheet.
    Hope this is of some help to you.
    Debbie

  • BAPI or FM for scheduling a planned order (like MD11 or MD12)

    Hi guys.
    We are working with a group of materials and planned orders, in order to modify and create new planned orders depending on the stock per each material. So we use MD12 to 1) modify the quantity in the order, and MD11 to create new planned orders for the rest of stock for this material.
    For process of creation we don't have problems (BAPI_PLANNEDORDER_CREATE makes its work well ), but when we want to schedule the new planned order created before via FM or BAPI, we cannot see any results in MD12.
    I mean, when a planned order is scheduled via menu button, a new tabstrip appears in the transaction with dates. So this similar action we've tried using CX_PLANNED_ORDER_SCHEDULE or CX_CRP_PLANNED_ORDER_SCHEDULE but there was no change.  If we execute the Schedule button action, in table PLAF (master of planned orders) apears a new number in field PLAF-BEDID related to MRP.
    So guys, could you please help us how to get this issue? As last option is BDC, but BDC's and me are not good friends because its performance. So please, any suggestions?
    Thanks in advance!
    Raul Romero

    Hi guys...
    Sorry for the long time without an answer, which I'm sharing you now:
    1. In order to perform the proccess of scheduling, you have to record the steps from menu bar in your batch input. I mean: (1) set values into fields CRHARBPL-LOW () and CRHWERKS-LOW
      PERFORM set_batch USING: 'X' 'RCCRY000' '1000',
                                      space 'BDC_CURSOR' 'CRHARBPL-LOW',
                                      space 'BDC_OKCODE' '=PLNG',
                                      space 'CRHARBPL-LOW' p_arbpl,
                                      space 'CRHWERKS-LOW' 'PR01'.
    (2) After you ordered your list of planned orders or production orders, loop your internal table and per each order record these commands (these simulates the popup option to select the order you want for scheduling and mark it in the dynpro you are processing):
      LOOP AT gtd_tabofplan INTO gvc_tabofplan.
        PERFORM completa_bi_campos USING: 'X' 'SAPLPLAT' '4000',
                                        space 'BDC_OKCODE' '=Z021'.
        PERFORM completa_bi_campos USING: 'X' 'SAPLCY19' '0120',
                                space 'BDC_CURSOR' 'CYMARK-VALUE(02)',
                                space 'BDC_OKCODE' '=BACK',
                                space 'CYMARK-VALUE(02)' gvc_tabofplan,
                                space 'CYMARK-MARK(01)' space,
                                space 'CYMARK-MARK(02)' 'X'.
        PERFORM completa_bi_campos USING: 'X' 'SAPLPLAT' '4000',
                                space 'BDC_OKCODE' '=SL25'.
      ENDLOOP.
    (3) Set the SAVE operation.
      PERFORM completa_bi_campos USING: 'X' 'SAPLPLAT' '4000',
                              space 'BDC_OKCODE' '=SAVE'.
    Hope you' ve succeeded in this task, let me know if you've another questions.

  • Planned order to purchase requisition - Manual / MRP---How do we confirm

    Hi,
    I have a planned order which is converted into purchase requisition (PR). I want to know the following.
    I know only PR number now.
    a) How do I know the reference planned order from Purchase requisition number? (In PR, creation indicator shows as U-Converted planned order)
    b) How do I confirm whether this planned order is created manually or by MRP?
    Please help me in finding out the above.
    Thanks in advance
    Muthu

    Hi,
    a) When you convert the PldOrd into PurReq it disappears from table PLAF, it ceases to exist. There will be no PldOrd-reference in PurReq (you will not find such field in EBAN). (if you check field RSNUM in PLAF before converting the PldOrd and you check field RSNUM in EBAN after converting the PldOrd into PurReq, you wlll find the same number)
    b) It's not easy to say. You can check PLAF-PSTMP and PLAF-PUSER and compare these with data you get from trx STAD. But this is also not an exact methode since these field are in connection with the last date of change.
    Firming indicator cannot help also since you can remove it manually... - even though the PldOrd was changed manually, no firming indicator will be seen...
    (Of course, generally firming indicator helps if the user doesn't remove it intenionally)
    Regards,
    Csaba

  • Partial conversion of Planned orders to Production orders

    Hi all
    I wan tot partially convert planned order to production order. I am able to do this with MD04. Is there a tcode for mass partial conversion. CO41 does not allow a partial conversion. Is there a way I can collectively do a partial conversion.
    thanks

    Hi John,
    To the best of my knowledge there is no t-code to do a mass partial conversion of planned orders.
    You can try with a lsmw recording of t-code co48 & then input your planned order numbers with the qty to be partially converted or alternatively use co41, change the qty & convert the planned orders, but with this you will need to re-run MRP to create another planned order for the balance qty.
    Hope the above helps.
    Regards,
    Vivek

  • Reg. Component list of planned order

    Hi All,
    My requirement is i need a simple components list of planned order similar to COOIS - Component list, but not with all information.
    Only I need the list of components planned order wise with component number, quantity, Sloc, Header material number, Production line and Production start and end dates.
    To achieve this I am going for Z report development, I found the BAPI-BAPI_PLANNEDORDER_GET_DETAIL has all information what I need.My question is does this BAPI is fetching the values of component from the reservation table against that planned order number.Meaning does this BAPI output of Components and RESB output for that planned order will be same?
    Regards,
    MBN.

    Hi
    Yes both results are the same if you check the RESB table with reference to the planned order number for which you have fetched data from BAPI BAPI_PLANNEDORDER_GET_DETAIL, both are the quantities are same, Also you can see the same in MD12/MD13, but when you check the RESB table only input as one of the component assigned in Planned order , then the quantities will differ,
    The result will be the same only in case when you execute the data from table RESB with respect to the planned order number( given input in BAPI).
    Regards,
    Anupam Sharma

  • Planned order problem

    Sir i want to know the t-code where i will get planned order initial quantity .If i have planned order of say 1000 EA , now if i convert it to partial production quantity of say 200 EA by t-code MD04 then in front of my planned order quantity is 800 EA .I want to know from where i will come to know that my initial planned order qty was 1000EA.
                            Sir i wait for reply.

    Hello,
    You will get the initial Planned Order No. and Quantity in the Table : PLAF.
    The Field Names : PLAF-PLNUM and PLAF-GSMNG.
    The logic should be:
    As all the Planned Orders of a specific material are not going to be converted to Production Orders.
    Which ever the Planned Order, you are going to convert to the Productio Orders, the report should update at the run time the Planned Orders to a Z Table.
    If the Planned Order is converted Partially, the Planned Ordr no. will be intact with the reduced quantity, so your program shoud check the Duplication of the Planned Order numbers with the Actual quantity.
    When required, the oupput should from the ZTable..
    On similar lines or with some other logic ask your ABAPers to Devlop a report for you..
    Regards,
    Siva

  • SNP heuristic error maximum number of orders per period reached

    Hello All,
    I am getting one strange error "APO SNP heuristic error maximum number of orders per period reached (000000040)"
    Product XXX/ Location XXX: Maximum number of orders per period reached (000000040)
    For the problem : PPDS heuristic is working fine, while running the SNP heuristic I am getting this problem.
    Please let me know asap.
    Thanks in Advance,
    Kind Regards,
    Santosh

    There is a section in the IMG where you can change this behaviour.
    in SPRO - SAP SCM - IMG
    -> Advanced Planning and Optimisation
      -> Supply Chain Planning
        -> Supply Network Planning (SNP)
           -> Basic Settings
              -> Maintain Global SNP Settings
    You will see the field "Heu.: Orders per Bkt" which should have the value of 40 in there, e.g. the limit to the number of orders SNP can raise in any planning bucket.
    If you raise this number (to say 100) then hopefully your message will no longer be issued by the system.
    Alternatively, you can check the cause of why the system is rasing so many orders. For example, check the lot size that the Product has for that location (lot-for-lot will create an order for every demand for example).
    Hopr that helps
    Regards
    Ian

  • [HELP] - Maximum number of Planned Orders generated by MRP

    Hello SAP Gurus,
    How can I define the maximum number of planned orders generated by the MRP?
    Thanks in advance,
    Adelmo

    Hi Adelmo,
    Check in OPPQ for your plant, you can make a setting there. I am not in front of the system at the moment, so just check.
    If you need any additional info, revert back.
    If helpful award points
    Regards,
    Vivek

Maybe you are looking for

  • Index, Hints, etc

    All, I was wondering whether you could please help out on the following points: (a) In the query below, what might be the suitable (and why?) indexes to be built? ======================================= SELECT CONTRACT_PAY_GROUPS.CPG_AMOUNT_CY_AP, CO

  • How to completely delete Photoshop Elements from my computer??

    Hi I am trying to completely remove Photoshop Elements from my computer.   So far, I have failed in my attempts to do this.   The reason I'm doing this is b/c for some reason that I can't fathom, the folders in My Pictures -- the folders named by sho

  • Where can I get a used MacBook

    Where can I get a used apple MacBook for around 100-200$ please help

  • Push button after press any key to turn-on

    Hi guys I've notebook toshiba model: L515-SP4011L and the problem is: that push it button to start, turn on but don't show screen after press any key notebook and show logo toshiba wait a moment for turn-on, after follow  don't show screen press key

  • Crystal Reports XI R2 and Window Server 2008 Hyper-V environment

    Hello, Is there any known issue that Crystal Reports XI R2 running on Window Server 2008 Hyper-V enviroment? I tested on Development Server which is Window Server 2008 and it is working fine but when tested with another servers which are in Hyper-V e