Dear All,
I am trying to create one planned order with planned order profile LA  in Trx MD11. But in first screen after entering material number,qty & date. when I press enter planned order profile get changed to KD.
I do not know why it is happening? Please suggest me on this.
In OMDD Trx, is there any dependency between plant and planned order profile??
While creating a new order profile where we define the order type related to this??  
Thanks & Regards
Kundan Kumar

Hi
The problem is because of Account assignment category (E) which is getting copied to Planned order in MD11 and resulting to convert the order in to individual customer order (PP-SD-FI integration).Plz chk the Planning stg assigned to the material in MRP-III view
Regards
Brahmaji

Similar Messages

  • Planned Order Profile for REM

    Hi,
    Is Planned order profile for REM needs to configured for Planned Order type PE in IMG(T Code OMDD).
    Thanks in Advance.
    Regards,
    PPcon

    Dear,
    SPRO>Production>MRP> proc.proposals>planned orders-->Define order profiles
    Ypu have set the rep mfg indiactor & suitable rem profile in MRP 4 view of material
    BOM Explosion Tab
    Selection method : 2 -By production version (prior to this , a Prod version shd be created)
    Please try and come back.
    Regards,
    R.Brahmankar

  • Planned Order Type/Profile

    Hi
    The Planned Order Profiles does not contain any account assignment category defined and also the requirement class (030 in my case) does not have any acc assignment category specified. After MRP run, the system defaults to the planned order type NB. Can somebody explain, how does this happen? What is the link?
    Please explain and elaborate if possible.
    thanks a lot.
    BE.
    Edited by: Brian Elfie on Jan 8, 2008 2:54 PM

    check in SPRO
    Production>Material Requirements Planning>Procurement Proposals>Planned Orders>Define Order Profile
    entry
    Object = 1
    planned ordxer profile = NBE
    the data for this is
    order type = NB
    acc/assignment = E
    i hope you got it

  • Error while creating Planned order in SAP PP

    Hi ,
    I am creating planned order for finished material and system has given below error - Please specify the order deadlines in ascending order.
    SAP Message Error- Message no. 61009  Please specify the order deadlines in ascending order
    Very first planned order get saved and we declare the production and business completed
    Now creating second planned order , while saving system giving above error.
    I am Taking Planned Order Profile LA -Stock order
    Any solution  ...?
    Thanks in advance !!!
    Deepak.

    Hello Deepak,
    Please adjust the order dates in the scheduling of the planned order. In normal production scenario operation completed end of the night shift and order finish date is possibly moved one day in the future for this reason we need to set the operation timing in 24:00:00 format
    In your issue change date like this
    End date : 30.06.2014
    Start : 31.05.2014
    Opening date : 31.05.2104
    Check with this date, it’s work for you 
    Regards
    Umesh Mali

  • Manual creation of planned order in REM

    Hi, 
    Can we manually create a planned order in repetitive manufacturing? I know that in case we run MRP , then planned order for finished is created with order type 'PE' due to which it cannot be converted to production order.
    I dont want to run MRP , still can i create a planned order manually with the same order type 'PE' ? I tried in MD11, but not getting option to chose PE as it is not available  in F4 of planned order profile.
    Please help..
    Regards.

    Dear,
    You cannot create a planned order with PE order type manually, because a planned order of REM related material gets order type "PE" only when it is assigned with a Production Version.
    So achieve manual creation of REM Planned order with PE type with the following options,
    I - Using MD11 transaction create a planned order with LA type and assign a suitable REM related Production version to the planned order during creation itself, now this order would automatically become "PE" order type on saving the order.
    2. In the planning table using MF50, you can directly create a planned order for a production line using F7 key.
    Regards,
    Prasobh

  • How to create a new Plan order type or make changes in current stock type?

    Hi
    I need to do following for my client.
    After the planned order is created either manually or automatically a planned order profile
    is allocated and data is processed. The data would include: material, plant, order quantity
    and basic order dates. The system will check component and capacity availability and if needed, capacity leveling
    can be carried out. Saving the planned order creates a purchase requisition, planned load,
    creates dependent requirements and allows the processing of the planned order.
    NUMBER RANGES FOR PLANNED ORDERS: - 1000 to 9999

    Animesh,
    Could not fully understand what is your requirement, please rephrase and explain again. In the statement given by you everything happens expect while saving the planned order, PR getting created.
    Regards,
    Prasobh

  • Planned Order for Purchased Parts W/o using MRP

    Hi All,
       I want to create the New Planned Order which I want to convert it to Pur. req. and then further convert it to Purchase Order.
        But I don't want to run the MRP for the same. And also we have maintained ND (No planning) in MRP1.
       It is possible that system can create Planned order by using any contract/ agreement of that material???
    Thanks,
    Shailendra
    Edited by: Shailendra Hadkar on Mar 14, 2008 12:17 PM

    Hi
    you have to create Planned order manually from MD11 using planned order profile NB.
    system cannot automatically create planned order from contract etc, without MRP.
    Regards,
    Krishna Mohan

  • Planned Order convert to PR

    Hi
    When I do conversion of planned order to PR, the defaulted PR type is NB, but I would like to change it to ZNB (customised), now I need to change it manually during the PR screen, how can I defaulted the PR type to ZNB. I look at the IMG, in the planned order conversion to PR, the NB there is for planned order not for PR, I cannot find the relationship of the planned order type to PR type..look at PR IMG, cannot find anything as well..
    anyone done this before please share, this should be something common as of many company do change the standard PR type of NB to ZNB..
    thanks
    dannnysao

    Hi,
    The system determines the document type from the stettings u are making in "planned order Profile" in Customising for MRP. There u define the order type, the procurement key and the special procurement key and also the account assignment category. So based on the procurement key and the special procurement key maintained in the Marterial master, the document type is selected.
    Production > Materials Requirement Planning > Procurement Proposals > Planned Order > Define order profile
    Choose the planned order type - NB1 Within this you specify the P req doc type to be used.
    Through MRP group and the different PR document type for MRP generated PR is possible only if you assign the document type to MRP group in the MRP configuration.
    You need to perform some modifications in  as per OSS Note : 46919 .
    Please try and come back.
    Regards,
    R.Brahmankar

  • Default PR Type when convert from Planned Order

    Hi all,
    How can I default my PR Type when convert from Planned Order after MRP run. This can done via MRP Group control but how to go about controlling via Planned Order profile?
    Which planned object type and planned order profile to be used? assuming that i need my planned to be output at LA type and convert to NB1 PR type instead of the default NB PR type?
    Thanks.
    Regards,
    Andrew

    Hi,
    The system determines the document type from the stettings u are making in "planned order Profile" in Customising for MRP. There u define the order type, the procurement key and the special procurement key and also the account assignment category. So based on the procurement key and the special procurement key maintained in the Marterial master, the document type is selected.
    Production > Materials Requirement Planning > Procurement Proposals > Planned Order > Define order profile
    Choose the planned order type - NB1 Within this you specify the P req doc type to be used.
    Through MRP group and the different PR document type for MRP generated PR is possible only if you assign the document type to MRP group in the MRP configuration.
    Please try and come back.
    Regards,
    R.Brahmankar
    Edited by: R Brahmankar on Aug 28, 2008 10:54 AM

  • Purchase requisition type while converting planned order

    When We convert planned order to purchase requisition in MD04 how the system picks the  Purchase requisition type ?What configuration needs to be done in Spro

    Dear
    Please check the following
    Basically , document type selection for PR depends on the planned order profile -SPRO-MRP-Procurement Proposal-Planned Order Profile .
    Check in
    1.OMDV -Conversion of planning run -Purchase Req item -Order Type -It should be NB
    2.Or else , check in OPPR-Carry plant parametrs MRP group -Scehdel/documets type .-NB.
    MRP checks in MRP group level.
    Regards
    JH

  • Settings for order type in planned orders

    Dear All,
    Where can i customise the order types for planned order.?
    My scenario is.. i can not send complete product in vehicle , which has to be dismantle and send in different vehicle, so the different invoices are required. i can dismantle  the product and add these assemblies as line item and invoice. in this case i will loose the main product code which i dont want. i wanted this to behave similar to phantom item , where i can see the phantom item and plan only components.
    Please throw sme lite on this...
    Thanks
    Raghu

    Hi
    You can customize the planned order profiles in
    SPRO--- Production MRP- Procurement proposals -
    Planned orders--- Define order profile.
    Thanks
    S.Murali

  • Different type of planned orders

    Hello Friends,
    I went to an interview, in which I've been asked a question to describe different type of Planned Orders ?????????
    Is there type's of planned orders in MTS or MTO environments ???
    Pls enlighten me on this.
    Thanks Sir,

    Rahul,
    For interview questions, you should first consult with SAP online help before posting a question on this forum.
    In SAP, there are not planned order types, there are planned order profiles.  SAP supplies some basic ones, and you can create additional profiles as well.  Reference to order profiles when creating planned orders
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/f4/7d310944af11d182b40000e829fbfe/frameset.htm
    and surrounding pages.
    Configuration for Planned order profiles at OMDD.  Doc:
    http://help.sap.com/saphelp_46c/helpdata/en/48/e92c7dd435d1118b3f0060b03ca329/content.htm
    Standard as-delivered Planned order profiles are
    KB     Standard purchase order
    KD     Individual customer order
    LA     Stock order
    LB     Standard purchase order
    LBE     Standard purchase order
    NB     Standard purchase order
    NBE     Standard purchase order
    PR     Project order
    UL     Standard purchase order
    You can see the details of these in OMDD.
    Best Regards,
    DB49

  • Define New Planned Order Type

    Hi All,
    I would like to ask where in SPRO can I define a new Planned Order Type (not the Planned Order Profile). 
    For example, the existing Order Types are :
    NB - Standard Purchase Order
    LA - Stock Order
    RS - Reservation
    KD - Individual Customer Order
    KB - Consignment Order
    OE - Run Schedule Quantity
    VP - Planned Independent Requirement
    I would like to add a new Planned Order Type Z1 and change the scheduling type from Forward to Forward Time. 
    Thanks in advance.

    Dear
    In SAP Standrad , there is nothing called Planned Order Type .Basically , it is the planned order profile which decides  all the realted category like accounting assingment  , special procurement , prcurement type etc .
    So you need to fgo SPRO-MRP-Procurement proposal -Define planned Order profile -New entries .At the saem time  assing the accouting assingment categoery in OME9 and define scheduling parameters in OPU3 ( Scheduling Type , Adjust scheduling , Logs ,Automatica scheudling , CRP  etc )
    Hope this helps
    Regards
    JH

  • Query about planned order

    Sir,
    Can I create planned order manually ?
    I have defined procurement type X for FERT material type. Hence while doing MRP run, system shows planned order. Now planned order can be converted into purch. reqn or production order. But while converting planned order into purch. reqn it shows the procurement type as E i.e inhouse prodn. Can we have a debate on this matter ?

    Hi,
          Since it has been correctly cleared/answered by "mangalraj; that-
    Planned orders can be manually created using T.Code MD11 for a suitable planned order profile.
    However while converting this so-called planned order  into Pur Requistion ,first make sure-whether it manually created or by MRP Run?
    If Manually created,it would reflect Procurement Type 'F.
    If By MRP,it would reflect Procurement Type 'E'.
    And please note that above two outcomes are standard SAP functionalities.It can work  in another required process provided the configuration is done accordingly.
    Hope it fulfils your requiremnt at some extent.
    Please revert if required.
    Regards
    Chandra

  • Planned order types

    Hi All,
    Is it possible to create new planned order types. I need to create a copy of NB, LB etc.
    If so how and how do I get MRP to use the new ones?
    I now how to create a new planned order profile but I still have to select the original order types!!!
    Thanks
    Stuart

    Dear Ramesh,
    I think, you must post your thread in to Forum - [SCM - PP|SAP ERP Manufacturing - Production Planning (SAP PP);
    Best Regards,
    Amit
    Note: Check with:
    Re: Planned Order Type
    Re: Planned Order type

Maybe you are looking for

  • How to install OID connector using OIM API in 11g?

    Hi All, We are using OID connector in OIM 11g environment. It is a simple process to install OID connector by unzipping the connector zip file to ConnectorDefaultDirectory and goto Admin console and load the connector. However, we are looking for API

  • I need to pass values dynamically into schedular

    I need to pass the values into the schedular dynamically like 2 hours ,4 hours ,i minute and soon ...

  • Scratch disk is almost full

    Hello, I just got a message while I was using photoshop that my scratch disk is almost full and that I need to delete files to clear up space. I am not sure how to clear files from the scratch disk. I cleared all the files listed under open recent. I

  • DW8 No longer creates standard Recordsets

    For what ever reason, I want to blame it on an extension, but I seem to have two unique problems. The first is when I try to creat a recordset (using a connectionless string) DW8.0.2 places : <!--#include @@urlformat@@="Connections/connQuality.asp" -

  • Double tap to wake up screen function for Sony Xperia Z Ultra

    Hi all, i have a question, how to configure "double tap to wake up screen" on sony xperia z ultra.. thank you so much.. Reo