Planned order qty. based on usage probability in quotation
Hi ,
I created a quotation with 5 qty. and kept usage probability as 60%. I did the requirement transfer in MRP.In MD04 it generated a planned order of 5 qty. and quotation with 3 qty.
Is there any setting so that system should generate planned order also with 3 qty. i.e. same qty that of quotation.
Regds
Hi,
After the req. transfer from quotation to MRP, go to MD04 & check the qty which has been transferred, is it 5 or 3 ?
If it is 3, then check in material master / info-rec if any min order qty / min. lot size is maintained. Also check the lot sizing procedure & safety stock if specified.
Regards,
Vivek
Similar Messages
-
BADI For Changing Planned order Qty during MRP Run
Hi,
My requirement is i want to change Planned order qty based on some conditions during MRP run(MD02). Is there any BADI to fullfill my requirement.
Thanks,
KishoreNot sure I understand the situation correctly...You want to delete the planned orders before MRP runs again. WHy do you want to do that ? Are these firmed Planned orders ?
-
Production order and planned order qty should not consider in MRP
Dear All,
i do not want to consider the previous month production order qty and plenned order qty (Nothing but WIP qty) in the current momth MRP, but the stock has to consider in MRP.
Example,
Before MRP,
material : XYZ
Stock : 1000
Prod Qty : 500 for 02.04.2008
PIR Qty : 2000 for 02.05.2008
After MRP, the requirement should be as below said,
material : XYZ
Stock : 1000
Prod Qty : 500 for 02.04.2008
PIR Qty : 2000 for 02.05.2008
Pld OrdQty : 1000 for 02.05.2008
For the above requirement ,i have done settings in the availabilty check like , for include planned order and include production order are "DO NOT TAKE IN ACCOUNT".
Even then also the planned order qty is generating for the "500" only.
please give the solution for the above said requirement.
thanx in advance
Regards
Srinivashi
MRP will always consider the prod order qty while doing nert req calculation.One thing u can do is TECo the prod orders and un MRP then it wont consider prod order qty.
The Availability check will check whether the components r avalaible or not based on ur scope of check
Reward points if useful
Amit -
Hi I want to round off my order qty based on ROH. Say ROH is available multiples of 0.6 TONS.My Fert is need to plan so to that it consumes 0.6 ,1.2 , 1.8 etc TONS.
Without using Material-Qty calculatiuon is it possible?? Because I am using Discrete Mfg.Hi,
You must be having the Lot-size as EX.
In this situation, For your lot size : EX, in OPI4, Activate the MTO Lot size as "1" (Lot-for-lot with Rounding).
Maintain the Rounding Value in MRP1 View.
Now the Order will be created with Multiples of your rounding Value.
Hope this helps..
Regards,
Siva -
Bapi for sfg dependent dem,snp planned order qty, and ppds planned orde qty
Hi Gurus,
I am not much familiar with APO, so please help me,
Input details:
Field Value
Planning Version 000
Source Location * 1001 Single/Multi Value
Product * 1000061 Single/Multi Value
Production Planner * PRC Single/Multi Value
Start Date *
End Date *
o/p:
Source Location Date Semi-Finished Material Material Description SFG Dependent Demand SNP Planned Orders qty PPDS Planned order Qty Total SFG Variance due to Lot size Total SFG Variance reference to dependent demand
1001 15-Jul-10 1000041PP PRIMARY FF MILK 3% FAT 340 412 420 8 80
1001 15-Jul-10 1000041PP PRIMARY FF MILK 3% FAT
1001 15-Jul-10 1000041PP PRIMARY FF MILK 3% FAT
Is there any bapi to fetch the data as shown in o/p.
ThanksHi Phani,
Tryout the below BAPIs
IF10503 (object)
BUS10503
Regards
R. Senthil Mareeswaran. -
Planned order qty. shodnt change after copying quotation and creating SO
Hi Guys,
In my scenario i am creating a quotation of qty. 100. Sytem generates planned order of 100 qty.After i copy the quotation and creates a sale order changing qty. to 50, the system is changing the planned order qty. to 50 whereas the requirement is planned order qty. must not change i.e. it must be 100.
Is there any setting for this.
Regards
Laxmikanthanswered
-
Adding Total plan order qty to 2lis_04_p_matnr
Dear BW Gurus,.
I am appending a standard field (GAMNG - Total plan order qty) to the extract structure MC04P_0MAT.When i activated the structure,got it done but with warning that the Field GAMNG is not within the customer namespace...Now when i check the DS,the appended field is present with "HIDE" AND "FIELD ONLY" Options checked.When i try to uncheck them fields and check "select" field and save,it throws an error" THE OLTP SOURCE STILL CONTAIN ERRORS"..Would appreciate any help on this..
manythanks
arunHi,
Check by deleting the setup table for the DS 2LIS_04_P_MATNR.
If there is delta already running, then you need to do initialization once again for field GAMNG.
Vis -
User should not allow to exceed planned order qty
Hello Experts
In present case user can change the planned order qty when he converts it to a process order or purchase requisition.
Is there any way to restrict the user, where user can not exceed the planned order quantity?
Request to reply with a solution.
Regards
Pradipta SahooHi Sahoo,
I have two suggestion regarding the restriction of Changing the quantity while converting the Planned order into Process Order OR Pur Reqt. :
1. First one is through the authorisation for the user, the suggestion given by our friends.
2. You can use a User exit in the Planned Order Conversion transaction (CO40 / CO41/ MD04 etc). Where you can code to refer a Z- Table created with the User whom to be allowed.
You can create a Z table and mention the user id for whom system should allow the change of Quantity during converion of planned order. So wheh the user is trying to convert the planned order system will fire the User exit and check if the user is available in the Z-table then it will allow him/her to modify the qty otherwise it will through an Error as required.
Request you to take the help of the Abaper to invoke the userexit .
I can suggest the third option too, but not sure whther it will work, you can try out.
3. If you feel no user should be allowed to modify the quantity then I suggest you to create a Error message in the conversion tcode if the qty is being modified. You can try using a field exist.
Regards
radhak mk -
Determination of Planned Order Type based on Requirement
How does order type for planned order gets determined?
For example
planning strategy 50, planned order type is VP
planning strategy 10/40, planned order type is LA
planning strategy 20, planned order type is KD
Checked in tcode OPPS & SAP forums, could not able to find how
does system determines planned order type based on type
of requirement i.e. sales order/PIRHi,
please check the link below:
http://help.sap.com/saphelp_scm2007/helpdata/en/87/04f73b8003b409e10000000a114084/content.htm
Regards,
Alok Tiwari -
Reserved sales order qty based on sales order
Dear All,
is there any way to reserve the sales order qty in stock based on the sales order?. Actually i want to block the some qty for paticular sales order. For example I created one sales order with 100 qty of x article and now i want to delivery of sales order with the same qty after one month . In this case i want to reserve this qty for this sales order that should be not deliverd by another sales order.
Thanks
AbhiHi,
Block this qty against sales order
MB1B >>> Use movement 413 & enter
Speciefy sales order number & item number
Then this qty will be permanently reserved or blocked for the perticular order.
Kapil -
Planned Order Qty updation in S225 Table
Hi Friends,
In S225 Table there is a filed of Planned Order PGMNG. Can anyone tell when this field gets updated?Dear Nilesh,
Update the statistics using MF27,after taking MRP run.
Check and revert back.
Regards
Mangalraj.S -
Production Order created from Planned order qty should not be changed
Dear PP Gurus,
IKindly give your valuable inputs on the below mentioned subject.
From MD04 planned order is converted to production order user should not be able to reduce the requirement quantity below Production Order quantity.
Thanks & regards,
Shanmugam BalamuruganHi,
This is common problem. to control this you need to develop an user exit . This exit will check the fixed lot size in material master and will compare with the quantity of production order. The exit will get fired at the time of order saving.
If any miss-match happens system will give an error message
Regards
Amit Parkhi -
Open Purchase order Qty based on BUM
Dear Experts
We place the po in different different unit But I need the Open quantity based on basic unit of measurement.
how can I take this details. what and all tables I need to look to conver order unit to base unit of measurement .Hi,
Take the selection option from ME2O. How u want Pur. group base. Or user base
SAM -
Planned order against quotation
Dear guys,
In my current scenario i need to create quotation and against the quotation multiple sale orders will be created.
i created quotation with 5 QTY. and system generated planned order of 5 QTY. Now i created one sale order referring to quotation but changed QTY. in sale order to 3. Now when i checked in MD04 system is showing planned order of 3 QTY.
But the requirement is planned order QTY. must remain 5 against the Quotation and mutiple sale orders can be created.because production must happen for 5 QTY. only.
Regards
Laxmikanth1. what is the Qutation type that you are using ( Kindly tell me the equivalent to standard)
2. Also which t.code are using to create the quotation ( va21 / va01)
reg
Dsk -
Check in Production order qty with ref to Planned order
Dear all,
Please suggest me, when i am creating a productin order with ref to planned order , so the order qty should not exceed the planned order qty.
How can i control this , please give ur valuable inputs on the same.
regards
Ravi AroraDear
If you are not particualr to conver the planned order to production order through CO40 , then you can control with the help of
Enhancement : PPCO0007 (Exit when saving production order)
Functional Module : EXIT_SAPLCOZV_001
Include : ZXCO1U06
Compare the Order header Qty with the sales order Qty If the production order header qty is more do not allow the system to save the production order..
Otherwise please check those out for your requirement :
Planned Ord. to Production Order User Exit (PPCO0005)
EXIT / BADI for Tcode CO40
Regards
JH
Maybe you are looking for
-
Possible bug in GDM with new user
Hi, I created a user in the system settings app in gnome and I set the password to be set at first login, but now logging out of the current user and trying to login to the new user without the password on gdm I just get nothing where 'create new UNI
-
XDM has problems with consolekit
I recently switched from SLIM to XDM, and now when I shutdown the computer in gnome (launched using ck-launch-session), the computer sometimes restarts instead, even though I pressed 'shutdown'. This didn't occur with GDM or SLIM. /etc/inittab line x
-
I am facing a strange behavior from SharePoint:DateTime control. I have a webpart containing couple of fields along with datetime control. If I leave this page inactive for a while and then click submit, an exception is thrown stating that "Hour, Min
-
LISTENER" finished with status TST_ERROR
Hi all, I'm tryin to do a systemcopy. I get this error by the db upgrade: "MUT-03010 Execution of the command "/oracle/<SID>/102_64/bin/lsnrctl stop LISTENER" finished with status TST_ERROR The step StartListener with step key .... was executed with
-
Install two CC memberships on the same computer?
My primary computer is broken and being repaired. In the meantime, I'd like to install my CC Illustrator and Photoshop on a secondary computer, so that I can continue to work. My husband has already installed his CC photographer's membership on tha