Planned order scheduling mass update

Hello all,
Is there a way I can change the scheduling dates for the planned orders collectively. (not MD16) ?
Thankyou

Hi,
check the following
Mass Changes of Planned Orders (Action Control)
Use
You can use this function to execute one or more actions for a large number of planned orders simultaneously. This is possible both within the SAP System and over an interface from an external assembly control system.
Features
SAP supplies the function module MD_SET_ACTION_PLAF for action control.
This function module includes the following actions:
Explode BOM
Explode BOM, check availability
Check availability, only explode BOM in the case of a requirement
Check availability, do not explode BOM
Reset availability
Change planned order data
Schedule planned order
Delete planned order
Confirm planned order (in repetitive manufacturing)
Firm planned order data
Firm planned order components
Print component overview
In connection with an action, you can always change planned order data, for example; order quantity, dates or production version.
The function module also enables you to program further customer-specific actions.
You can execute the actions for several planned orders simultaneously.
You can create action chains, that means, have the system execute several actions in a single operation.
Activities
Define your own actions and program a report that includes these actions. As an example of this, the transaction MDAC Execute action for planned order (MRP ® Planned order ® Execute action) is available.
In this example action, you can use actions only for individual planned orders. Nor can you form action chains, only simple action transitions are possible.
Determine an action key and action controls in Customizing for MRP in the IMG activities Define action key and Define action control. An action key describes the actions that can be executed for a planned order. Action controls determine which actions are allowed and in which sequence they are to be executed.
Assign the key for the respective action control to the materials in the material master (MRP 4 view).
Regards,
nandha

Similar Messages

  • Collective Planned orders Scheduling for lower level orders with reference to the Superior order

    Hi All,
    Collective planned order scheduling.
    I have been trying to reschedule the superior planned order and i was expecting the lower level planned orders to reschedule based on the superior planned order.
    My problem is
    when i try to reschedule the superior planned order the system is not rescheduling the lower level planned orders.
    For example if i change the basic finish date of superior planned order as 30/09/2014 and reschedule the planned order it is only scheduling the header planned order and the lower level planned order is not scheduling.
    Could some one tell me why this is not happenning at planned order level.
    As the rescheduling of collective order will work at production order level but for some reason it is not happening at planned order level(as there is no option available to do so).
    Please give your thoughts on this asap.
    Mahee.

    Hello Mahee
    Please observe that your system is working as designed. Planned orders are scheduled independently, even when they are part of a network/collective order. Note 152319 explains the planned order scheduling in detail and it provides the following information:
    * No scheduling of overall networks is executed although a directly manufactured component is assigned.
    Note that no scheduling of the overall network is executed for planned orders. For the components requirements dates are determined. In order to cover them, planned orders are created in the next MRP run. Since the requirements are not managed using the exact time, the results of the planned order scheduling and of a scheduling of the overall network of the converted collective order can differ.
    BR
    Caetano

  • Planned orders scheduled on Non working days

    Hi,
           Planned orders scheduled on Non working days no Planning calnder assigned to the Material

    Hi
    Just go to transaction code MD26 and check the what calender is assigned to plant and validity period of the calender. If the calender is not valid in the MRP run period then also planning may differ
    Krishna

  • How to view the planned orders in mass and how to delete in mass

    Hi gurus,
    How to view the planned orders in mass and how to delete in mass.
    Regards
    R.Rajakarthik

    Hi,
    Use the collective display of planned orders, transaction code MD16.
    You can select the data by different options and choose which ones or all that you need to delete.
    Click the Delete button to trash them.
    This will delete planned orders without deleting the planned independent requirements and sales orders.
    Hope it helps

  • Delet plan order through mass processing (cohv)

    hello,
    PP experts i want the solution for deletion of plan orders in the transition cohv
    in the COHV transition  the mass processing selection do not have the function
    technically complete for plan orders.
    plase tell me how the function tech. complete can be created for the plan orders in the COHV.
    regards,
    mangesh

    Mangesh,
    As suggested by fellow forum members "MD16" is the only possible option in Standard SAP to delete planned orders in mass.
    If you need anything other than that you need to go for your own custom program to do the way you want.
    Please close the thread after rewarding points for answers which helped you.
    Regards,
    Prasobh

  • Planned order scheduling in mrp

    hi
    iam trying to run MRP at my client place
    facing problem in planned order dates
    i choosen  tequirement type BSF and strategy group as 11
      in md 61 pir was given in a month of june2008(monthly)
    after mrp run at modo4 iam getting planned order with
    execption message 64 called order date in past
    means iam getting planned order START DATE AND END DATE IN THE MONTH OF JUNE
    where as i need to  my planned order satar date in MAY MONTH and
    end date must be 1st of june
    means i given PIR which is my start of my june month
    checked scheduling parameters which  says backword scheduling, and i choosed planning mode 3 and leddtime scheduling
    plz suggest which setting effects the planned order start and end dates??
    regards
    sasikanth

    hi
    i selected schedule margine key with 0 flots (key000)
    and chossed *LEED TIME SCHEDULING (in mrp controll parameters :-scheduling 2 at MD02 )
    how the reduction strategy helps in this case ,casue i am doing lead time scheduling system has to consider only routing time ??? right ??
    plz suggest how to  arrest message 64
    regards
    sasikanth 
    message 64 diagnosis enclosed
    64: Production finish after order finish                                                                  (P4)
    Message no. MD427
    Diagnosis
    The production finish date calculated using the routing lies after the order finish date that was calculated using the in-house processing time in the material master record.
    As the system uses the order finish date in the planning run, this situation may lead to material shortages if production is not finished until the production finish date calculated by the system.
    System Response
    This exception is displayed in the MRP list and in the current stock/requirements list.
    Procedure
    Check the times in the material master record and in the routing.
    Check whether the order has to be rescheduled in.

  • Planned Order Scheduling - No Valid Routing Selected

    Hi Friends,
    I am trying to create planned order and then trigger lead time scheduling for it.
    I have maintained BOM, Routing, Production Version, and Scheduling Parameters for Planned Order as Detailed Scheduling with Scheduling Horizon as 50 days, and gactivated scheduling anf enerate capacity requirements in OPU5.
    My Production Version is valid through 12/31/9999 and also validity in terms of order qty is correct.
    I face problem of routing not being selected beyond the 70 days horizon.
    I could not understand why the scheduling horizon considered is 70 days tough i have maintained 50 as scheduling horizon in OPU5.
    Waiting for your valuable help and pointers
    Regards,
    Mayur

    Dear Maulik and Dhaval,
    Good morning, Hope you remember me.
    In my material master I have 28 days as inhouse production time but even aftre changing it to 0 there is not change in the leadtime scheduling result. I still get the message that no valid routing found.
    Dhaval,
    For the selection ID routing status matches. My problem is, If my Planned Order has a basic start date on or before 30-Apr-2009 when I try to schedule order it successfully fetches routing but when i give basic start date as 1-May-2009 it results in message no valid routing found.
    I though it might be because i have maintained detailed scheduling horizon as 50 days but 30-Apr-2009 is 70 days from now, so I am confused where to check for. My material even do not use production shceduling profile.
    Thanks for replying.
    Looking to see some clue
    Mayur...

  • Planned order scheduling

    Hi,
    I want to create a planned order which is planned automatically and be visible in CM01..How can i do this?
    Thanks

    Hi Ellen,
    1.if you run the MRP run  (MD02)for material with lead time scheduling  indicator(scheduling =2) , u can see the palnned orders in CM01.
    Before that, u have to define capacity data under capacity view of work center that involved in planning.
    And also ensure " scheduling  & generate capacity reqs" check box has been selected for your plant and order type combination in OPU5
    regards
    pradeep

  • OPU5 Planned Order Scheduling

    Hi, I'm having a problem with my detailed planning scheduling.
    It is set for backward scheduling in config OPU5.
    Yet in the dropdown menu I can only choose between capacity requirments and Current date.
    Br matthias

    Please check OPJN setting

  • Scheduling of planned order and Production order

    Dear PP gurus,
    I have run MRP , after running MRP, system has created planned order. These planned order dates are  schedule by the system in 2015....I am not able to understand. how? . When i  double click on
    planned order order and try to convert it in production order  those dates get copied into production order.
    DO i need to change the dates thr? or  keep the same dates  which the system is giving>
    I  m going wrong somewhere. please tell me where and   what is config for scheduling for planned order and production order?
    Please tell me step by step procedure
    Regards
    Edited by: Aadi1981 on Apr 1, 2010 9:02 AM

    Thanks for replying,
    I have done the below setting for shceduling. Kindly check and let me know any setting needs ot be changed or incorect
    FOr scheduling  production order , i have configured below settings in OPU3
    In OPU3 ,  
    Detail scheduling tab
    Scheduling and  Generate cap req tab is checked.
    then
    adjust scheduling , adjust dates  tab,    :  adjust basic dates , adjust  dep , reqt to operation date  is selected
    scheduling type is backward.,
    Automatic scheduling tab is  checked.
    In OPU5
    Scheduling of PLanned order
    Scheduling and  Generate cap req box  is checked  (selected)
    Adjust scheduling
    Sheduling level: via  detail  scheduling
    adjust dates:     adjust basc dates , adjust  dep reqt , req to  operation dates
    For capacity  scheduling ;  always  basic dates, dep reqts to operation dates
    scheduling type ; backwards
    apart from this do i need to do update  ca96/ ca97?
    best Regards
    Edited by: Aadi1981 on Apr 3, 2010 7:42 AM

  • Using Planned order Change BAPI with out changing date

    Hi
    I have a planned order with start date in future.
    With in a program, I want to call the planned order using the FM BAPI_PLANNEDORDER_CHANGE to re-explode the order BOM.
    I find that only if I change the order start date to system/current date, the planned order BOM gets updated/re-exploded. Else there is no change in the order BOM.
    My requirement is to re-explode the BOM with out changing the order dates. In the function module I am maintaining "X' against BOM_EXP_FIX_IND.
    But when I do it manually using MD12 and explode BOM with out changing the future start date, the order BOM gets updated.
    Please help on this. Or is there any other FM/BAPI for this purpose.

    Dear Pradeep,
    you could try to set DET_SCHEDULE = X with out
    FIRMING_IND  --> No
    BOM_EXP_FIX_IND   --> No
    Let me Know if it modification setting have solved your problem and i have useful for you,
    Daniele

  • Repetitive manufacturing - Planned order

    Hello,
    I have got a list of 'firmed' planned orders of repetitve manufacturing. How to unfirm those planned orders in mass?
    Regards.

    Dear Mangal,
    I re-checked in the system & MD19 does not have option to go by planned orders. Further the options which exist are for single entry.
    However I wont say that the BAPI is the only solution, as the need in the initial query just states there are many firmed planned orders. It does not provide further details, so if its just for a single material or MRP cont. etc then MD19 should suffice.
    But if the planned orders are for different materials, then user has to do multiple MD19's or if the effort justifies the business need, then develop a Z program.
    Regards,
    Vivek

  • SAP PP-delete Production orders, planned orders, purchase requitions & othe

    How to delete Production orders, planned orders, purchase requitions & other orders .
    Pls send me the T-codes or Paths.
    Any comments welcome   & Thanks in advance.

    Dear,
    1) Delete Production Order,
    Please refer this link,
    [DeleteProduction Orders |http://www.sap-img.com/production/how-to-delete-old-production-orders.htm]
    2) Delete Planned Order,
    MD16 is the only option to delete planned orders in mass.
    During MRP run if you choose - Delete and recreate plan order mode. Automatically the unwanted plan orders
    2) Delete Purchase Requisation,
    Execute MD04, in that it will display the created PR's
    Check in tcode MD62 whether you have any demand for that material which you are getting PRs first delete requirement here/
    Then run MRP by tcode MD03 or MD02 giving input of material and plant. In the initial screen of MD03 / MD02, make field planning mode - Delete and recreate planning data
    Is that Old PR Firmed.
    If yes remove the Firm indicator and Re run the MRP with planning Mode 3.
    It removes the PR from EBAN.
    Now check in MD04
    OR,
    Use Mass change transaction code MEMASSRQ or use BAPI (BAPI_REQUISITION_DELETE) to do the same.
    Or
    Use ME57 with layout ALV, in this also u can delete PR
    If you want delete PR manually then
    goto ME52N --> enter PR number --> select line item --> click delete button
    or
    goto ME52N --> enter PR number --> Item --> Tab Quanties/Dates --> set tick mark for closed check box
    Please check this thread,
    Deletion of SubReq
    Hope it will help you.
    Regards,
    R.Brahmankar

  • Planned Order Delete

    Dear ,
    Can it be possible by single t-code i can delete all the planned order at plant level.

    Dear,
    You can delete a planned order by tcode MD12 / MD04 OR delete the requirement in MD62 after that run MRP (MD02) with planning mode-3 deleted and recreated. OR MD16 is the only option to delete all planned orders in mass.
    And check the result.
    Regards,
    R.Brahmankar

  • Mass update for production and planned order MRP controller

    Hi Gurus,
    It's anyway possible to mass update MRP controller for Production orders and  Planned orders. If any please provide me step by step process.
    Thanks,
    B.Deethya.

    I feel You have changed the MRP controller in Material master and want to incorporate same in production order & plan order.
    For Planned order Run MRP with delete and recreate mode, system will create a new plan order with MRP controller in Material master
    For production order, Mass change is not possible, create a simple BDC or LSMW, And change the MRP controller

Maybe you are looking for

  • PlanAhead - unable to open design - security attributes in generated netlist

    Hello, I am using ISE and PlanAhead 14.3 and the design goes fine inside just the ISE flow, but does not open in PlanAhead at all when I try to analyze or floor plan the device. The exact message is: ERROR: [Designutils 20-396] Could not read top des

  • Parsing sensor data (out of JMS queue)

    Hi, I´m currently trying to implement sort of a monitor using sensors. I´ve managed to set up a JMS queue that is used by a sensor and I have casted the message i got to a com.evermind.server.jms.EvermindTextMessage. However, all I can get out of thi

  • Problem uploading SSL certificat on a WLC 5508

    Hello, I'm trying to upload a SSL-certificate (RSA:2048) on a WLC 5508 via the "Management->HTTP-HTTPS" - Tab and get the following problem : *TransferTask: Jul 18 16:36:14.487: %UPDATE-3-CERT_INST_FAIL: updcode.c:1276 Failed to install Webauth certi

  • How can I set custom socket time out value ?

    I have tried to use httpclient, but it seemed that it didn't work. The time out value is still about 4 minutes, not 30s I set. Anyone know this? Thanks Qing

  • Delclaration of data type Char

    Hi Friends, My Requirement is as follows. I am having the amount filed.I have declared the Var as data var1 type P decimals 2.But Now In the output i am getting the the variable value as ****44.000.So Start(* is nothing but spaces.So I am getting 5sp