Planned orders scheduled on Non working days

Hi,
       Planned orders scheduled on Non working days no Planning calnder assigned to the Material

Hi
Just go to transaction code MD26 and check the what calender is assigned to plant and validity period of the calender. If the calender is not valid in the MRP run period then also planning may differ
Krishna

Similar Messages

  • Scheduling on non working day

    Hi All,
    If plant is linked to 5 day calendar, but we enter the finish date on  Saturday (with backward scheduling)
    system after displaying the warning message, automatically change the finish date to work day.
    Could we turn off the behavior and allow end user to override the date and have the finish date on Saturday.
    regards,
    Mohit Goyal

    Dear Mohit Goyal,
    Switch on the debugging mode after entering into CO01 and giving the date(which falls on saturday or
    sunday) with the help of your ABAP consultant and you can give a try for this.
    Also check this link,whether can it help you.
    Re: Operation to be scheduled on Holiday
    Regards
    Mangalraj.S
    Edited by: Mangalraj.S on Jan 9, 2009 9:32 AM

  • Supressing non work day messages for material requirments on Work orders

    Message CN687, pretaining to delivery date of materials takes into account the factory calender/nonwork days of the calender associated to the plant. This message pops up for every material line item on a work order, One could understand how involved it can be if ther are a number of materials on a work order, as you would have to enter passed each warning before continuing.
    Is there a way without preforming a mod that will allow us to supress this message on the work order side. Supply chain still wants to see it, however maintenance does not?

    Hi,
    As per my understanding your planned order is scheuling for 2 days.Check teh capacity view in the std plang book and check the date on which the capacity is being shown.IF the same is not showing on 15th then the problem is with scheduling not with capacity load.
    Also check the factory calendar assigned to resource master data.Check the date 15th on the bucket capacity on resource master SNP bucket capacity view.If the same is showing as working day then the master data needs to be changes.
    Hope this can help.
    regards,
    kaushik

  • How to create orders and deliveries on Non-working day.

    Greeting all,
    We set up all our national holidays and Sundays as non-working day in our working calendar for Japan(OY05) .
    But I have a request from Sales Dept that only one customer wants us to deliver products on the holidays.
    We don't want to affect other customers delivery date so we are thinking we have to change the holiday to working day on the day before the holiday for the customer.
    But we need a complicated procedure to change the calendar in our company IT rule so I am wondering if there is any other good solution that we don't have to change the calendar so often.
    Does anybody have the same situation like this?
    I will appreciate any kind of suggestion.
    Thank you very much for your help in advance.
    Best regards,
    Miki

    George,
    I understand that is simple and correct procedure but I wanted to consider other possibilities to ship on non-working day because it is NOT working day here.
    Finally, our management have decided we don't change the calendar and ship with date the system proposes. They explained the customer and our distributor center that shipping date is one day ahead because of the calendar.
    To all,
    Thank you very much all of your advice.
    Best regards,
    Miki

  • Factory Calendar to prevent delivery on a non-working day

    Hi Guys,
    You may have already come across this problem and hence requesting your inputs on the same.
    I'm able to create a delivery for a sales order on a week-end even though they happen to be 'non-working days' in my Factory Calendar. I have gone through the search forum and the 2 things that most of them said was to attach the Factory Calendar (having Sat and Sun as non-working days) to the Plant and Shipping Point, which I have already done, inspite of which I'm able to create a delivery for a schedule line date which falls on a non-working day.
    My business scenario requires that even though a Sales Order may be created on a non-working day, the delivery should only be possible on the next working day, even if stock is available on those non-working days.
    Your thoughts/suggestions/ideas would be useful.
    Regards,
    Shripad

    Hi Shripad,
    In Customer Master, General Data , We have  Unloading Points  Option. There we can opt for the delivery to the cutomer.
    Then we can stop delivery for that day.
    Award points if it adds information.
    Thanks
    Mohan

  • Create absences on non-working days.

    Hello Time Gurus,
    I have a scenario in which the employees can record absences on a non-working day.
    The scenario is as follows-
    I have a Work Schedule -
    Sun(working) Sat(working) Mon(working) Tue(off) Wed(off) Thu(off) Fri(Working)
    The working days have a planned working hours of 9 hours and off day has planned working hours of 0 hours.
    I have two sets of employees (ESG) - Salaried and Hourly.
    The hourly employees should to be able to record absence on non-working day (non-working for me includes the public holidays as well).
    I have set the input checks for the absence type OFF on non-working day. I am able to record absence but with 0 absence hours, even though I input some absence hours...the absence hours turns zero because of the planned working hours maintained as zero on non-working day.
    How can I achieve this?
    Thanks & Regards, Swapnil Mishra

    Swapnil,
    How can I now configure so thet the hourly worker on non-working day...can record some absence...
    how will we overcome the planned working hours as zero abd convert the same to working using the sleection rules for daytype....
    I still don't understand why you want to put an absence on non working day.
    Suppose the first week of Jan is as below in period work schedule 01.01 to 07.01
    NORM NORM NORM NORM NORM OFF OFF
    NORM will have 8 working hours and OFF will have zero working hours. Suppose say that 03.01 is a public holiday.
    In DWS NORM planned hours will be 8 hours but still due to day type rules it will be a holiday(non working day) day type = 1
    So now 03, 06 and 07 are all non working days for both salaried and hourly class.
    Now do you want that for hourly employees these days should be considered as working? and the same days should be non working for salaried?
    AJ

  • Non working days in Deployment

    Hi all
    When running the deployment, system is proposing a non working date in the deployment order although a shipping calendar is assign to the location.
    Saturdays and Sundays are non working days in the shipping calendar.
    Does anybody knows how to fix this issue?
    thanks so much

    Hello,
    The problem should not be with deployment.
    Deployment only "confirms" the planned distribution demands created by heuristic (or other planning run).
    You must first make sure that there's no distribution demands created in non-working days by the planning run before deployment.
    Please make sure that you have set the calendars correctly and run the planning run again.
    Best Regards,
    Ada

  • How to enter a Absence on a Non- working day?

    Hi All,
    In our company we dont have exact work schedule rules. So we have the need to be able to enter a Absence on a Non- working day for Salaried employees. when i try to enter an absencen on-working day, the number of hours are zeroed out.
    What configuration settings I need to do So that the system will take a Absence on a non working day.
    Thanks in Advance!!!

    Hello,
    I am having the same problem currently.
    When an absence that is less than one day is entered on a non-working day with a given start time and end time (we are using CATS for entering the times) along with some attendance records, there are collisions as the system tries to create the infotype 2001 record as a full day record, and the start time and end time is not taken into account, so we are not able to transfer these hours correctly to SAP HR.
    I checked all the settings regarding the day types, but could not find the trick..
    The days we are trying to create the absences and attendances for are not public holidays, just ordinary weekends with no working hours, so I don't think Holiday Class is relevant here at all.. 
    If anyone has a solution, please update the thread..
    Best regards,
    Nihan

  • Collective Planned orders Scheduling for lower level orders with reference to the Superior order

    Hi All,
    Collective planned order scheduling.
    I have been trying to reschedule the superior planned order and i was expecting the lower level planned orders to reschedule based on the superior planned order.
    My problem is
    when i try to reschedule the superior planned order the system is not rescheduling the lower level planned orders.
    For example if i change the basic finish date of superior planned order as 30/09/2014 and reschedule the planned order it is only scheduling the header planned order and the lower level planned order is not scheduling.
    Could some one tell me why this is not happenning at planned order level.
    As the rescheduling of collective order will work at production order level but for some reason it is not happening at planned order level(as there is no option available to do so).
    Please give your thoughts on this asap.
    Mahee.

    Hello Mahee
    Please observe that your system is working as designed. Planned orders are scheduled independently, even when they are part of a network/collective order. Note 152319 explains the planned order scheduling in detail and it provides the following information:
    * No scheduling of overall networks is executed although a directly manufactured component is assigned.
    Note that no scheduling of the overall network is executed for planned orders. For the components requirements dates are determined. In order to cover them, planned orders are created in the next MRP run. Since the requirements are not managed using the exact time, the results of the planned order scheduling and of a scheduling of the overall network of the converted collective order can differ.
    BR
    Caetano

  • Team Calendar non-working days

    Hi Gurus,
    Is there a way we can configure the team calendar to show non-working days for the employee (public holidays, days off in part-time/shift work-schedules) in green for example?
    I haven't seen any configuration options for this, but I would expect it to show them somehow!?  Will we need to do custom development for this?
    Many thanks,
    Russell.

    Hi Russell,
    You can check this<a href="http://help.sap.com/saphelp_erp2005vp/helpdata/en/2f/d7844205625551e10000000a1550b0/frameset.htm">SAP Help</a> for additional info on the Team Calendar iView..
    ~Suresh
    Russell,
    I didn't think the "10 points offer" was open to all.. ideally, it should be to Duxton only.. You could probably open a customer message in OSS & seek SAP's clarification on Team Calendar
    Message was edited by: Suresh Datti

  • Editing Working Days/Non Working Days in the base Project Calendar PWA

    Hello Experts,
    I am attempting to edit working days/non working days in the base project calendar PWA 13. I receive an error message when I attempt to open the base project schedule.
    I click the "edit" button under "Enterprise Calendars" page.  The error message states:
    "This Project Web App feature requires at least Microsoft Internet Explorer 8.0"  (using Chrome)
    Attempting to Opening PWA in I.E. I receive a different error message stating that I need Project Professional installed on my computer and it cannot find the current project.  
    I have Admin rights, I have project pro, and Im able to access any project or function using PWA and Project Pro. Can you tell me what I am missing (detailed steps--kinda new to PWA)
    Thanks so much.  

    If you allow me to jump in, I'd advice you to first open MS Project Pro and then try again.
    Also check that your MS Project Pro URL account do not finish with /default.aspx.
    Finally ensure that your PWA URL is in the trusted site and eventually add it to the compatibility sites.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • NON-WORKING DAYS

    Hi Gurus
    when SD and MM persons are doing their transaction on non working days (Sundays & public holidays).the system should restrict the posting.what i need to do if any configuration left pl z help me to restrict.
    Thank 's
    With Regards

    Dear Experts,
    I am also facing the same problem.  I have done all the necessary configuration settings in public holiday calendar and factory calendar. But when MM people are trying to raise a purchase order and do goods receipt on a non working day, the system is allowing them to do so, and even not showing any warning message and the same problem exists with SD people when they do any sales and deliver goods on a non working day.
    What additional settings should I do in order to make the system to throw an warning message atleast.
    Thanks & Regards
    Shankar

  • Non-working day setting affects in MM

    Hi,
    in case Saturday and Sunday are defined as non-working days in factory calendar, what funtions are possible in MM on non-working days? Is it possible to perform physical inventory, create and post deliveries, create purchase orders and so on?
    Br,
    Tapio

    done

  • Changing working and non-working days

    Hi
    I am trying to make a permanent (default) change in working and non-working days. I am living in Israel and our non-working days are friday and saturday. I want to configure these as the non-working days so I won't need to do it manually via the change work
    time menu.
    Thanks
    Chen

    If you are using project server then you can do it permanent from 
    PWA --> Server Settings --> Enterprise Data --> Enterprise  Calendar then
    You can configure either your stranded calendar or create a new calendar in which you can make Sunday to Thursday as working days and Friday and Saturday as non working days.
    You have to do it manually. There is no tool available which will do the same for you.
    Where as if you are using Microsoft Project professional stand alone then for every plan (MPP file) you have to do it.
    kirtesh

  • How to create an absence on a non-working day?

    Hi HR experts,
    Is it possible to create an absence on a non working day or holiday? I tried to do so and I get all these information messages, until it finally saves. But it wont accept any number of Absence hours. Is there a way to allow it to accept 10 hours of absence for a holiday?
    I'd appreciate your insight, thanks in advance!

    hello annalyn,
    I think you have got 2 possibilites.
    you have to change the absence definitions for entering on free-days
    table: V_T554S
    are you using TM?
    if yes, you can change in a rule the working hours.
    or second solution would be changing T556C for this absence. also and this i have not tested changing the day type.
    regards
    Stefan

Maybe you are looking for