Planning Calender MD26

Hi Gurus,
I have a requirement in Planning calender.
My clients wants to change the Planning Calender Validity Period From 2011 to 2050.
When I try to change (T Code MD26 ) the period from 2011 to 2050 it is allowing me to do it but when I try to save or click on check calender it is giving error message " Data is incomplete".
In general setting Tab I have maintained the Minimum Period as 999
I have checked the setting in SCAL .
Help will be rewarded
Regards
Dhananjay

Hi
Planning calender does not look for SCAL .
you might not have completed the settings in MD26.
Go to Help file & try to correct the settings.
Regards
YMREDDY

Similar Messages

  • PLANNING CALENDER IN LOT SIZE

    Hi
    What is the function of Planning Calender in Lot Sizing procedure in SNP.

    Hi
    You can define the planning calendar to define the periodicity of lot size.
    For example in our case we want to SNP to create requirement only in alternate month based on lot size.
    So we create planning calendar which consist only alternate month and attach to lot size.
    Now when we execute the SNP planning, it will create supply element only in alternate month.
    I hope this will give insight of it. Please let us know , if it helps you.
    Thanks
    Amol

  • Use of Planning Calender in MRP Area

    Hi ,
    Can any body tell me the possible way to use Planning Calender in MRP Area for Vendor direct Orders
    Thanks & Regards,
    Nirmalya

    Hi
    i have tried above link ..........But still not able to get the desired results.
    Need your help on this.
    Thanks,
    Nirmalya

  • Linking of planning calender to vendor master record

    Hi All,
    Could you please let me know how I can determine a particular date of a week as the delivery date (Monday to Friday) by  the vendor and plant combination.
    That means
    A purchase order created on 30 September for material X plant YYYY and vendor V1 has a receipt date of Friday 10 October.
    As the fixed receipt date is Thursday, the actual delivery should occur on Thursday 16 October.
    This receipt date based on fixed weekday must be the one computed by MRP calculation and appears on MD04 stock requirement list as actual receipt date.
    (I have got how to make it for the plant, that is by giving the Planning cycle in the MRP2 view and for that we have to select time phased planning that is R1 in MRP type field in the MRP1 view.) I have also seen in the vendor master alternative data for a particular plant I can give the Delivery cycle and planning cycle but they don't determine according to vendor plant combination when I do MRP run in MD03 and see the PR s created.
    Please let me if you need further explanation
    Brownie points are waiting for helpful answers!!!!!!!!!

    Hi Kishore,
    Thanks for the suggestion, but I have one question in my mind. If we have to determine the delivery date according to a particular vendor then we are maintaining the planning calender and delivery calender in  the vendor sub range,and we are also maintaing the vendor in the source list for that plant and material and making the vendor as MRP relevant, then
    Is there any need to give planning cycle in the MM record,as now we are not utilizing the material master record planning calender, instead of that we are using vendor subrange planning cycle and delivery cycle.( I tried to run MD03,after removing the planning calender in the MM record and I got the error "Error determining planning periods for calender")
    More over what is the difference between the planning cycle field and delivery cycle field in the VM record?
    Please let me know as  this is a requirement from the client which we need to map ?
    I am using MRP type PD and lot sizing as PK(period lot size for planning calender)
    Regards,
    Sushanta

  • The delivery date for the PR needs to consider planning Calender Periods

    Hi Friends,
    Please help me in solving in my scenario given below:
    The Planning calender periods are from Monday through Thursday(No Friday and weekends). When there is a Purchase Requisition (PR) planned date on Monday and the GR processing time is one day. The delivery date should be on the before Thursday (Becasue there is no period on Friday).
    But, the delivery date is being created with the before Friday, which shouldn't happen.(Requirement is that Delivery date shouldn't consider that friday, hence, the delivery date needs to be on Thursday).
    NOTE: The lot size settings are Lot sizing Procedure : P(Period lot sizing procedure), Lot-size indicator: K (Period lot size as in Planning Calender), Scheduling : 1 (Period Start = Delivery date).
    Thanks for helping me in advance,
    Surendra Chakka

    Hi Santosh,
    Thanks for your Questions. Below are the explainations:
    1. Can you expalin how your system is behaving at the moment?
    A. Presently the GR Processing time is 1 day for a material in Plant. So, if the user wants to produce on Wednesday (Planned date in PR, provided by the MRP run), then the delivery should be on Tuesday (Because GR processing time is 1 day). In  the same way, he dont wants the delivery to be on Friday. I mean, if he wants to produce on Monday,  he wants the delivery to be on Thursday.
    Only Friday, he don't wants to make the Delivery.(The delivery date should not show Friday in PR's).
    2. Pls explain your original MRP view and planning calendor setting...
    A. For solving of the above issue, we changed the Lot size to copy of "PK" - Period lot size acc to planniong calendar. Then we maintained the Planning calendar, in which the periods are for every Monday, tuesday, wednesday and thursday. Expecting, the delivery  should be excluded for friday, the friday in the planning calendar is not given as a period.
    The scheduling paramter in the Lotsize is tried with both the options (period start = Deliery date and period end = Delivery date).
    Later removed "PD" in MRP type and tried with "R1" Time phase req. But, the precondition for this is to maintain "Forecast req". This is also done. But, then, the system for this material is not responding to the MRP run. It is asking to run the forecast model. We ar not using SOP.
    3. The results thst you get with current setting?
    A. For the planned date in PR of Monday, the delivery date in PR is on the day before monday. i.e., Friday (Saturday and sundays are holidays).
    4. Expected results...?
    A. For the planned date in PR of Monday, the delivery date in PR should be Thursday (the day before monday production).
    Hope, i am clear in my explaination. Please revert back, if you need any more information.
    Thanks and Regards
    Surendra Chakka

  • Planning calender for BTO

    Hi,
    While using Planning calender, it works for TAN related orders,.i.e Delivery dates are determined correctly in PR/PO.
    But when we use TAB related orders planning calender does not work, delivery dates are not determined correctly.
    Is there any config/ master data change so as to include BTO also?
    Regards,
    Vengat

    HI
    You can check History of PIR through MD62 itself.Select particular row, Goto Menu, Select Item History(Shift +F6).
    Or
    You may pls execute transaction MD73.
    Plz select option "3 :History Planned ind reqmnts " in the display options and execute the report.
    Regards
    Anupam Sharma

  • Use of Planning Calender

    Hi gurus,
    I want to understand the use of Planning Calender. I want to know what will happen if i use the Counter as 2 and give the day as Monday. Please give me an example so that i can understand the use of Planning Calender. And also on the Procurement Proposals getting created based on Planning calender.
    Regards
    brijesh

    Hi,.
         Planning calendar (MARC-MRPPP) in combination with lot size PK works in MRP calculation date, but not in ATP.
    Example: today is 1/15/09 (Thur), my calendar is configured to have deliveries on Tues, Planned delivery time is 6, GR time is 1. MRP will calculate the following date:
    1/15 + 6 = 1/21 (Wed). It would then increase the date to the next Tues (1/27)
    1/27 + 1 = 1/28 - this is the result for the requisition date.
    If I enter a sales order (ATP check to use RLT) and there is not available inventory, I get confirmed date 1/22! The system takes today 1/15 + 6 + 1 = 1/22. But this is 6 days before MRP can confirm it!
    Menu path: Production -> MRP -> Master Data -> Planning Calendar (MD25)
    You will then need to use this planning calendar (the one you created) in the material master when planning your raw materials (MRP2 View in 4.6C - Field name : Planning Calendar).
    1. When you maintain the planning calendar you will need to enter a valid from date and valid to date.
    2. Your periods will also need to be set up and they will be weekly, for example:
        From Date : 11/23/2009   To Date : 11/29/2009   (11/23 is a Monday, this is your from date).
        Do this for as may weeks as you wish (say weekly for 2 years).
    3. When you have set up the planning calendar, you will then need to make some changes to the weekly lot size configuration
        (WB), or you may need to create a new lot size key if you do not want to change 'WB'. Essentially, you will need to use the
        following in the lot size configuration (OMI4) :
        No. of Periods : 1
        LotSizeProced.: P
        LotSize ind : K
        Scheduling : 1

  • Planning calender: Delivery 2 times per per week

    Hello,
    we got an arrangement with one of our vendors. When we order on Monday, Tuesday they will deliver on Friday the same week. Wenn we order on Wednesday, Thursday and Friday the will deliver on the next Tuesday.
    I tried to solve this by using a planning calender for Tuesday and Friday. The calender works fine. But please see the following table and the problem. You can see that i can not reach the expected delivery days exactly.
    Order                                                   Monday   Tuesday   Wednesday   Thursday   Friday
    expected delivery day                          Friday      Friday       Tuesday        Tuesday    Tuesday
    Delivery with 1 day delivery time         Friday      Friday       Tuesday        Tuesday    next Friday
    Delivery with 0 days delivery time       Friday      Friday       Friday            Tuesday    Tuesday
    Anybody an idea to reach the expected delivery days?
    One solution could be to change automatically via batch the planned delivery time, two times a week.
    Thanks for your response.
    Johannes Schulte

    Hello Antony,
    i do not now how this should solve my problem. Can you please add more information?
    I add some periods from my planning calender. There are two types of periods:
    1: start at Tuesday and end at Thursday
    2: start at friday and end at Monday
    09.02.2010     11.02.2010     12     2010     0
    12.02.2010     15.02.2010     13     2010     0
    16.02.2010     18.02.2010     14     2010     0
    19.02.2010     22.02.2010     15     2010     0
    23.02.2010     25.02.2010     16     2010     0
    26.02.2010     01.03.2010     17     2010     0
    02.03.2010     04.03.2010     18     2010     0
    05.03.2010     08.03.2010     19     2010     0
    09.03.2010     11.03.2010     20     2010     0
    12.03.2010     15.03.2010     21     2010     0
    16.03.2010     18.03.2010     22     2010     0
    19.03.2010     22.03.2010     23     2010     0
    Regards
    Johannes

  • Planning calender

    Hello all
    I want to receipt a material every tuesday,so i use MD25 to setup a planning calender,also use lot-size PK and select the calender
    i just setup.
    But when i use md03 and md04 to display the result of MRP run,it cannot follow my planning.
    Why?can anyboby gave me some advice?
    Thanks a lot

    Hi Vikas,
    You are creating planning calendar which works only to create MRP lot size during MRP. It is nothing to do with factory calendar.
    If you want to have diffrent calendar for production then create the second one from SCAL for 5 days and assign this to work centers in capacity tabs. Then this calendar will be taken for capacity planning only..not during the MRP. MRP will take the 6 days celandar during planning which is asigned to plant by MM.
    If any clarifications then revert.
    BR,
    TAJUDDIN

  • Sybase - dba planning calender backup scheduling hangs....basis 740

    Dear All,
    We are using ERP6 EHP7 on sybase and we are facing an issue for scheduling a daily backup.
    When I am trying to schedule a backup via "schedule an action" from dba_cockpit its getting hanged. And it has taken now more than 1 hr.
    Even I have implemented the dba_cockpit correction note for 740...but nothing works.. 001882376
    is there any one who can help me on this..??
    Regards,
    Letz..

    Hi Deepak,
    Thanks 4 the quick reply when i am clicking on DBA Planning Calender and after selecting the job when i clicked on Action Details it is showing only this as per screen below
    Is there any further option apart from this...
    Please Excuse me for the silly question as i am new in SAP Basis...
    Thanks & Regards,
    Prasad Deshpande

  • Table for Planning Calender

    Hi Gurus,
    Can someone pls tell me table for Planning Calender.
    Regards

    HI
    Check Table T439G PPplanning periods: header table.
    Regards
    Anupam Sharma

  • Planning Calender Assignment to Plant

    hello experts
    wee have maintained 7 planning calender to plant 0020, the same client wants to maintain to the plant 0010,
    pleazse let me know the procedure and implications and impact of this assinment .
    please suggest me earliest.

    7 planning calenders maintained earlier, its not by me, now, customer is asking me to maintain same 7 calenders to plant 0010,
    screen shot attached for ref, dta from table T439g
    0020 ES1 1 - 999 04.01.2006 29.12.2020 19.10.2006
    0020 ES2 1 - 999 02.01.2006 30.12.2020 19.10.2006
    0020 ES3 1 - 999 28.03.2007 23.12.2020 26.03.2007
    0020 ES4 1 - 999 04.01.2010 20.08.2020 10.09.2010
    0020 ES5 6 V 999 18.09.2006 30.12.2020 19.10.2006
    0020 QP1 1 + 900 04.01.2010 17.05.2020 03.11.2010
    0020 QP2 1 + 900 04.01.2010 21.05.2020 03.11.2010

  • Planning Cycle / planning calender

    Hi,
    I am trying to maintain a new planning Cycle / planning calender in Article Master : Logistic Store view under replenishment.
    Can you tell me how to create a new planning cycle. I want to replenishment to happen twice a week on Monday and wednesday.
    Thanks

    Hi Barry,
    Would help if you could share how you mange to do it with the rest of us.
    many thanks

  • Help on Planning Calender and lot size procedure settings

    Hi Gurus,
    We have 2 different schedule at the moment for our PO Placing to our supplier :
    1. Planning Calendar D01 --> For Seafreight shipment, PO Placing on bi-weekly basis, every Monday and RDD (Request Delivery Date) is on Thursday (11 days after PO Placing)
    2. Planning Calendar D02 --> For Airfreight shipment, PO Placing on weekly basis, every Friday and RDD (Request Delivery Date) is on Wednesday (5 days after PO Placing)
    Now we have required to change the SEAFREIGHT process by having the PO Placing on weekly basis, every Monday and RDD (Request Delivery Date) is on Wednesday (9 days after PO Placing).
    Please let me know the step by step procedure to create a new Planning Calendar and Lot Size Procedure to accomodate this requirement?
    Thanks for your help.
    Regards
    Brijesh

    Dear Brijesh:
    1. I think you are planning to change the Planning calendare D01.
    2. For this go to MD26- GIVE THE plant / palnning calendar id.
    3. Then in the CAlc rule for spec peroid - change the day from wednesday to Monday.
    4. SAve this and generate periods.
    5. Now in the maeterial master- check if you have the lot size as PK and also planning calendar as d01.
    6. In the planned dleiveyr times you enter 9 days.
    Kindly check this and revert back.
    Reg
    Dsk

  • SOP flexible planning calender

    Hi Experts,
    Plz light on the issue, we are going with SOP flexible planning -
    client want planning result for only 6 days/week but we maintained calendar for work center for 7 days,
    How assign 6 days calendar for only for SOP planning purpose,
    Thanks in advance
    Mohan M

    Dear,
    You can define the Factory Calender  for Info structure in  Tcode: MC7F asign 6 days work calender here.
    Regards,
    R.Brahmankar

Maybe you are looking for