Planning Collaboration with Partners (diffenrent product/location numbers)
Hi,
We have a requirement to support the supply planning collaboration.
We are going to use transaction /SAPAPO/CLP_PBPUSH for sending LC data from a plbook and for a given selection from our client to some affiliates and also transaction to pull data from affiliates to client.
We know it is possible using these transaction to make a mapping between key figures or characteristic names but our problem is that sending and receiving systems have different numbers/codes for the same material and location, that is, in the sending system prodA number is P1A but in the receiving system this product number is Q1A, and the same goes for locations. (In our client master data we have the number for the material and the location in the affiliates in the free attributes)
Does anyone know how could we overcome this issue? We would need to map material/location combinations between sending/receiving systems. We have been looking for some badi or user exit to change this but as of now we have not come across anything useful.
By the way, the exchange would be done between SAP APO systems.
Thanks a lot for reading!
The only BADI that may be of use is /SAPAPO/CLP_SDP01 which allows you to change values of the characteristics.
May be worth looking into that.
Regards
Ian
Similar Messages
-
Costing affect with MRP at planned order level and after production order
Dear all,
How the costing affect with MRP at planned order level and after production order completion?
Edited by: Maulik on Jun 24, 2009 1:59 PMDear Maulik,
check Mr. Vinod's inputs abt costing
1. Maintain following master data:
MM01 Material Master with Costing and accounting view. Make sure all the cost Std, Moving avg etc is maintained along with valuation class in Accounting view 1. In costing tab pls make sure "with qty structure" and "Material Origin" are ticked.
CS01 BOM with components marked with costing relevance in Status/Long Text Tab. Also check all the qty are correct.
CR01 Work Center in Basic data tab maintain standard value key sau SAP1 and in costing tab maintain the workcenter, activity type and formulas (Usually standard formulas like for Machine Hours SAP006, Labour SAP007, Setup Activity SAP005 is used).
KL01 Cretae activity types, in basic data tab maintain ATyp Category AS "1" and cost element (as provided by your FI Guy).
KP26 Activity pricing, here with the combination of Activity type and the cost center you assign price to the activity.
2. SPRO Activity
Maintain Costing sheet IMGControllingProd cost controllingProd Cost PlanningBasic settingoverheadsdefine costing sheet.
OKKN Define costing variant, you define costing type (In the costing type, you define the purpose of a material cost estimate by specifying, for example, which field in the material master record the costing results can be transferred to like std price, moving avg etc), Valuation Variant (defines how the prices are prioratized), date control and transfer structure.
3. Costing Process Flow:
1. CK11N CREATE COSTING RUN
2. CK24 CREATE PRICE UPDATE (You Mark and release the prce to be updated)
4. COSTING VARIANT WRT PP
1. OPL1 DEFINE COSTING VARIANT WRT PP
2. OKK4 or OPN2 DEFINE VALUATION VARIANT
3. OKK1 or OPM1 DEFINE COSTING TYPE
4. OPL8 ORDERTYPE DEPENDENT PARAMETER (assign the above creted costing type for both planned and actual)
Hope this will throw some light on product costing.
Regards
kumar -
T510 - No label with product key numbers for Windows 7
I just noticed that my T510 does not have the Product key numbers for the installed OS (Windows 7 64-bit), which I find quite strange. My previous three T machines, both from IBM and Lenovo, all have those labels n the back.
What is going on and what are the possible implications?
Thanks for any enlightenment on this issue.
Lin Yu
Solved!
Go to Solution.Hello mate,
Remove the battery it's under it.
Knowledge is of two kinds. We know a subject ourselves, or we know where we can find information on it.
ThinkPad T510 4313-CTO Windows 8 x64 - Intel Core i7-620M - NVIDIA NVS 3100M - 8GB RAM - 240GB SSD- Intel Centrino Ultimate-N 6300 - Gobi 2000.
ThinkPad Helix 3697-CTO Windows 8.1 x64 - Intel Core i7-3667U - Intel HD Graphics 4000 - 8GB RAM- 256GB SSD - Intel Centrino Advanced-N 6205 - Ericsson C5621gw -
Planning with diff. Production versions
Dear all,
i am using make to order strategy and scenari is that there are three versions of a fert. when sale order is generated and i run MRP how can i have three plan orders with 60:30:10 ratio. i mean if sale order is of 100 units then i want to plan 60 units by version A ,30 units by version B and 10 unitsShoaib ,
It will not work with sales order, but it work fine with MTS.
with sales order it will take whole quantity of all the orders and divide it into the quota.
check my reply in the below thread and the findings of the Jawad.
Re: Quota Arrangement in Make to order Environment
Hope it will help you.
regards
Ritesh -
APO Constrained and unconstrained Forecast for a Product, Location
Hi Gurus,
Please let me know the simple ways to get the constrained and unconstrained forecast for a product / location. I am new to APO, so please help me to send the detailed information. I would really appreciate it.
Thanks in advance for your wonderful help.
Best regards
NagarajanNagarjan,
When you run the fortecast in DP you consider the sales history. Now, this sales history is actual sales. While forecasting all that is considered are these values of the past and not the present and future capability to actually meet this forecast. Its just plain statistically generated numbers. Now suppose based on your sales you generate the following forecastL
Jan 1000
Feb 1000
Mar 1500
This is then released to SNP. Use the TX /sapapo/mc90. The idea is now to EVALUATE THIS FORECAST AGAINST OUR CAPABILITY TO SUPPLY, IN OTEHR WORDS CONTRAINTS!
After releasing to SNP you can do a finite planning taking into consideration constraints such as Capacity, vendor capabilities, procurement constraints etc... Its almost always the case that the exact numbers cannot be met and thats whgy we do all the replanninga and levelling and rescheduling etc etc...
In SNP you can run an unconstrained pla., You can then level this using SNP capacity levelling. Remmeber this process may span certain levels like DC- > FG Plant -> SFG Plant etc...
After considering supply capcbilities you can come up with a REVISED forecast:
Jan: 800
Feb: 1000
Mar: 1600
Note that for March you are able to take an increased volume. You can now release this plan to DP back again to tell it that this is the demand I can meet and this is what should be planned. This can be done using Tx /SAPAPO/SNPFCST or /SAPAPO/LCOUT
Hope this clarifies.
Abhi -
Supplier collaboration with SNC
Hi Gurus,
We intend to use Supplier collaboration with SNC, where plant will share component plan with supplier and supplier will comeback with constrained component plan and based on which plant will modify production plan.
These are the steps we have done:-
1) Created BP as Organization for Plant and Supplier
2) Created BP as person and assigned to plant and supplier respectively
3) Extended product to the supplier and created TLane
4) We are able to login into web portal for supplier view with login and password maintained.
issue are:-
1) We understand that, component forecast will come from APO and it will come to as demand. If we see Demand Tab and look at Order Forecast Monitor - > Order forecast details, it asks for selection of SKU and Location. If we select our SKU and vendor Location created, it says Invalid Selection......Not sure if we have missed anything.
2) When vendor will confirm the plan, which key figure he will modify?? which Tab we have to refer.
Any help will be appreciated.
thanks,
jaideepHi Gurus,
Yes, the OSS helps and we are able to see product location in the Order Forecast details screen.
We are checking Key figure " Supplier Planned Receipt" which supplier will use to modify his plan against customer requirement.
Wondering this key figure is Non Editable for our case....then how supplier will enter his constraint plan?? Any help
Are we missing any customization to make key figures editable/non editable like Planning Book in standard APO?? plz help -
I am feeling so ripped off right now. I have wanted a Mac for years and believed the hype about it's stability and I have had more trouble with this Imac 2011 than I have ever had with a pc. It locks up with several software products from APP store. I have already had to have a technician to look at it and really couldn't figure out what the deal was. I was told that the APP store software should give me no problems but the truth is that it locks up on the software. This machine is only 4 weeks old and I am using 37 g on a 1 T hard drive. There is no reason for it to be locking up. Also, when I try to use the help program, it always tells me that I am not connected to the internet even though I have used both the mail program and the browser with no problem just before that. I successfully used the help program on my pc lots of times. I did not need a $2000. plus machine to just get email. I just wanted to unload on somebody that might understand my pain and after checking out this site...I think there is a few of you out there.
I was told that the APP store software should give me no problems but the truth is that it locks up on the software.
The apps downloaded from the Mac App Store are written by third party developers, not Apple. If you have problems with those apps you need to visit the support area for their websites. Launch the App Store, locate the app name. You should see a support link.
when I try to use the help program, it always tells me that I am not connected to the internet even though I have used both the mail program and the browser with no problem just before that
Go to ~/Library/Preferences. Move the com.apple.helpviewer.plist file from the Preferences folder to the Trash. Restart your Mac, try the Help menu.
If you need help finding that file, hold down the Finder icon in the Dock then click: New Finder Window. From the menu bar top of your screen click: Go > Go to Folder. Type this in exactly as you see it here: ~/Library/Preferences/com.apple.helpviewer.plist That will take you right to that file.
(.plist) files stores information about a particular app or in this case, the Help viewer. Often times deleting the .plist file resolves the issue.
It's fine to "unload"... we understand that you expect your iMac to be stable but there are times when things go awry. That's why we have these forums so that you can you get help.
You may want to read up on how to repair the disk if necessary or reintsall Lion > OS X Lion: About Lion Recovery
Apple - Find Out How - Mac Basics
How to "switch" from PC to Mac > Apple - Support - Switch 101
I'm sorry you feel, "ripped off", but you are using the world's most advanced operating system and it may take some time to adjust to a new OS. http://developer.apple.com/technologies/mac/ -
Supplier collaboration with contract management
Hi All,
is there any functionality available in SRM to allow collaboration with suppliers for the contract management functionality within SRM?
I thinking of any possible integration via SUS?
Cheers
ChrisHello Chris,
Use of cFolders can be one of the option, which version you are working on.
SRM supports integration with SAP Product Lifecycle Management (PLM) cFolders 2.0 or higher. Once SAP PLM cFolders has been installed, purchasers can create a folder there to store information and share it with potential suppliers.
http://help.sap.com/saphelp_srm2007/helpdata/en/74/344c430fab4d0bbc30996d56cc293a/frameset.htm
Hope this might be helpful.
Thanks
Ashutosh -
How to CIF product locations for many parts from R/3 to SCM SPP
We are trying to CIF product locations of 2500 parts. We are able to take only 10 parts
in one transfer. Can anyone help us with this. How do we transfer all these parts in a single attempt.Thanks for your answer.
In the product selection screen in CFM1, there are limited no of rows that can be copied in one go. The next set of rows have to be added by scrolling down.This becomes very manual if we have to do it for 2500 parts.
Can u suggest a better way of doing this activity? -
Where/ how do I set SNP to create Planned orders with multiple line items?
Hi
Currently our SNP is generating planned orders on a daily basis, it creates a single order with a single line item per location.
Where/ how do set SNP to create planned orders on a daily basis to generate a single order with multiple line items per location, so therefore one planned order with multiple line items for a single location.
Thanx
KeeganHi Keegan,
In SNP (APO) it is not possible to create order with multiple line items.
But you can do some settings so that while planning system can do aggregation and disaggregation.
But your requirment should be set on Aggregation/Dis-aggregation logic.
Please follow the follwing links:
http://help.sap.com/saphelp_scm2007/helpdata/en/2c/c557e9e330cc46b8e440fb3999ca51/content.htm
Aggregation:
http://help.sap.com/saphelp_scm2007/helpdata/en/42/f731d078e73ee4e10000000a1553f6/content.htm
Disaggregation:
http://help.sap.com/saphelp_scm2007/helpdata/en/a6/ebefaf32e22e468355da304cc59387/content.htm
Please be sure that the setting of this logic will be at planning area level.
You can't change aggregation/disaggregation logic further.
Regards,
Santosh -
I have product key numbers for my PS and Premier Elements 12
I have product key numbers for my PS and Premier Elements 12.
I installed on one computer 8 months ago.
I now want to initiate my 2nd download onto another computer.
I cannot locate the appropriate download instructions.
Any help out there?
Thanks,
EllisDownload and Installation Help -
https://helpx.adobe.com/download-install.html
http://www.adobe.com/cfusion/tdrc/index.cfm?product=photoshop_elements
Adobe - Download free trial version Adobe Premiere Elements 12 | Adobe -
JSP tag collaboration with BI Beans
Hello!
We need to reorganize a dimension hierarchy in runtime during presentation. It's merely a matter of formatting. We use a tag handler that reeds its body doing some operations and puts a new content for body in page.
We tried this
====================
<My:BodyReaderTag>
<orabi:ListCombo renderAs="combo" autoSubmit="true" biList="${tagtest_dimMemList1_data}"/>
</My:BodyReaderTag>
====================
When doing this my tag grabs all content except the output from orabi:ListCombo. It seems like orabi:ListCombo does not push the JspWriter on the stack (by collaboration with orabi:BIBody tag). When, for testing purposes only, I removed the orabi:BIBody tag, I got the result I would like to get.
How can I get the output from orabi:ListCombo tag? Or if that is not possible, where can I find detailed information so I can create my own customized tag handlers that collaborates with BI Beans,
Thanks in advance,
MatsThe implementation of the <orabi:ListCombo> is based on UIX JSP tags technology. It uses an instance of oracle.cabo.ui.RenderingContext created earlier by the BIThinSession tag to do the actually rendering.
May I ask what are you trying to do with the <my:reformatter> tag? The ListCombo tag has attributes like "styleClass" and "inlineStyle" that can be used customize the look and feel of the content it renders. Also, we provide a set of built-in styles. Have you looked into whether you can use "styleClass" or "inlineStyle" attributes to satisfy your formatting needs?
Hope this helps,
Keith
Oracle Business Intelligence Product Management
BI on Oracle: http://www.oracle.com/bi/
BI on OTN: http://www.oracle.com/technology/products/bi/
BI Beans http://www.oracle.com/technology/products/bib/index.html
Discoverer: http://www.oracle.com/technology/products/discoverer/
BI Software: http://www.oracle.com/technology/software/products/ias/devuse.html
Documentation: http://www.oracle.com/technology/documentation/appserver1012.html
BI Samples: http://www.oracle.com/technology/products/bi/samples/
Blog: http://oraclebi.blogspot.com/ -
My Adobe - all my previously registered product serial numbers are missing!
I logged in to my adobe today using the same account I have used for years.
I found that all my registered product serial numbers are missing.
On previous log ins this list correctly showed all my adobe purchases.
There must be about a decade's worth of purchased serial number now
missing from this list.
I had logged in to check my cs5.5 serial number in order to purchase a
creative cloud subscription.
However, finding all my details missing has put me off buying more products.
Is the wiping of the data a temporary database problem at your end?
or will this permanently affect my ability to upgrade products and services?Palaab wrote:
…I contacted customer support and he asked for my serial number and then told me he can't help with this issue and I need to look in these forums for a solution…
Most irresponsible, ignorant and unprofessional of that nincompoop who sent you to the forums for a customer service issue.
Unfortunately, only Adobe customer service can assist you with your issue. These are user forums; you are not addressing Adobe here. There's no one here who can help you.
Click on the link below, and after that click on "Still need Help? Contact us."
Then on the next page, click Chat
There is also a phone option.
http://helpx.adobe.com/contact.html?step=PHXS_downloading-installing-setting-up_licensing- activation -
Hi All,
I am running product Location consistency in OM17. In the results I got few inconsistencies. In the result system does not give product/location name instead it gives pegging area ID. for E.g. "IVLIV57s0h}X0800Av4pk0". I would like to know how can I find for which product/location there is inconsistency from pegging area? Is there any table where this relationship is maintained?
Regards,
Harshil DesaiThanks a lot every one for all your help but I am not able to get details for pegging area that I am getting in OM17.
I tried in /sapapo/pegkey
/sapapo/ac05
/sapapo/om16 but no entries found.
OM17 results giving details,
for E.g.
Planning Version:000
Message Text: Entry only in Live Cache
Pegging Area: IVX0r0q30VNX0800Av4pTG
Return Code: 0
Regards,
Harshil Desai -
Goods reciept with HU # from Production
Hello all,
I would like to know the steps/procedure involved in doing a goods recipt of a finished material with HU# after production in to a HU managed storage location.
pl. let me know the steps and is there any possibility of printing HU labels when the material is goods receipted from production.
Thanks,
MaxxHI,
Follow these steps :
Create packing instruction : POP1
Create Packing determination records : POF1
Now you need to generate HU in against production order : COWBPACK.
It will automatically generate HU with respect to the packing instruction u created.
Now do GR through COWBHUWE
REgards,
Vishal
Maybe you are looking for
-
In the report S_ALR_87012178, Customer name needed
Hi Friends, In the report Customer Balance of Overdue Items (S_ALR_87012178), full address of the customer is not necessary. Instead we need only the Name of the customer to be displayed in the report Suggestions are rewarded with points Regards Jyos
-
Problems with the Controller in WebDynpro
Hello, I have a question: I am trying to do create files to my project in WebDynpro and it gives errors me, one of the so many errors that leave to me is: wdContext cannot be resolved, this to that it must? Another one is: IPrivateComponent cannot be
-
Fault Module Name: QuickTime.qts Fault Module Version: 7.72.80.56 Fault Module Timestamp: 4f8f8aa7
-
What's best: placing images in Photoshop or InDesign?
Hi guys Since I hear different things about creating for example posters etc. is this my question: What do you think is best to do when designing a poster or flyer (or whatever) with a nice background, bursh effects, pictures and text? I do it like t
-
"Fails to initialize" on Mac 10.7.4
Downloaded Configurator 3 today from labs, tried to install, but get a message that it failed to initialize. Suggests I download Support Advisor, which I did, and that reports nothing wrong. I have Air installed, using it fine with related applicati