Planning dependent and independent requirements in DP

Hi,
      We have a material A here that has a BOM defined. The components of the BOM are all dependent on the initial material. There are some cases where theBOM is recursive, meaning that the components of BOM could include material A. Now, I also have some more components that are infact independent of this material but are necessary for material A but it's dynamic. How do I plan this scenario in DP?
I think DP-BOM does the dependent requirements planning for the material A.
How do I plan for the dynamic components? I have some history on how they are generally consumed. So, should I plan them separately, I mean the material A along with the dependent components and the independent dynamic no. components? But the problem, I am guessing, comes up when we forecast more of the independent components and plan fewer for this month....Can somebody suggest me something?
I think I am correct in going for DP-BOM instead of CBF as I donot have variants involved here.  Please correct me if I am wrong, we use DP-BOM when we need to plan on simple BOMs (no variants, multiple BOMs etc.) and use CBF in case we need to deal with variants involving characteristics.
Any suggestions are highly appreciated.
Thanks.
Message was edited by:
        Visu Venkat

the realignment will depend on the realignment table. So if you devise a way to keep that as dynamic as your changes in the components you should be able to do that
there are quite a few ways you can achieve your means... the realignment thought occured because i was posting another answer on it
am sure there will be other issues we havent foreseen that might arise when you actually try it
here is another alternate you might want to try.... just some more vague thought....
if you are on SCM 5 (if you are on another version there are other ways of doing this)
1. create CV Cs based on a worklist that lists the dynamic components ... (you can automate this if you want - as long as there is a reference spreadsheet)
2. Create a selection profile that has the Main component and the dynamic components (lets assume there are 3 components and this will be a 1:1 ratio with the main productA)... now the total of the forecast for this selection profile will be say 100
2. Run a macro that will multiply the forecast with the number of products in it (so 100*4) . this will make the forecast 400
3. If you have set a disaggregation on the forecast KF that is equal distribution (this may not be the case in your business scenario) you will get 100 on each of the selections
am sure there are a lot of holes in this that can be plugged or variations worked on...  depends what works easier for you...and the amount of maintainance and data involved ... it will all boil down to the business process

Similar Messages

  • Dependent and Independent Requirements

    Hi Gurus,
    Please tell the table and field name for Dependent & Independent requirements.
    Regards,
    Senthil.K

    Hi,
    Thanks
    I fouond the logic for Independent requirements.But I can't get the Dependent Requirements.In Table PKSL very less fields only available.Please give the logic.
    Regards,
    Senthil.

  • Activity Dependant and Independant Cost in real time scenarios

    Hi SAP Gurus,
    I know what is activity Dependant and independant costs.  But i would like to know in the realtime scenario what are the costs that would be treated as activity dependant costs and how thay will be handled.
    You answer would be suitably rewarded with points
    Thanks in advnace

    Hi
    In real time based on client practices, the cost/activity plan will be based on activity dependant cost.
    ex: There is Quality control department and it carries out testing of the products.
    now, to get plan/budgeted cost/activity, we can choose the requied cost elements to be planned for the period.
    like:
    the cost elements are
    QC cost elements
    Salararies & Benefits
    Indirect Materials
    Indirect Expeneses
    and fixed expenses
    for above cost elements we do cost/activity dependant plan and calculate the cost per i hour of testing based on parameters.
    Regards
    Laxmiprasad

  • Differentiating Between Dependent and Independent Data

    HI,
    How can I make a differentiation between dependent and independent data?

    HI,
    If you double click a Transfer requirement in SE10 or SE09 and then press F4 in the field category, you will find some helpful information.
    Client dependent or independent transfer requirements include client specific or cross client objects in the change requests. Workbench objects like SAPscripts are client specific, some entries in customizing are client independent.
    If you display the object list for one change request, and then for each object the object attributes, you will find the flag client specific.
    If one object in the task list has this flag on, then that transport will be client dependent.
    You can also find a list of the high class objects in SAP, here you will see the flag on/off. Use TCODE SOBJ.
    Start STMS and double click on the request itself, you will see which type of request it is (Workbench -> client independent or Customizing -> client dependent).
    I recommend you to import every request on each client without looking inside the request.
    Reward Points if found helpfull..
    Cheers,
    Chandra Sekhar.

  • List of client dependant and independent

    Hi All,
    Can any one let me knw the list of objects which are client dependent and which are not.
    Thanks,
    Vibha

    Hello Vibha
    The following list shows the client-dependent repository objects:
    LIMU     FSEL     Field Selection
    LIMU     VARI     Report Program System Variant
    R3TR     COC1     CO: Cost Centers
    R3TR     COC2     CO: Activity Types
    R3TR     FORM     SAPscript form
    R3TR     LODS     HRDSYS: Logical information object client-dep. table E SYST
    R3TR     PCYS     HR: Transport standard personnel calculation rules
    R3TR     PHDS     HRDSYS: physical information object client-dep. table E SYST
    R3TR     SBNL     Logical Information Object for BDS
    R3TR     SBNP     Logical Information Object for BDS
    R3TR     SBNR     BDS: Relationship Between Information Objects
    R3TR     SBPL     Logical Information Object for BDS: Bid Invitation
    R3TR     SBPP     Physical Information Object for BDS
    R3TR     SBPR     BDS: Relationship Between Information Objects
    R3TR     SBRL     Logical Information Object for BDS
    R3TR     SBRP     Physical Information Object
    R3TR     SBRR     BDS: Relationship Between Information Objects
    R3TR     SBSL     Logical Information Object for BDS
    R3TR     SBSP     Physical Information Object
    R3TR     SBSR     BDS: Relationship Between Information Objects
    R3TR     SBTL     Logical Information Object for BDS
    R3TR     SBTP     Physical Information Object
    R3TR     SBTR     BDS: Relationship Between Information Objects
    R3TR     SBWL     Logical information object for BDS
    R3TR     SBWP     Logical information object for BDS
    R3TR     SBWR     BDS: Relationship between information objects
    R3TR     SRHL     SRM: Hierarchical Lists
    R3TR     SRLD     Language-Dependent Client-Specific Retrieval Index Objekt
    R3TR     STYL     SAPscript Style
    In contrast to client-independent repository objects which can be imported into any client these objects must be transported into their specific target client.
    Regards
      Uwe

  • Multiple Dependent and Independent Samples

    Hi,
    Can anybody explain about Multiple Dependent Samples and Multiple Independent Samples with proper Examples?
    Regards,
    Raj

    dear Raj
    Multiple Dependant Samples,
    Suppose you have sampling scheme in which the lot size is 10, sample size is 5. acceptance number is 1 and rejection number 4.
    Now during RR you found that 2 values are ok and 3 values are not ok. So the system is in confusion because it requires 4 to reject. So system proposes you another sampling plan by which you can further do testing and record the results. The defects get cumulated and is then valuated. you can do this 7 times. For this you need to maintain c1,d1,c2,d2 ,c3,d3 for the same sample size
    Hope this helps
    Regards
    gajesh

  • Instance dependant and independent

    Hello
    I cannot access the method getDetail() in Purchase order BAPI. It shows an error [" GetDetail on type _Com Object not found "].But I can access the method getItems() in the same BAPI (Both are tried from VS .NET 2003 ). In SAP GUI I noticed that getDetail() is  instance dependendnt and getItems() is instance independent . Is this the reason for showing the error ? Can any one of you tell me the difference between Instance dependant BAPI method and Instance independent BAPI method. and how i can solve this issue
    Thanks in advance

    Hello
    I cannot access the method getDetail() in Purchase order BAPI. It shows an error [" GetDetail on type _Com Object not found "].But I can access the method getItems() in the same BAPI (Both are tried from VS .NET 2003 ). In SAP GUI I noticed that getDetail() is  instance dependendnt and getItems() is instance independent . Is this the reason for showing the error ? Can any one of you tell me the difference between Instance dependant BAPI method and Instance independent BAPI method. and how i can solve this issue
    Thanks in advance

  • Hi abapers doubt in client dependent  and independent

    i am having a doubt could you please explain me
    i created a dependent table using mandt in client 100(development).
    if transfered this  table to quality 110(quality). it is possible access data?
    when i see development 100 it's having data but i can't find any records in quality it's not showing the records.
    how we can see data in quality110 , if table is dependent.

    Hi Sayeed,
    Data in the table will only we transported accross a system landscape if you have marked the recording routine in your development system.
    Regards,
    John.

  • Independent requirement and dependent requirement

    Hi,
    Can anybody explain me what is dependent and independent requirement in PP?
    thanks

    Neha ,
    The function of <b>Demand Management</b> is to determine requirement quantities  Goods/products.<b>Customer requirements</b> are created in sales order management. To create a demand program, Demand Management uses <b>planned independent requirements</b> and <b>customer requirements</b>.
    To create the demand program, you must define the planning strategy for a product. Planning strategies represent the methods of production for planning and manufacturing or procuring a product. Using these strategies, you can decide if production is <b>make-to-order production(MTO</b>) triggered by sales order  or if it is not triggered by sales orders i.e make-to-stock production (MTS).
    Let me explain with one example.
    Finsished product "A" has BOM and BOM items are "B" & " C".
    There could be a demand for Product A from customer or from Planned independent requirement . planned independent requirements are maintained in the system (t code MD61). so when you run the MRP for a Finsihed product A it also creates the dependent requirement for items B & C ( B /C are dependents, for product A ). in turn the requirements for the items will be fulfilled by raising the purchase requisition , if procured externally or production order if it is in-house.
    hope this explanation is helpful.
    Thanks
    Kiran
    P.S  Pls award points if you find the answer is helpful.
    hope this

  • Urgent:Why Script is cliend dependant and smartform is not client dependant

    Hi all,
    Can any one pls tell me why script is client dependent and smartform is not client dependant.
    <b>Please give some real time examples in brief</b>
    regards
    tapu

    Hi
    DIFFERENCE BETWEEN SMARTFORMS AND SAPSCRIPTS ARE:
    1. script is client dependent one while smartform is client independent.
    2. In scripts we have to write print program while in smart forms it is not necessary.
    3. In scripts we can print background logo while in smartforms we cant print background logo
    4. In scripts we have 99 main windows while in smartforms we have only 1 main window.
    5. In scripts we should write paragraph format otherwise we cant execute program while in smartforms no need to create paragraph formats .
    6. In scripts we can print the text in only two character formats.
    while in smartforms we can do with more.
    7. In scripts we dont have line types while in smartforms we have linetypes.
    8.Multiple page formats are possible in smartforms which is not the case in SAPScripts
    9.It is possible to have a smartform without a main window .
    10.Labels cannot be created in smartforms.
    11.Routines can be written in smartforms tool.
    12.Smartforms generates a function module when activated.
    SAPscript technology is based on a mainframe product from the 1980s, while Smart Forms have only been around since (roughly) 2001. With that sort of time gap, there are bound to be significant differences between the two tools. Client dependence is a fundamental one. Although SAPscript has had some incremental improvements over time, its forms have always been -- under the hood -- relatively ...
    also refer
    difference between smartforms and scripts
    Diff betwen Scripts & smartforms
    advantages of smartforms over scripts
    Whenever a smartform is created, a funciton module gets generated. So, we can access the smartform in different clients. But in case of scripts, it is not so.. So, scripts are client dependent.
    Smart Forms are implemented using the Function Module SSF*, and all the logic lies in the FM. Function Modules are client independent objects, so Smart forms are also client independent
    SAP Scripts are the Layout Forms that you design and there are aviable in the client in which you have created them, for making them available you have to copy across the clients.
    Because, Sapscripts are saved in ITF format as text in client dependant tables STXH and STXL. smartforms are not saved in client dependant tables and visible across clients.
    SAPscript technology is based on a mainframe product from the 1980s, while Smart Forms have only been around since (roughly) 2001. With that sort of time gap, there are bound to be significant differences between the two tools. As you have noted correctly, client dependence is a fundamental one.
    Although SAPscript has had some incremental improvements over time, its forms have always been -- under the hood -- relatively passive objects, with minimal embedded logic. These forms were designed to be driven and controlled by ABAP programs, much in the way ABAP programs read in database tables to produce reports; if you ever download a SAPscript form (e.g., via utility program RSTXSCRP), and look at the portable text file it produces you'll see what I mean. Many text objects (e.g., invoice header texts) are bound directly to documents which are client-dependent, so it makes sense for these text objects to also be client-dependent. From a complexity standpoint, SAPscript forms are close enough to these text objects where I can see how it made sense at the time to make them client-dependent too.
    Conversely, a Smart Form is significantly more robust and complex. For instance, it can contain program nodes and nested tables with patterns. When a Smart Form is compiled, it generates an ABAP function module – and these are always client-independent. This is appropriate, given that this form has more in common with an ABAP program than its predecessor. For instance, when a print program calls a Smart Form, the form itself takes over to produce output, without any further direction from the print program. In fact, the join is so seamless that I often find myself using a Smart Form's Initialization section for logic to handle any data gathering not handled by the print program. I would never even think to attempt this with SAPscript.
    I suspect several factors figured into SAP's decision to make Smart Forms client-independent, including customer feedback. There are significant advantages to client-independence. For instance, a change made in one development client happens immediately across all development clients. Among other things, this means we don't have to waste time figuring which client contains the most recent version -- they all do! In addition, transporting Smart Forms is easier, since we can safely bundle them together in the same transport as their client-independent print programs (no worry about mixing client-dependent and independent objects).
    <b>Reward points for useful Answers</b>
    Regards
    Anji

  • Plant Dependent and Plant Independent Requirement.

    Hi,
    I want to know in details, meaning of "Plan dependent Requirement" and "Plan Independent Requirement".
    Rajesh

    Hi Rajesh,
    PIR(planned independent requirement)  is created for the parent(finished) material in tcode MD61
    Then in MD04 you can check the same
    Dependent requirement will automatically get created for the child materials(semi finished,raw) of the parent material for which PIR is created
    Hope the above is clear
    Regards,
    SVP

  • Idoc type and message type for Planned Independent Requirement (PIR)

    Hi
    Can anyone please give me the information on the idoc type and message type for Planned Independent Requirement(PIR)?
    And also the prerequisites to use them.
    Regards,
    Lohitha
    Moderator message: please do more research before asking, show what you have done yourself when asking.
    Edited by: Thomas Zloch on May 23, 2011 10:45 AM

    Hi,
    You can use IDoc type WMMBID02 with message type WMMBXY.
    Also please check test program RLMBXY00 to simulate IDoc WMMBID02.
    Regards,
    Ferry Lianto

  • Planned Independent Requirement Not getting displayed in MD04

    Hi,
       I am assigning material to nwa and doing advance procurement by using procurement type PIR. Reservation is getting created after release of activity but the same is not getting displayed in MD04.
    The items of the reservation are getting displayed in MB23.
    what could be the reason for this?
    Regards,
    B P Singh

    Hi,
    Planned Independent requirements (PI) are normally configured for consumption by 'Dependent' requirements. Hence the PIR would have been replaced by the reservation from 'dependent' requirement. You can test and verify the same in development system.
    Regards
    Murali

  • Planned Independent Requirements

    Can any body tell me what exactly Planned Independent Requirements means and how it differs means from dependent requirements?
    Thanks for your time
    Thanks Again,

    Hi,
    To produce a finish material, there should be some requirements. The requirements can be in form of forecast or order based. Order based requirements are triggered by sales order or customer requirements. The forecast can be done in any any system for a particular finished product in SAP or non SAP system. After carrying out the forecast, this can be entered into SAP as planned independent requirements. The term PIR is nothing but requirements which are triggered by planning and not by order.
    PIR comes into picture when you are using a MTS or related scenario.
    Hope this make it clear to you.
    Regards
    Vineet

  • Long-term planning: how can I reorganize "bulk" independent requirements ?

    Hello,
    Due to some circumstances I have dependent simulative requirements with no relation to any independent requirements.
    I thought that with ms01 (Processing key NEUPL -Regenerative planning and Planning mode 3 - Delete and recreate planning) those independent requirements will
    be deleted because the former independet requirements are no more existing.
    But they remain existing. (in mfs0)
    How can I reorganize "orphaned" independent requirements in long term planning.
    Thanks for any help
    Thomas

    Thanks a lot for answer.
    The subject of my original-question was
    wrong. It should say "dependent" requirements
    instead of "independent" requirements.
    I solved the problem by deleting the
    respective entries in MDSM-Table
    But anyway, the usage of md74/75 was a
    good recommandation, thanks very much.

Maybe you are looking for

  • Can't view .swf files in Dreamweaver

    I'm using CS3 versions of both Dreamweaver and Flash and when I import a .swf file into dreamweaver it works perfect locally but doesn't show at all when I've uploaded the file into my webspace. What am I doing wrong? I never had this problem when I

  • Wrong XML parsing in Java  6.0 , the same code works fine with Java 5.0

    I have the following xml data in a file ( C:\_rf\jrebug.xml ) : <?xml version="1.0" encoding="UTF-8"?> <rs>      <data           input3='aa[1]'           input4='bb[1]'           input6='cc[2]'           input8='dd[7]'           output2='ee[7]'      

  • Javac Error

    when running javac i get this error Error occurred during initialization of VM java/lang/NoClassDefFoundError: java/lang/Object to me that looks like my JDK or something to that nature did not startup cause i ran javac on a file i know worked i recen

  • What am I missing out on using color on 15" MBP (1400x900) monitor?

    Minimum recommended resolution: 1650x1050 Should I trade the 15" in for 17" model (Just bought it)? I'm a complete beginner and have never used color before. Basic answers are appreciated. This is not for "TV" production, just small shop jobs and hob

  • Custom tag library problem

    I created a workspace with two projects in it. In the first project I realized a tag library with its deployment descriptor. In the second project I realized a .war component with a jsp that uses the tag in the library. In the .war deployment descrip