How I can get the planning Good issue date? I found that the loading date is the same as the planned Good issue date, what's the loading time?
As what I understanding, loading date + loading time = Good issue date,  But I am not sure how to calculate the planned Good issue date.
thanks,

Hello Friend,
It is determined in Shipping Point configuration.The path is as follows SPRO--> Enterprise Structure >Definition>Logistics Execution-->Define, copy, delete, check shipping point and go in detail the concerned shipping point.

Similar Messages

  • New planned goods issue date during delivery creation due to changed route

    Hello All,
    I have defined 2 routes with different values for transit time and transporation lead times. I have configured routes such that in order creation - route A is determined and while delivery creation due to weight group - delivery B is determined.
    Now for Route A i have maintained transit time of 3 days and Transportation lead time of 4 days and for Route B it is 1 day each.
    Delivery scheduling is active for the order type.
    Now when i create the order with a delivery date of say 05/24/2010 then (route A with transit time of 3 days) is determined and the planned goods issue date of 05/21/2010 is in the order.
    Now while creating delivery (Route B which has transit time 1 day) is determined due to the weight group. But the planned goods issue date is still the same 05/21/2010 as in order.
    I am assuming that since the route B has a route of 1 day so the planned goods issue date should be re-determined to 05/23/2010? IS there no scheduling done during delivery creation even though route and subsequently transit time has changed?
    Please let me know the answer to this...
    Thanks
    Shobhit

    Hi ,
    You can use TA - MASS . Enter object type - BUS2032(for sales orders) on initial screen and select sales item data.
    Next screen enter selection fields like sales order no and items. After giving order no and item range , execute and enter all new values for any item data fields. After pressing button "carry out mass change", don't forget to press save button.

  • Actual goods issue date required to be equal to planned goods issue date

    Hi All,
    Can anybody tell me on what basis does the actual goods issue date get determined and what needs to be done if we want to restrict the actuall goods issue date to be equal to the planned goods issue date?
    Avinash

    Avinash,
    Can anybody tell me on what basis does the actual goods issue date get determined
    ???? It is the date that the goods are actually issued from stock, e.g. whatever the date was when the delivery was actually issued, that is the date that is normally written to this field in the delivery.
    what needs to be done if we want to restrict the actual goods issue date to be equal to the planned goods issue date
    That's a pretty restrictive criteria.  Basically, you are telling the warehouse that they are not able to issue the goods early or late.  In companies I have seen, that would constitute a lot of deliveries.  Hope your customers don't need the parts....
    Anyhow, the restriction would have to be against the goods issue transactions being used by the warehouse.  I don't believe there is any standard configuration that creates such a restriction, so it would require custom development.  If you pursue this restriction, make sure you leave yourself some kind of override.
    In many companies, this problem is handled through policy and procedure.  Warehouse manager simply creates a policy about early and late goods issues.  The system will track discrepancies in the case the policy is not followed.
    Best Regards,
    DB49

  • Planned Goods Issue date

    Hi,
    We have the system set up as follows:
    When the user enters the delivery date, and then material, route determination occurs. If, for example, there is a lead time of two days on the route, the Goods Issue date is set to two date before the delivery date.
    The user can enter many items.
    If, for different reasons,  the lead time is only a day, the user has to drill down on each item multiple times to change the Goods issue date. We are looking for a quick way, something similiar to "Fast change of delivery date" to change the goods issue date.
    Please share your experineces or proposals on the above problem for the user.
    Thanks in advance,
    Finbarr

    Hi ,
    You can use TA - MASS . Enter object type - BUS2032(for sales orders) on initial screen and select sales item data.
    Next screen enter selection fields like sales order no and items. After giving order no and item range , execute and enter all new values for any item data fields. After pressing button "carry out mass change", don't forget to press save button.

  • Actual Goods Issue date and Planned Goods Issue date

    Dear All
    we are loading the january,08 sales  invoice from the legacy system to SAP system through BDC program.
    for this at the time of PGI we are using Actual GI date as month of January, 08 and keeping planned GI date as the system date and at the time of creating sales order, delivery, we are not changing the material available date, loading date, delivery date, at the item level and system taking automatically based on the current date
    when doing PGI system accepting and creating PGI document and billing also creating based on this delivery.
    But dose it give problem in Inventory managements and FI in future, then what would be the right procedure to uploading the back dated invoices in the system.
    Please give me solution for this issue, or what we are doing is the right procedure.
    Thanks In advance

    For those who might come across this note, the design issue was solved by incorporating Rule Groups.
    Problem:
    Need to have 2 different Date references for 0calday, based on the key figures. For example for Sales key figure date it would reference to Actual GI Date. But, for Intake key figure I needed the date reference to be Planned GI date.
    Solution-- applied to the transfer rules of the desired cube:
    1. In the starndard rule group delete the transfer rule for the appropriate key figures. in this case (sales key figure)
    2. In the same rule group map all time characteristics from the cube to Planned GI date from DSO
    3. Create a new rule group in the transfer rule between the DSO and the Info Cube
    4. In the new rule group, create a new rule for the appropriate key figure i.e. sales
    5. In the new rule group, Map the date/week/month/fiscal period to Actual GI date
    6. save/activate
    This solution eliminates the need for changing the data model, which makes everything almost transparent to the report users.
    Hope this helps someone.
    Edited by: Babak Shafiei on Dec 12, 2008 5:23 PM
    Edited by: Babak Shafiei on Dec 12, 2008 5:24 PM

  • Planned Goods Issue Date adds by 7 days

    Hi,
    I have an issue with GI date increasing by 7 days when we do picking by vl06p.
    Delivery copies with the exact dates of the sale order but once the picking happens the GI date adds up to next 7 days. we  have route schedule active, but the Actual PGI was before the Route Schedule date,even then 7 days are added to GI date
    please help

    dear Varada,
          check in the material master whether the planned del time  and GR processing time is mentioned in MRP2 view.
    May be because of that you are having 7 days difference.
    Regards,
    Sudhir

  • Purchase order delivery shedule tabl , no Good issue date, loading date.?

    Hi Experts
      We found some Purchase order, in po item, it is without goods issue date, loading date and so on.
    Material has set ATP check on mrp3. what's possbile wrong? something wrong for matieral setup or others?
    Thanks
    Alice

    Hi
    Really thanks for your help. You mentioned " SD delivery of the sending plant is created and processed."
    Do you mean in material master , the sales view -delivery plant will impact this po GI date and Loading date? It maybe something wrong?
    Thanks
    Alice

  • Delivery date and goods issue date anomaly

    I am seeing issue in client site where when an order is entered for customer with a delivery date in December 2010 the goods issue date and loading are all correct. Soon as I put a delivery date after Jan 6, 2011 all the dates become the same. For example I enter Jan 29, 2011 as delivery all the goods issue, loading etc become Jan 29, 2011. Is there some config issue somewhere causing this issue.

    hi harvinder
    this is all happening because
    when you entered the customer and material in sales order the system automatically prompts the delivery date of the material.
    because in SPRO there is a setting called - DELIVERY SCHEDULING AND TRANSPORTATION SCHEDULING. with the help of factory calendar or shipping point calendar.
    in the same process it has shown these dates and these dates might be the tentative because material may not be available at that time & as soon as you changed the delivery date in the system manually again system will do RE ATP and would have given confirmed date as 14.01.2001 & basing on the confirmed date every date follows.
    this is standard behaviour of the system.
    balajia

  • How to fetch post goods issue date and sales order creation date

    Hi All,
    How to find out the difference between SD Sales Order Item Creation Date and final Post goods issue Date. I would like to know how to fetch those dates and what is the relationship between the tables from which i will get the dates.
    Please let me know the solution .
    Thanks in advance.

    Hi,
    Sales order creation date is when u raise a sales order in favor of the customer using VA01.......using ATP logic system purposes the material availability date....
    after saving ur sales order...when u raise the Delivery using VL01n  w.r.t to OR...than u have to perform picking ....In the picking Tab...specify the amount to be picked than press Post Good Issue....means the goods left the company premises ..
    You can the fetch the values using tables-  Use T code   SE12  or SE16
    Vbak-----order header
    Vbap-----order item
    Vbek-----order schedule line
    Likp-----Delivery header
    Lips----Delivery item

  • Want to change Del Date and Goods Issue date in Delivery scdl tab of PO

    Hi Gurus,
    I am in a situation wherein i need to change the Goods Issue date in Delivery schedule tab of Purchase Order and make it equivalent to Delivery date in the same tab.
    Currently the Goods issue date that is taken by default will always be one day after the Delivery date.
    Where is the control for this???
    Regards,
    Trishul

    Hi Jürgen,
    Thanks for your response. You are right. The Process is STO.
    The delivery has not been created as yet.  Everything is happening while creating the PO. The settings are such that the delivery date will be taken by the system automatically by doing the Availability check and simultaneously the goods issue date will be updated. But it will be one day later to the delivery date. But i want this to be same.
    Incase if i change the Goods Issue date manually, this is the message i get "Goods issue cannot be carried out in the past"
    Message no. V1062
    Please let me know if i am not clear.
    Regards,
    Trishul
    Edited by: Trishul Das on Mar 17, 2009 4:09 PM

  • Goods issue date and goods receipt date

    Hi Guys,
                 i was asked to display STO list.They asked me add goods issue date and goods Report date in the o/p columns.So any body can tell me what are the fields for goods issue and goods Receipt date's.?can u guys tell me the Tr code for these fields .?
    Thanks,
    Gopi.

    Hi there,
    I already solve it by myself.
    Actually is i call the initialization twice:
    Company.GetBusinessObject(SAPbobsCOM.BoObjectTypes.oInventoryGenEntry)
    Thats what make this problem happened.
    Sorry.
    Best Regards,
    danny

  • What is the difference between delivery date and actual goods issue date?

    Hi ,
    Can you please tell me the difference between Delivery date and Actual goods issue date ?
    Delivery data can be be greater than goods issue date?
    Thanks,
    Ajay

    Hi Ajay,
                  Delivery date means its the original date on which the delivery should be done.Actual goods Issue date is the date on which goods to be delivered according to the purchase order.There can be delay in the delivery so we maintain 2 objects.
    Yes delivery date can be greater than Goods Issue date.
    Hope this clears
    Regards
    Karthik

  • Change goods Issue date and delivery date

    while crating Sales document through VA01
    i want  to replace goods issue date (VBEP-WADAT ) with my Z calender date.
    so that delivery date(ETDAT) aslo should chaged automatically ( bcz iof the change in goods isuue date ).
    how to achive this ?
    i tryied in  Program    program of MV45AFZZ/ MV45AFZB in the User Exists mentioned below:
    1.     Form Userexit_Check_VBEP
    2.     Form userexit_move_field_to_vbep
    i was able to change goods issue date (VBEP-WADAT )  but  not refleting in output screen,..
    regards,
    ramesh

    Hi Venkat,
      Even it did not update in my user exit when I update from VBEP-WADAT.  So, I did back calculation (considering route lead time) and updated Delivery date field VBEP-EDATU.  It is simple.  I have given the sample code as below.
       if lines( xvbap[] ) = 1 and VBEP-ETENR = '0001' and            "Calculate RDD while the first line item entered
         vbap-route <> space and <<your GI date>> is not initial.    "Only when header RSD is filled
          select single TRAZTD into ws_traztd from tvro
                where route = vbap-route.
          ws_days = ws_traztd / 24 / 10000.
          if ws_days <> 0.    "Only when Transp. Lead time is maintained ( So, will not affect other entities )
             select single FABKL into ws_fabkl from T001W
                where WERKS = vbap-werks.
             CALL FUNCTION 'WDKAL_DATE_ADD_FKDAYS'       "Calculate as per Factory calender
                 EXPORTING
                   i_date        = <<your GI date>>
                   i_fkday       = ws_days
                   i_fabkl       = ws_fabkl
                 IMPORTING
                   E_DATE        = ws_date
                  E_FKDAY       =
                 EXCEPTIONS
                    ERROR         = 1
                    OTHERS        = 2
             IF sy-subrc = 0.
                VBEP-EDATU = vbak-vdatu.   "copy to the first line item
             ENDIF.
          endif.
        endif.    "Route days

  • Regarding Goods issue date and order date.

    Hi All,
    Could you please tell me from where we can fetch Goods issue date and Order date.
    Waiting for your reply.

    Preeti,
    Goods issue date/order date of what ?
    Goods can be issued in a number of ways, in reference to many types of documents.  In each case, the GI date and order date are found in different places.
    Please elaborate your request.
    Best Regards,
    DB49

  • Deliveries and goods issue date

    Hi,
    can any one tell me here the name of the table which can show the details of the deliveries against the goods issue date along with the sales order?
    Thanks,
    Ravi

    You can get these details in LIKP/LIPS and VBFA.

Maybe you are looking for

  • Enable Commenting for Reader not working

    I create a PDF file in Acrobat 8.1 and select Enable Commenting in Reader. However, the users open the file in Reader 9 and it doesn't work. I've been able to replicate this. And no matter what I do - save the file with a different name, in a differe

  • "open file in Photoshop" doesn't work any more.

    When I right clicked a picture in Lr (most recent version) and selected "open file in Ps (CC 2014)" Photoshop launched, but the image didn't show up. I tried several times, with Ps closed or open, but to no avail. Opening the file as a "smart object

  • Safari, iChat, Installer Problems!

    I tried the update manager, and it said to update a few things. After the updates, I realized I can't use some things such as safari, ichat, and the installer. At least I downloaded Firefox, so I can use the internet. I'm running a Mac OS X 10.4.11.

  • Itunes stores opens automatically

    hello: I don't want the itunes store to open automatically when I strat itunes. Any suggestions Thanks

  • Handling Sequence of Services in Oracle Service Bus 11g

    Hi there, I am very new to Oracle Service Bus, I want to achieve the following sequence of operations in OSB, please help me or guide me how to achieve it in sequence manner. 1) Transfer .txt file from STFP server to local shared folder. 2) Calling E