Plant cut off time to determine confirmed delivery date
Hello Friends,
Where do we maintain plant cut-off time for deliveries, while confirming delivery in sales documents, how system takes consideration of plant cut-off time?
Can anybody help me ASAP?
Thanks,
Nilesh
Edited by: Nilesh B on Jun 17, 2010 3:54 PM
Hello Nilesh
Apart from what usasapsd usasapsd mentioned, you need to maintain working hours and assign them to the Factory calendar and/or Shipping Point.
SPRO/IMG/Logistics Execution/Shipping/Basic Shipping Functions/Delivery Scheduling and Transportation Scheduling/Maintain Working Hours and Maintain Duration
Hope this helps,
Similar Messages
-
Online order cut off times for next day delivery
what is the latest time I can order off your web site for next day delivery?thanks
For all waiting on your preorders- I preordered mine Sept. 5th about 5 hours after the announcement (engraved, standard shipping). It was shipped Sept. 19th and was delivered to my house at 10am today (Sept. 20th), despite having an estimated delivery date of Sept. 21st. As noted in another post, they seem to be coming out of Kunshan, China and then Shanghai and Anchorage, Alaska. Mine might have arrived a day early because Indianapolis is a major FedEx hub and there is a direct flight from Anchorage to Indy. Suspect many will get their Touch models today and tomorrow.
-
Order entry cut off time to avoide same day line itme confirmation
Hello Friends,
We have a very unique requirement as below u2013
Business want SAP System to automatically determine the Order entry cut off time to avoid same day line item confirmation. I.e. If an order is entered after a specific time in a day (For example if order is entered after 2 PM local time) system should not confirm that order on the same day. In such cases system should confirm the schedule line for that line item on the next day.
Requesting you kindly guide us if there is something we can do in SAP to achieve this.
Thanks and Best Regards,
Amol Wadekar.Hi,
check the Rounding Work days in the shipping point customizing.
"Rounding-up period for delivery scheduling (in days)
The amount of time that the system automatically adds as a safety margin to the estimated time required for processing a delivery."
Check also http://help.sap.com/saphelp_46c/helpdata/en/dd/5607e7545a11d1a7020000e829fd11/frameset.htm -
Userexit which determine the confirm delivery date in order creation
Hi,
I need to obtain the ATP details which contain confirm delivery date of all the lineitem. The BAPI BAPI_MATERIAL_AVAILABILITY determine the material availability date but not the Confirm delivery date. But I require the Confirm delivery date which will be calculated based on picking, working day ...
Is there any userexit available to determine the Confirm delivery date from the material available date.
Pls help..urgent..
Thanks
Suresh KumarHi,
The userexits related to the material availability during sales document processing are:
User Exits For Availability Check
The user exits named here are planned for projects that are to be carried out in agreement with SAP development as they may only be used in consultation with SAP. SAP provides no guarantee if they are used without our advice!
USEREXIT_PLANT_SELECTION in program RV03VFZZ is an exception to this rule (see below).
User exits in program FV45VFZZ
USEREXIT_ADD_FIELD_TO_HEADER
USEREXIT_ADD_FIELD_TO_LINE
User exits in program FV45VFZY
USEREXIT_DELIVERY_GROUPS
USEREXIT_MVERF_INIT
USEREXIT_QUOTA_KEY_VALUE
User exits in program RV03VFZZ
USEREXIT_AVAILABILITY_IN
USEREXIT_AVAILABILITY_OUT
USEREXIT_DARA_REFRESH
USEREXIT_PLANT_SELECTION
This might be of some use.
Thanks and regards,
Satya -
Fetch max datetime records based on cut off time
Hi,
I want to fetch max date timestamp value for each key value but i do have cut off time as 21:00:00, which means anything after this time will be considered as next date 00:00:00 time value. I have attached an example for the same and
result set which i want. Kindly provide a SQL query for fetching like this.
Note: I have to use in a SELECT statement and i should not use temp table or cte, because i have to use this piece of code in another program where i cannot use temp tables. :(
Thanks!
Input:
ID is my key value
Output:
Regards,
FazluHi,
It should be partition by ID column and we need to add 3 hours during ORDER BY clause, isn't it?
select * from (select * , row_number() Partition by ID Order by Cast(dateadd(hour,3,[Date]) as date) DESC ) rnfrom yourtable) t WHERE rn=1
I will try the query in office tomorrow and let you know the status.
Thanks for the reply!!!
Regards,
Fazlu -
Updation of SO Confirmed Delivery date based on GR date for BANC parts
Dear All,
Would appreciate an answer on the following issue:
For Back to back/Indiv Purchase Order parts(BANC) the confirmed delivery date in the SO is updated based on the Order Acknowledgement date sent by the vendor for the corresponding PO generated for the SO. If the the vendor happens to deliver the parts in advance of the OA date(it happens quite often), the parts wait in stores till the confirmed delivery date is reached on the SO even thugh the original requested date on the Sales order is long past. If there is an order acknowledgement date in the system, at the time of GR, a warning message comes, but as our system is a high volume systme it is not possible to update the date in SO manually. Is there a way we can update the confirmed delivery date in the SO based on the Goods receipt date automaticall through config or a batch job?
Thanks
SumanDspsac,
Delivery date can be any date. For instance, if your customer insisted on a Sunday delivery, you would accommodate him, regardless of any calendar.
From the delivery date, the system counts backwards USING THE FACTORY CALENDAR ASSIGNED TO THE ROUTE by the number of days in the route. You have to consult the FC assigned to your Route to determine if the GI date has been properly calculated.
From the GI date, the system counts backward Pick/pack time, using the shipping point calendar, to arrive at Material availability date.
Calculations are explained in SAP online help
[Transportation and Delivery Scheduling|http://help.sap.com/erp2005_ehp_04/helpdata/EN/dd/5607e7545a11d1a7020000e829fd11/frameset.htm]
Regards,
DB49 -
Third Party Sales - Confirmed delivery Date
Hi,
In third party sales, vendor is delivering goods to the customer directly. My question is while creating the sales order from where the system is fetching the confirmed delivery date.
To get the confirmed delivery date, material availability date, picking & packing, transit time will be taken into account.
All the above activities are taking care by the vendor from where and how system is confirming the delivery date.
Thanks.Victor
System takes the Planned Delivery Time, Goods Receipt Processing Time from the material master and processing time from purchasing to determine when the material will be available. -
Confirmed Delivery Date in PO - Weekends Are considered
Hi All,
I have created a PO for a country XX to a Country YY
I have defined a Route from XX to YY with a transit time of 5 days and also factory calendar of XX as calendar.
When i create a PO from XX to YY , in Delivery Schedule of the PO , i see the commited date of delivery considers Sunday and Saturday also.
But the business does not want to conisder sundays and saturdays, How does the commited date determined in PO?
The factory calendar of XX does not consider Sat and sunday but the Confirmed delivery date shows Sunday ?
For example if delievry date: is 19 Sep
Transit time is: 5 days
Confirmed Delivery date in PO is : 14th Sep( Sunday)
But actual date should be :12th Sep ( Friday)
Please advice!!
Thanks,
Kumar
Edited by: Venkata Kumar on Sep 10, 2008 9:38 PMHi,
If you want to avoid del.date in the past go in customizing :
Materials Management
Purchasing
Environment Data
Define Attributes of System Messages
and set E for the message ME 039
Regards,
Mauro -
Hi SAP gurus
I have a problem in Sales order delivery confirmation date. Now lets say I take todays date as required delivery date. but confirmed delivery date comes to be 2 days later. Now for this material Total replenishment time is 0, GR processing time is 0, In house production time is 0. MRP type is Pd.
Requirement type is 041. Can any one put light on this issue how is it still getting 2 days later. or where should i check in all.
Thanks in advance.
Regards
sreekanthHI,
1. STEP: PL. SEE UNDER DEFINE SHIPPING POINT, WHAT YOU HAVE MAINTAINED. LIKE PICK/PACK DETERMINATION AND LOADING TIME. IF YOU WOULD HAVE MAINTAINED AS 'C', THE REMOVE IT AND CHECK THE ORDER.
2. STEP: UNDER CONTROL PANEL IN YOUR SYSTEM, WHAT THE TIME AND DATE SETTINGS MENTIONED. IF IT IS PAST OR FUTURE, THEN THOSE ERROR WILL THROW WHILE U R CREATING THE SALES ORDER.
PL. REWARD IF IT IS SOLVED.
REGARDS
KR -
Confirmed delivery date should be on Monday Only
Hi All.
I have a requirement wherein, for a customer the confirmed delivery date should be on monday only.
We are using APO for GATP.
Can anyone please guide how to go about this?
Thanks in advance.Hi,
Create a Separate Factory calendar with only working days on every Monday
The Factory Calendar will be done either in the OVR3 or SCAL
And assign this newly defined Factory calendar in the PLANT--Factory Calendar
Please do this and check
It will help
regards,
santosh -
Statistical Delivery date vs Confirmed Delivery date
Hi Experts,
Been browsing a bit in the threads and found that there are two notes that need to be implemented for a correct refreshing of Statistical Delivery date.
We would like the system to take the Confirmed delivery date as the Statistical Delivery date.
My question is, since we are using manual confirmations in the PO, Is it possible that the manually confirmed date in the PO is copied automatically in the Statistical Delivery date?
Or we need to manually confirm, and then again manually copy the same date in Stat. Del. Date field?Toni,
In Standard SAP, there is no relationship between 'Statistical Delivery date' and any date contained in the confirmations. If you want them to somehow be linked, this will require custom programming. Spec it out and hand the requirements off to your ABAPers.
One thing to bear in mind is that the Statistical delivery date(s) are related to the Purchase Order Item SCHEDULES. Confirmation date(s) are related to the Purchase Order ITEMS (not the schedules). If you decide to create some custom code, you will need to accommodate the instances when the number of confirmation lines is different from the number of schedule lines.
For example, for one Purchase order item, I might have 3 schedules, with 3 statistical delivery dates. When the Purchase order item confirmations are entered, I might have 1 confirmation, 3 confirmations, or 4 confirmations, all for the single PO Item. You will then have to decide which date should be moved to Statistical delivery date.
Regards,
DB49 -
Posting a confirmed delivery date to web
Dear All.
We'd like to be able to promise a customer confirmed delivery date to the web based on SAP ATP. This should take in to account current ATP, and the customer's delivery service.
We've been reviewing bapi_material_availability. This seems to be promising based on availability very well.
However, what I'm not seeing is any transit times from the route, pick/pack time, etc.... taken in to account.
Does anyone know, should this bapi provide this and possibly we are using it incorrectly?
Or is this bapi limited to only providing ATP info only? Do we need to call SD_SCHEDULING as well.
Is there an easier way to provide a confirmed delivery date to the web?
PS - there's also bapi_salesorder_simulate. But it's more complex for the developers to use, and performance is not as good. But maybe this is the only alternative.Material availability BAPI provides only ATP (same as CO09 pretty much). To my knowledge, there is no function that would provide ATP + transit time, etc. You would need to use ATP plus something else (perhaps your own code, based on the specific business requirements), shouldn't be too difficult IMHO.
There could be an Enterprise Service that provides this functionality, but it might require additional work to implement.
In any case, ATP + estimated transit time hardly seems a "confirmed" date to me. Many web sites provide "in stock availability" and transit times separately. E.g. maybe the customer would want to pay extra for faster delivery, who knows. -
Confirmed delivery date on sales order
Dear specialists,
I have a problem and I don't know how to solve it ...
When we create an order, we automatically create purchase requisitions ... The confirmed delivery date on the order-item is calculated by adding the value of field eban-plifz to the delivery date ... We manually change the value of eban-plifz in user-exit ZXVVAU16 and the confirmed delivery date is (re-)calculated automatically ... This works fine, except when we create a new order-item and go through the logic for the first time ... The first time we press enter and we see the screen 'Purchase order scheduling', the date is wrong ... I found that the value of eban-plifz is refreshed in function ME_REQUISITION_PRESTEP in the form neue_pos_banf - bezugsquelle_3 ...
My question is if there is a possibility to change the value again in a user-exit before we get the screen 'Purchase order scheduling' ???
Hopefully someone can give me an answer ?
Greetz,
Kurt.Hi,
i have a similar problem. You talk about user-exit ZXVVAU16, but this is the project (CMOD), don't?. Can you tell wich enhancement do you use to change availability sales order???
Thanks
Edited by: RODRIGO PEREZ on Feb 20, 2009 2:24 PM -
Confirmed delivery date should be on Monday
Hi All.
I have a requirement wherein, for a customer the confirmed delivery date should be on monday only.
We are using APO for GATP.
Can anyone please guide how to go about this?
Thanks in advance.Hi,
1. For this you need to maintain the Customer Calendar...
IMG --> SD --> Master data --> Business Partner --> Customer --> Shipping --> Define Customer Calendars....
Here create a calendar with working day as only on Monday and other days as holiday.
2. Assign this calendar in the Customer Master --> General data --> Unloading Points....
create atleast one unloading point and assign the newly created calendar... you can also set this unloading point as default one...
Now the confirmed delivery date will be only on monday... if the confirmed qty is available on tuesday then it will be confirmed to the customer on next monday....
Hope this solves your issue.
Muthu -
Credit Card Authorization for Confirmed Delivery Date
When a credit card order is placed and the confirmed delivery date is beyond the expiration date on the credit card SAP allows the order to be placed and authorized. If the confirmed ship date is beyond the expiration date of the card then shouldn't SAP block the order? Currently, it is not doing this in our systems.
Is anyone aware of how to change SAP to check if the confirmed delivery date is passed the expiration date of the credit card?
Many Thanks!
KyleHi Deborah Bourgeois,
There is no Credit Hold check box enabled in the Customer window, We are getting same error in order management too.
Scenario 1:
When we set the profiles like below iStore,OM,AR order getting confirmed with Hold and tangibleId is starting with as shown below
TangibleId:
iStore = ASO%.
Order Management = ONT%.
AR Manual orders = AR%
Profiles:
ASO: Credit Card Authorization = No
IBE: Perform Payment authorization = Yes
ASO: Default Order State profile = Booked
Scenario 2:
When we set the profiles like below iStore,OM,AR order getting confirmed without any Hold and all the tangibleId is starting with ONT%
ASO: Credit Card Authorization = Yes
IBE: Perform Payment authorization = No
ASO: Default Order State profile = Booked
Our Expectation:
1. Order should be confirmed with out any Hold.
2. Tangible id should as below
a. iStore = ASO%.
b. Order Management = ONT%.
c. AR Manual orders = AR%
3. All this should work for iStore when the below profile is enabled
IBE: Perform Payment authorization = Yes
Could you please help me on this.
Thanks
Vino.
Maybe you are looking for
-
Xml report getting errored out
hi friends i have one custom xml report with ten parameters whenever i submiteing concurrent program with mandatory paramas it will getting succesfully completed without requirement out put. Again whenever i submiteed program with mandatory params an
-
How can I create a new sales order template
Hello, how can I create a new sales order template in SAP CRM 7.0 (Web UI)? I want to use this sales order template in scenario ´'Mass Generation of Sales Orders via Marketing Projects'. Thanks for your support in advance. Best regards, anvan
-
I'm not very tech savy and this Nook is new to me.
-
I have conection to the internet but Safari is not loading pages, the blue line stalls half way through loading the page. Any sujestions on how I can fix this?
-
Why is the mail, calendar, and contacts grayed out in system preferences
why is the mail, calendar, and contacts grayed out in system preferences?