Plant Maintenance with MRP

Dear all,
Sorry because i can't find a forum for PM function, so i have to post this subject in PP forum. But I think thera are some solution for my problem.
1. Does anyone run MRP for Plant Maintenance??? because I have to make requirement planning of material for maintenance plan in my company.
2. I have a equipment BOM, so when I have a maintenance order. Why the system does not auto load all of component in BOM into tab component of maintenance order? If I want to load assign component fof maintenance order, I have to do this by choose each item in BOM equipment and assign it to maintenance order.
Thank all

Hi VU,
As i u/s MRP is not run like for PM or PP or MM, it is run for Materials in the plant & any material which allows MRP will be considered for MRP, Coming to PM you may stock your spares not on individual requirement but say based on consumption(reorder point), consumables like grease & oil can also be planned this way, then these materials will be considered in MRP, and when you create an order and you have missing part, MRP would consider the requirement from order.
Coming to 2nd part, In manufactuirng(PP) a material, all the materials given in the BOM would be required,
while in maintenance this would not be so, for an equipment you may have no.of spares listed out but all the spares would not be used ?????
Hope this helps.
Regards
Mithun

Similar Messages

  • Which book to buy for Plant maintenance on SAP press...

    Which book to buy from SAP press which book has good amount of configuration details regarding Plant maintenance i found three books if there is some other good book please do let me know
    1.maximize your plant maintenance with sap
    2.sap enterprise asset management
    3.plant maintenance with sap

    Hi Mohammad
    I already posted a query for SAP PM in certification forum , but i couldnt see any active replies.
    SAP PM certification
    I am already SAP SD certified and working on Support sider of Customer Service Module , This Teched Planning to take certification exam for SAP PM maintenance and repair, But i am not getting any source of help as to how do i start with for preparing for the certification and no idea as to what are the topics to be covered and how will be the set of questions , Is there any seperate certification only for SAP CS
    Please do reply on my query and guide me accordinlgy
    Best Regards
    Waseem Mohammad

  • MRP VIEW For Plant Maintenance

    Hello friends,
    My Client require Minimum Stock of Spare Parts in Maintenance Store and when ever the minimum reserve quantity hit an automatic PR will generate and the purchase deptt. can Procure. so what will be the MRP View for Plant Maintenance in this scenerio and what will be the configration.
    Thanks
    Neeraj Gupta
    Edited by: neerajj0 on Jun 11, 2010 11:33 AM

    Hi,
    Material Master will be maintained by MM people. For Spare parts, material type would be ERSA. Maintain the MRP type for Reorder Point Planning in MRP1 view of Material Master & Reorder Point Qty in MRP1 view.
    While running MRP, spare parts also will be planned.
    Regards,
    Maheswaran.

  • MDG with Plant Maintenance

    Hello Experts,
    Is there anything called 'MDG with Plant Maintenance'?  If yes, what activities are involved related to Plant Maintenance?
    Thanks
    Sanjay Tiwari

    I'm not aware of anything in the PM module..
    But I did find this on the web:
    http://www.utopiainc.com/data-services/eam/mdg-for-eam
    PeteA

  • Are there any third party pacakages for plant maintenance that can be interfaced with

    are there any third party plant maintenance packages that interface with OPM? does Oracle apps have a module for plant maintenance?

    I'm working for a leading Food Industry in Kuwait (The Kuwaiti Danish Dairy Co.) We have a massive implementation of OPM with 24 modules, BI tools (OSA, OFA) and Maximo (The only third party package) integrated with Oracle. OPM version is 11.0.3 on database 8.0.5. Now you have option of 11i (eAM) with POC (PM) or Maximo 5i integrated with 11i (and of course any other 3rd party solution which can be integrated with OPM).
    You can write to me on: [email protected] or call me on: +965-9650172 for details.
    All the best.

  • Intergration of Production Planning with Plant Maintenance (SAP Modules)

    Our SAP Implentation Consultants are creating work centres in Production Planning which are different to the workcentres in Plant Maintenance as follows.
    Work Centres in PP
    Mixing
    Blowing
    Filling
    Packaging
    Work Centres in PM
    Mechanical
    Electronics
    Electrical
    My observation is that in PM the work centres should be identical to PP work centres. whereas Mechanical, Electronics and Electrical should be configured as divisions or departments. The idea is that by having PM WC identical to PP WC the costing will be simplified.
    looking forward to expert's advices, please
    Amjad

    I am locking this thread in PI forums. Ask your question under SAP Solution forums
    /community [original link is broken]
    Regards,
    Prateek

  • Purchase Order is generated after MRP for Material with MRP Type ND

    Hi Everyone,
    Material type := HAWA
    My material procurement type = F i.e. External Procurement.
    MRP Type = ND in Production server , and VB in Quality
    Lot Size = EX
    Material Status :- 15 Pre-release both for Quality and production server
    The Material is bulk material and bulk material indicator is set.
    Purchasing View is also maintained for the same.
    Planning Strat = Z5 Company specific
    Special procurement key:- Z7 Company specific
    I am running MD02 with following parameters.
    Create Pur Req =1, PR
    Create MRP List = 1, MRP List
    Delivery Schedule = 3, Schedule Lines
    Planning Mode = 2 Re- Explode BOM & Routing
    Scheduling = 1
    Issue:
    After MRP run, system is  generating PR, Though with MRP type ND purchase requisition should not be generated.
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.
    After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    We havent been able to locate the root cause so far
    Please guide us
    Thanks in Advance,
    Ayaz
    Edited by: Ayaz Alam Khan on Feb 16, 2011 2:41 PM

    IF the material is ND, system won't Run MRP for the material
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    There is no link
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    system will read the X plant  material status or plant specific material status first and then only system will read MRP type

  • Creating Z report for material stock (plant maintenance module)

    hello,
    we are implemented Plant maintenance module (SAP PM)  in our organization.
    our requirement is to create a stock report which will incldue
    followings:-
    1)material number
    2)plant number
    3) storage location
    4) material type
    5)valuation type
    6)Opening Stock 
    7) OpValue 
    8)Received Stock  
    9)   ReceiptValue      
    10)   Issue Stock          
    11)  IssueValue        
    12)  Closing Stock      
    13)  Closing Value
    we want above details in ALV grid format.
    to gert all the details for perticular material, we calcute closing stock and closing value in following manner:-
    opening stock + received  stock - issue stock = closing stock
    opening value + recipt value - issue value = closing value
    we are unable to find table name for  accessing  opening stock,  received  stock , issue stock  & opening value ,recipt value , issue value from system. please suggest table name information for getting above details  for creating Z report

    Dear friend,
    Before to make a decision to bulid a custom report make sure you have checked out the following standard transactions:
    MB5T Stock in Transit
    MMBE Stock Overview
    MD04 Stock/Reqs list
    MB53 Plant Stock Availability
    MB52 Warehouse Stock
    MB5M Expiration Date list
    MB5B Stock for Posting Date
    MB5T Stock in Transit
    MBBS Valuated Special Stock
    MBLB Stock with Subcontractor
    The possible tables are:
    MARA, MARD, MARC, VBEP, VBAK(VBAP), EKKO(EKPO), EKBE, EBAN, EBEW, MSEG, MKPF,...
    Good luck!

  • Intercompany Stock Transfer starting from Plant Maintenance

    Dear SAP Experts,
    We are planning to implement Intercompany Stock Transfer Process starting from Plant Maintenance side.
    We would like to be able to order for maintenance work order material which belongs to different plant.
    After adding such material to work order system should automatically create purchase requisition with Item Category U – Stock Transfer.
    Such purchase requisition will be then converted to P.O. Then standard MM process will follow meaning on supplying plant side Delivery & Goods Issue will take place. And on receiving plant side Goods Receipt against P.O.
    Can you please let me know whether there is standard process which covers what was described above especially part on Plant Maintenance side?
    If there is no standard process can you please advise (propose some best practices) how we can realized such request?
    Many thanks in advance.
    Grzegorz

    Grzegorz
    From memory, with intercompany trading you need to create a PO/PR on Company A and a corresponding Sales Order on Company B.
    This can be automated via MM
    I would suggest you ask the question in the MM Forum..
    PeteA

  • Goods issue for plant maintenance order

    Goods issue with ref to plant maintenance order( Componenets of the order) is not possible in transaction code MIGO. Error message " MIGO is not possible for the refurbishment order".
    Goods issue for the same order can be posted with transaction MB!A.

    hi santhosh
    kindly check the order type .i think you are using MB1A for refurbishment process.but it is not possible.only maintenance order can be posted via MB1A
    follow the procedure for goods issue in refurbishment order.
    Choose Logistics ® Plant maintenance ® Maintenance processing ® Completion confirmation ® Goods movement ® Goods movement.
    The entry screen for a goods issue appears.
    Choose the pushbutton For order.
    Enter the relevant order number in the dialog box and choose Continue.
    An entry screen appears.
    Choose Copy.
    The Maintain Serial Numbers dialog box appears.
    Choose Reference document.
    Enter the order number in the Refurbishment order group box and choose Execute.
    A list appears with the planned serial numbers for the refurbishment order.
    Check the selections of serial numbers, for whose material you want to post a goods issue, and choose Copy.
    The serial numbers are copied into the Maintain Serial Numbers dialog box.
    Choose Exit window.
    The goods issue is posted.
    regards
    thyagarajan

  • Urgent Issue in Plant Maintenance Module

    Dear Experts,
    We have requirement as described below, please give us your solutions / comments on this.
    We have GTC company which is having around 800 trucks for transporting the products. I n this company we have implemented SAP Plant Maintenance Module, as we have the maintenance activities done for vehicles.
    Under the same group of companies, we have PM1,PM2,PM3 companies which provide maintenance to GTC. These companies are not external to the group.
    When I raise a maintenance order for a vehicle then I will mention hours of work and material that need to be used in the activity. This maintenance work / labour is provided by PM1/PM2/PM3 company.
    In plant maintenance we have external service management, but that is for external vendors who provide service to GTC.
    But how to handle the same with internal vendors like PM1/PM2/PM3.
    Please tell me how to handle this kind of scenario.
    Thanks in advance.
    Nagesh

    Hi,
    this is a major topic and cannot be covered in a blog. Even if it can it will take a lot of time to clarify. So, first do your checks within your module. Check if u really need to treat the services from the other company as external services. You might as well create workcenters in the plants of the other companies. And make a single maintenance planning plant for all the plants in these companies. This will make a better solution technically. But think also from the perspective of the cost of this solution. Meaning, is it worth doing all the jobs such as maintaining activity prices, work centers in the other plants etc..
    In general, my suggestion is include the FI and CO consultants at least in the discussion. It will b good if u can have the MM consultant also during the discussion.
    Bala

  • How to claim the insurance of equipment in sap plant maintenance

    Hi,
    I have a question for you, in our company with lots of equipment's. Insurance has done for some equipment's, how to claim the insurance using plant maintenance. Kindly let me know the process how to claim the insurance of an equipment.
    looking for your valuable information
    Thanks

    mohan kumar
    This is an interesting requirement - I've never seen a process to cover insurance using the PM module.
    You could follow the warranty process to claim insurance.
    Alternatively, talk to you Finance team to see what they recommend.
    PeteA

  • Problem With MRP

    Hi Friends,
    I am facing a problem with MRP. In my Implementation, my Client is a Automobile Gasket Manufacturer.
    One major product line is Gaskets which is high volume and low price
    We will use Make to stock  with streategy 40.
    Now the queries are as follows-
    1)       What should be the frequency of MRP Run for the plant (weekly , monthly of daily)
    2)       If  after one MRP Run- some Planned Orders and some Purchase Req are converted to Production Orders and Purchase Orders. My Prod Orders- 100 Pieces and PO is 1000 Kgs.
    Now subsequently , due to change in schedule,(PIR is maintained by Sales Department and it changes  often) lets say, my PIR is Changed from 100 to 10 Pieces ,
    How can a PPC  person come to know of this and inform the Buyer to foreclose the PO or amend the PO and as well change the Prod order also.
    Thanks in Advance
    Waiting for your Reply,
    Praveen

    Hi Praveen
    1) What should be the frequency of MRP Run for the plant (weekly , monthly of daily) : Daily Basis as your demand changes frequently.
    2) PPC will understand from MD04 screen where all the result of MRP as Stock Requirement List available.U cant change Production Order while running MRP as your demand changes from 100 to 10 pecies because Prodction Orders are firmed recipept.In that case you can change quantiy , do the availablity check and scheduled again  or set TECO so that it will not show up in the MD04 screen also.
    Any changes to demand and subsequent effect can be viewed through the exception messeges column in MD04/MD05
    Hope this will help you to figure it out.
    Regards
    Jia

  • Queries on plant maintenance

    Hi all
    Can anyone tell me where can I raise queries about Plant Maintenance?
    Looking is an option.
    Edited by: kishan P on Oct 5, 2010 2:35 PM

    Dear Saran,
    Thanks for responding to my query. Kindly let me know does these tables have got any link with other Quality Notification tables like QMEL, QMFE, QMIH, QMMA, QMSM, QMUR and QPCT. I am picking rest of my report data from these tables.
    Regards,
    Alok.
    I'll be rewarding you the points without fail.

  • Plant Maintenance to External Service Requirement (MM-SRV)

    Hi,
    Kindly tell me how to create a MM-SRV Purchase Requisition from Enterprise Asset Management (Plant Maintenance).
    eg. A plant maintenance order (IW31) is created for repair of a transformer. It requires external service procurement with following structure.
    Service Item D: Transformer repair
    Limit 10,000 eur
    Outline 10: Dismantling
    Service Line 10: Junior Technician 5 hr, 10 eur
    Service Line 20: Senior technician 3 hr, 15 eur
    Outline 20: Cleaning
    Service Line 10: Oiling 5 hr, 20 eur
    Outline 30: Reassembly
    Service Line 10: Junior Technician 15 hr, 10 eur
    Service Line 20: Senior technician 10 hr, 15 eur
    Kindly tell me how Purchase Requisition can be created with service structure from Plant Maintenance.
    Thanks & Regards,
    Ashish

    In IW31, select the Order type. Select the Planning Plant.
    give the main work center & Functionla location of performing the services
    Click on the operations tab, select the Control Key PM03 Plant maintenance-External(services). Enter the operation short text. Select the line item & click on External Icon (at bottom of page)
    Give the details such as material group, purchase group, Purchase organization , requisitioner.
    Create the service lines & Save the data. Order gets created. goto IW32 & release the order.
    PR can be viewed in Act. Data tab at the service lines.
    Thanks & Regards
    Kishore