Hi experts,
I am getting this error-Plant Z199 not assigned to controlling area (when creating sales order)
I have gone through OX19 and then OX18 for company code assignment to plant.
No clue on google. lot of people suggested lot of things.
Srinu S given some solution. But that is also not working.
No solution.
Kindly resolve.
Thanks & regards,
Supriyo

hi,
Did you assign Plant with sales area and company code. please check also in enterprise structure plant assignment with sales area.
Enterprise Structure => Assignment => Sales and Distribution => Assign sales organization - distribution channel - plant
go to OKKP and check Sales => Alternative Authorization=> Heirarchies for Cost
Center and Profit Center for Credit control assign.
thanks
Md. Enayet Hossain

Similar Messages

  • Various FM areas are assigned to controlling area

    Dear Sir,
    While uploading budget throufh KP06 the error is coming :
    Various FM areas are assigned to controlling area 6000
         Message no. F6097
    Kindly suggest
    Regards
    Raj

    Hello Raj,
    There are many different reasons/options:
    1) If you are on EA-PS package 200 you can try note 723605 to avoid the error message.
    2) If you are not on EA-PS 200 (application release 4.7) the reason of the message F6097 is the following:
    If for example Fund was activated in Customizing of Public Sector Management, it is not possible to assigned an company code to an controlling area, that is not FM relevant.
    Please check if it is one assignment available. It can be field fund or the others available in the following SPRO settings:
    SPRO -> Public Sector Management -> General Settings for Public Sector Management -> Basic Settings: Account Assignment Elements -> Activate Account Assignment Elements
    Please check if you have activated Fund or Functional Area or Grant or Funded Program there.
    How could you solve this problem: Please deactivate the fund (or the one that was active) temporary. Then assign FM area to Controlling Area. Then activate the fund again.
    3) Please notice, the standard is the following:
      COarea CCCC
           >  CompCode 0001     > FMarea FFFF
           >  CompCode 0002     > FMarea FFFF
           >  CompCode NNNN     > FMarea FFFF
    All CompCodes, assigned to the same CO area have to be assigned the same FMarea. This is not so in your case. Because different local currencies in the assigned CompCodes you assigned FM areas with
    corresponding currencies. Result: The assignment COarea <  > FMarea (via the CompCodes) is not ambiguity. This is what the error message of KP06 is saying (note  908908).
    If you want change the currency settings in CompCodes to assign only one FMarea to all CompCodes maybe you have to covert the existing transaction data, too (see notes 89531 and 39919).
    But I found a modification note 779180 it meets your assignments.
    Please check that. Maybe it have to be extend that KP06 will work also then. I'm not sure if it will also work if you assign these CompCodes to the same COarea.
    4) The relation between FM-area and CO-area can only be 1 to n. Because there is no direct relation between FM- and CO-area, you have to check the relations between the assigned company codes to FM- and CO-area. Please read the doumentation under the path:
    Public Sector Management -> Funds Management -> Master Data -> Enterprise Structure - Organizational Units -> Organizational Structures - Assignments.
    I hope it helps to resolve your issue.
    Kind Regards,
    Vanessa.

  • Ship to party not assigned to sales area

    Hi everybody
    When I am creating sales order for a customer in the sales area into which it's CMR is maintained  eg. 1000, 10 , 00. I get an error message ' ship to party...is not assigned to sales area 1000, 10, 01.'' Here SP is also SH.
    I checked the common Distribution Channel & common Division Master Data & the ref dc & ref dv are properly maintained. I don't know from where system is taking division 01.

    Hi,
    Please check VOV8(Sales documet type control).Here in the document type which you are using,check if Item condition field is marked.If it is marked then system is checking the division of the material you are using.
    Extend the customer to 1000/10/01 and then try creating the order.
    Reward points if useful
    Regards,
    Amrish Purohit

  • Profit center not found in controlling area

    Hello all,
    While trying to change the wbs element of a PO in ME22N, I am getting the error message "Profit center XXXX not found in controlling area".
    Do any one hava an idea how to fix this problem?
    Thanks in advance for your help,
    Soumaya

    Check whether the PC Hierarchy has been defined or not in KCH5N / KCH6N for your Controlling area.
    Single PC - Check in KE53.
    If not, you need to define the PC Standard Hierarchy
    Thanks

  • Assigning plant to controlling area

    Dear Gurus,
    Got this error message while doing Individual Purchase Order.
    " Your Plant is not assigned to controlling area"
    Here I have created controlling area and assigned to the company code but could not find where i have to assign it to a Plant?
    Hope Gurus can solve this for me.
    Regards

    Hi Venkat
    I think it is referring to Purchasing Organization.  Check in <b>OX17</b> whether you have created and assigned your Purchasing Organization to Plant. If not, assign it and try once again.
    Thanks
    G. Lakshmipathi

  • Two Company Codes and one Controlling  Area  Issue

    Hi,
    Client has company code 1000 and 1001
    Company code 1000 has been assigned to controlling  area 1000,but company code 1001 was not assigned to controlling area.but in last month they have posted FB75 credit memo with profit center.Now when they are trying to post the same it is giving the error saying company code was not assigned to controlling area.
    they are also using document splitting concept.How to solve this issue without assigning profit center.
    why this is giving the error now and why it was accepted before.any idea.
    Thanks
    Sunitha

    HI,
    Can u explain clearly for which company code u have posted document in FB75. If it is 1001 Company code It will not able to take Profit center or any cost object. Since u have not assigned comapny code 1001 to controlling area 1000.
    Please check Correctly.
    Regards,
    Sreekanth

  • Controlling area does not exist in assignment ?

    Hi,
    I've created & assinged controlling area to the company code , But then When I used PPOME to create org unit and assign the Controlling area , It did not exist in the list ? How can i configure this
    Thanks in advance

    Hi,
    Check in V_TKA01_GD table (assign company code to controlling area) whether controlling area is assigned to company code properly or not. If it is assigned properly then in PPOME Tcode in Account Assignment tab once you enter your company code Controlling area will be selected automatically.
    If controlling area is not assigned to company code properly then you will not able to see that in PPOME. In this case you can take help from FI consultant as they only create Controlling area and assign it to company code.
    Regards,
    GRM

  • Implementing FM, "Assign Controlling Area to FM Area" unavailable

    Hello,
    This is the first time I implement FM. I have activated the following bussiness funtions, and I am following the IMG installation instructions.
    One of the first steps is to assing a Controlling Area to a FM area, but this transaction is not available. It is not in Enterprise Structure --> Assingment --> Controlling. And when searching by transaction sapl0fmc, I get a message saying the transaction does not exist.
    My cliente is already using FI and CO in production. I am doing this in Development.
    The bussiness functions I activeted are the following:
    FICA_EF
    FICA_FM
    ISHERCM_MAIN
    PSCD
    PSCD_SETTINGS
    Am I missing something?
    Thank you in advance,
    Paola

    Hello,
    Thank you for your answer. I have already asigned my company code to the FM area. But in the IMG implementation guide "Prepare Funds Management Installation", it clearly states in point 2:
    You then assign an FM area to each company code and controlling area relevant to Funds Management.
    For more information, see sections:
    a) Assign Company Code to FM Area
    b) Assign Controlling Area to FM Area
    If I navigate to "Assign Controlling Area to FM Area, I get:
    Assign controlling area to financial management area
    In this activity you assign all controlling areas relevant for Funds Management to financial management areas.
    I posted this question since I was not able to find the transaction necessary to assign the Controlling Area to the FM area.
    So, if I want to associate a Cost element to a Commitment Item, it is not necessary to assign a controlling area to a FM area?
    Thank you,
    Paola

  • Assign Controlling Area to Financial Management Area

    Dear SAP Gurus!
    I'm greatly distraught! I have been reading SAP HElP. I'm using ECC 6.0.
    It says that to assign Controlling Area to Financial Management Area, I can go to the following menu path:
    Enterprise Structure >> Assignment >> Controlling >> by choosing Assign controlling area to financial management area
    However I'm not able to find the node "Assign controlling area to financial management area" in IMG.
    I'm trying to activate Fund Managment within CO area and therefore would like to assign controlling area to financial management area. Currently I have created company code and controlling area and have also assigned the controlling area to the company code.
    I would appreciate greatly your advise and feedback, thanks!
    Regards,
    Distraught!

    Hi,
    The FM area is not derived from a direct assignment of the organizational unit of Controlling, from the Controlling Area, to an FM area, rather from an indirect one.
    The FM area is determined via the company codes assigned to the controlling area to which the FM area is assigned, whereby the company code is determined from the CO objects
    You can deactivate the unrequired FM components from "Deactivate Account Assignment Elements in Controlling" which is in BCS.
    Regards

  • REG:ASSIGNING CONTROLLING AREA TO ENTERPRISE ORGANISATION

    hi ,
    i have created an org unit using the t.code ppoc_old.
    i have activated my controlling area .
    i have activated the the enterprise organsiation for this controlling area as active.
    i am not able to assign the controlling area , nor company code nor cost center to my org unit.....
    can any one tell me is there any other link between the controlling area and enterprise  organisation ????
    thanks & regards
    sharon

    Hi
    first you need to ask your fico people that for which company code they have created the cost centre and controling area. if they have done for another company code means then it will not be possible to assign to your org. unit .
    this assginement can do in IT1008 account assignment. pls check the comapny code here under which company code that unit is existing, and then try it will be resolved.
    Regards
    Suresh

  • Change maint Plant in diff controlling area.

    Hello Sapient's,
    Is there a possibility where i can change the maintenance plant in floc which belong to other controlling area & company code.
    If yes , how ..please help.
    Error - Message no. I0231
    regards !
    ajay

    Ajay,
      No, its not possible to change to a maintenance plant that belongs to a company code in a  different controlling area. You should be able to change the maintenance plant within the same controlling area however.
    Thanks
    Narasimhan

  • Profit Center Is not in Controlling Area BP01

    Hi
    I am getting the below error. Please help me
    Profit center 2100 is not created in Controlling Area BP01
    Message no. FAGL_ORG_UNITS001
    Thanks
    Surya

    Hi,
    It is what it's said: there is no profit centre in the CO area defined. You have to create one (KE51) or check if you are using the right one.
    Regards,
    Eli

  • Extraction error "Target cost version in controlling area does not exists"

    Hi Gurus,
    I am trying to pull some data from a SAP OLTP system into SAP BW 710 system, using extractor "0CO_PC_02". The data load is failing with the below error message:
    Target cost version in controlling area does not exist     KN     147
    Target cost version 2 not defined. Check your entry     KV     35
    Internal program error ( Order 000010510554 Version 002 )     RM     11
    Errors in source system     RSM     340
    The same error is thrown when I am trying to execute the extractor in RSA3 in the source system.
    Please help me with the resolution of the same. It's a high priority job we are handling as of now in this.
    Thanks & Regards,
    Vikas Kr.

    You are attempting to display data on a target cost version that does not exist in controlling area.
    see this http://forums.sdn.sap.com/thread.jspa?threadID=1609418
    http://www.consolut.com/en/s/sap-ides-access/d/s/doc/YV-KN147

  • Assignment of credit control area to sales area

    Hi Friends,
                     What is the advantage of assigning credit control area to  sales area when it is already assigned to the relevant company code ?
    Regards
    Mahesh.

    hi,
    Credit control area when assigned to sales area(sales orgd.cdivision) rather than company code, it will be more specific and relevant to track the credit record of the customer as he was assigned through the sales area where he is in.
    And also to generate reports based on the sales area , this helps in ease to monitor the customer behaviour based on the materials.
    Mohan
    Award  points if it helps.

  • How to get new company code and controlling area in SRM

    Hi SDN,
    we are on SRM 5.0.
    Our finacial experts want to implement a new company code and controlling area.
    In SRM I can set up a new company code easily in ppoma_bbp and import a new plant from backend for the new company code.
    When testing in EBP I get the error: "company code xyz not available in controlling area zzz"
    So I need to import the new backend controlling area, too. How can I get the second controlling area in SRM?
    Thanx for help,
    matthias

    Hi Muthuraman Govi  and Sanjeev,
    in fact I can see in backend in transaction KS03 (show cost center) there in the F4s, which comp.code + controll area combinations are valid and have indeed cost centers assigned.
    So I have a new valid comp.code and a new valid cont.area.
    The new comp.code belongs to the new contr. area.
    In SRM I set the BUK attribute as described by Sanjeev (I had that already done). Still, if it is like you say, why do I get an error in EBP when trying to buy products from the new plant in the new company code...
    Is there any more config.work necessary in backend or SRM?
    kind regards, matthias