Plant to plant subcontracting(Under one company code)

Hi,
I need a help on one issue.
We are having multiple plants under one company code.
Material goes with 57F4 challan for subcontracting plant to plant.
How to do the subcontracting process for plant to plant.
Please explain step by step.
I know the normal process (with vendor)
Also, if I have create a subcontracting PO, how the receiving plant will come to know about this?
How will he receive the material which I have send?
How the production activities at their end?
Do I need to do the MIRO?
Please thrwo some light.
Thanks in advance,
Piyush

1)  Create Subcontracting Purchase Order with `0` Cost
2) Transfer of Components to Subcontractor
3) Create Subcontracting Challan
   a)Receive the Components as non valuated Materials
   b)Process the Materials to get the SF Product
   c)Create the Outbound Delivery without Ref. To Sales Order
   d)Endorse the Subcontract Challan Manually
4) Post Goods Receipt
5) Reconcile Subcontracting Challan
6) Complete / Reversal / Re-credit SubcontractingChallan
During Reconcile the Subcontract Challan - J1IFQ,Enter Manually into the Assigned Quantity Field the Components that are actually assigned for this Subcontracting Process.
Regards,
eswarmanu...

Similar Messages

  • Multiple currencies under one company code for contracts

    Gooday!
    We have a new schenario ( In RE-FX) where we have a couple of contracts which were negotiated with the landlord that needs to be settled in Rand, whilst the company code are setup for another currency, which is dollar (caters for the bulk of the contracts). So each time you create a new contract the currency is already greyed out (Dollar), which obviously means that it cannot be changed there.
    Apparently the company code can be setup in FI to accommodate secondary currencies, however, this seems not to be the case in RE-FX.
    My question is this, is it possible to have multiple currency contracts under one company code in RE-FX, and if so, do one set it up in FI or RE-FX?
    Any assistance would be greatly appreciated!

    Conditions in Foreign Currency (New)
    As of SAP ECC 6.0, Enterprise Extension Financials, Enhancement Package 2 (EA-FIN 602), Business Function Real Estate (RE_GEN_CI_1), you can enter conditions for contracts, rental objects, or contract offers that are in a currency that differs from the local currency of the company code.
    You can enter the currency directly when processing conditions. You can also enter a currency translation rule in the posting term. The rule is then used for all conditions to which this posting term is assigned.
    You specify in Customizing which currency translation rules are allowed for each contract type and usage type.
    See SAP Note 123819.

  • How to see all the customers under one company code?

    hi,
    I would like to know, is there any standard transaction code to see all the customers under one company code?
    thanks.

    Hi,
    You can check through :
    1). SAP Menu ->  Accounting -> Financial Accounting -> Accounts Recievables ->Information Syatem -> Reports for Account recievable accounting -> Master Data -> Customer List
    2). Run Txn SE16 -> Enter Table name (KNB1) -> Enter Company Code -> Execute.
    Reward Points if this helps.
    Regards,
    Harsh

  • Sevaral Balance Sheet under one Company Code in SAP

    Is it possible to generate profit center wise, branch wise, balance sheets and income statements including other reports under one company code in SAP separatly.

    Yes. It is possible through Financial Statement Version. Further Report Writer or Report Painter helps to create your own Profit Center Reports.
    Regards
    Sampath
    Edited by: PSampath on Nov 25, 2009 11:08 AM
    Edited by: PSampath on Nov 25, 2009 11:08 AM

  • Different Document types under one company code

    Hi All,
    I am working on a project where i have to implement SAP PS in 3 Company codes.
    I have a requirement that Different number ranges should be used in different codes for creating PRs.
    In OPTT,order category 20 is used with NB,here i can change 1 Document type.Is it possible in std SAP to create different Order cat for 20 and then we can link diff document types for diff order cat of type 20.
    Regards
    Muzamil

    Hi,
    The assignment of the PR document type in Account assignment is only one is possible you cant assign multiple document type here.
    The Automatic PR raised from the PS is only one assignment is possible,so you can inform your MM consultant to create the seperate document type say ex ZNB-- PR for the Project which is common for all the three company code & assign this with the PR assignment in account assignmet filed.
    Regards,
    Raj

  • External processing in the plant as vendor under same company code

    Hi friends,
    In our project under implementation we have following scenario.
    we have 4 plants under one company code. one of the plant does powder coating as manufacturing activity. Other 3 plants sends components to the powder coating plant for coating purpose.
    In IDES Standard scenario of external processing, a purchase requisition is raised thro info record maintained for the external operation. This scenarion works if the vendor is external.
    In our case, the vendor is one of the other plant under same company code/client. Also the powder coating needs to be done without any profit margin for internal customers.
    Our FICO guys have the opinion that, intra plant can't be a vendor; because raising invoices among plants under the same company codes is against accounting standars.
    If anybody has faced this type of scenario nd found the solution, Please share it here.
    Thanx in advance

    Hi Shiva
    STO scenario
    You can not create only STO as you need to send the unpainted components to another plant through SAP & have them painted back with only payment of paining charges without margin.
    Subcontracting scenario
    You can not create the Subcontracting PO as this is not your external vendor.
    Does this involves excise?
    Then the PR/PO ctreated should be of combination of STO and subcontracting. If so this is not possible, as item category is the only field in PR/PO that identifies it as STO and subcontracting. obiviously it cann't have 2 values.
    My suggesion on this as...
    Create a BOM for painted component with sp procurement key as produced in another plant(paining plant). this will have STO cretaed for paining plant. This will inturn cretae a production order in painitng plant.
    The BOM in painting plant will have the unpainted component with sp procurement key as produced in another plant ( fabricated plant) this will have STO created for unpainted components.
    I hope I am clear & not confused you much.
    Regards
    Mahesh
    Regards
    Mahesh

  • Stock Transfer Plant to Plant under one company

    Hi All,
    While transfering Stock from one plant to other plant I wanted to add some freight cost or may be some discount to other plant to dispose of inventory under one company code.
    Problem is under one company no accounting document is getting created. And MAP of recieving plant should also be affected by this freight cost and discounts. I mean in case of freight cost MAP of recieving plant should go up. In case of Discount it should go down.
    How I can achieve this.
    Thanks
    Sanjay

    Hello,
    While I am doing STO for doc type UB and want to define condition following error is coming.
    Function not possible for this item
    Message no. 06096
    Diagnosis
    The function cannot be performed because either
    invoice receipts are not allowed for this item (that is, IR indicator = -), or
    conditions are not relevant to the item (e.g. in the case of contracts with the item category 'W'), or
    taxes have not been defined for the item (that is, the VAT code has not been maintained).
    Any more suggestion since I am not able to define freight condition in STO.
    Thanks
    Sanjay

  • How to Maintain the MM Master Data from one company code to other co code

    Hi Experts,
    Can any one pls tell me how to Maintain the MM Master Data from one company code to other co code.
    Presently we created New plants,New Purchase Orgs under different company code.
    1) Material Master data
    2) Vendor MAster data
    3) PIR
    4) Source List
    Is there any standard Transactions...??
    Please reply.
    Brgds,
    KK

    Hi
    Check out the link -
    http://wiki.sdn.sap.com/wiki/display/ABAP/StepstocreateasimpleLSMWusingbatchinput+recording
    lsmw for data migration for  xk01 transaction
    http://www.sap-img.com/general/lsmw-steps-for-data-migration.htm
    Regards
    Anand

  • Urgent: Maintain std cost for plants under different company codes

    Hi all,
    Company code(s)/Plant(s): C1/P1, C2/P2, ..., CnPn
    BOMs and Routings are maintained under P1. I believe that unlike BOM routing can't be made available across plants. So how does one maintain std cost across plants under different company codes?
    Thanks.

    Hi,
    You have to maintain individual BOM, Routing and varaint for all plants.
    Best Regards
    Ashish Jain

  • Plant to Plant STO with excise invoice and taxes in one company code

    Hi,
    I have a new business requirement, we want to create only one company code and 12 plants in different states,  each plant will have separate purchasing and sales activity this is ok this can be done with separate excise and series group as ther will not be any issue for purchsing and saling of materisl with exice in each plant , but how we can transfer the material plant to plant  if the plant is in different states we want that the material should be transfer from palnt to plant  with excise invoice only,  as we have the company code common,  how to create the billing document for this, and how to pass the duty from the saling plant and capture the same in the recieving plant. with proper tax entry. Can we do the STO with biiling if the two plants are in single compnay code.
    regards,
    zafar

    hi,
    I am trying to create a Stock Transport Order (STO) with document type UB and item category U. My objective is to transfer material from Plant (supplying plant) 100 to Plant (receiving plant) 1100 within one company code (1000) with STO.
    For this purpose I created a raw material 1434 in plant 1000 with sales org 1 view and in that view entered in delivering plant field 1000 as delivery plant. After that I extended material 1434 to plant 1100 without changing anything what I did while creating the material first in Plant 1000 except in organizational level I entered 1100 in the plant field. I entered Sales org 1000 and distribution channel 10 in organization level for both plant while creating and extending the material. In me21n I chose Stock Transport Order with document type UB and item category as U also receiving Plant as 1100. With this when I tried to save the STO the message, I am getting an error,  Cannot determine shipping data for the material 1434? 
    I am doing solely mm function why I need to create Customer master? In this case plant 1100 is the customer right? 
    Solution:
    1. Mat.(1434) should be maintained in both the plants. (1000&1100).
    2. Should have enough stock in supplying plant(1000).
    3. Make its supplying plant as a vendor in vendor master record in receiving plant(1100).
    4. Make it receiving plant as a customer in customization.  
        Create customer (xd01) & and define the shipping data for plants in both the plants.
        Path: spro u2013 img u2013 m.mgmt u2013 purchasing u2013 po u2013 set up STO u2013 define shipping data (1 by1 )
        In Receiving plant (1100)                         In Supplying plant (1000)
        Customer num.  123345 (for ex.)              Customer num.  -
    (don't fill) 
        Sales org.yyy                                                  
        Dist. Channel                                                              
        Sales div.  y   
    5. Assign doc. Type is "NL" for intra company STO. If  STO is inter company, Assign doc. Type is "NLCC".
        Position doc type is "UB"
        Enter supplying plant(1000) & doc type (NL) & checking rule (ex:01)
    6. Assign doc. Type is "UB" to u'r plants.(PO)
        Go for new entries 
        Enter supplying plant(1000) & Receiving plant (1100) & doc type (UB).
    7. Create a PO, choose the doc type is `UB' & item cat.'U', Enter supplying plant as a vendor in PO  of the receiving plant(1100).
    8. Provide this num (PO) to SD people, they will do the delivery by using transactional code is VL10B.
    9. Sales people they will provide "out bound delivery num".
    10. Do the GR. In GR the second tab 05 out bound delivery instead of PO mov.type 101.
    11. See the stock over view in the receiving & supplying plants.  
    thanking you

  • All plants Under specific company code

    Hi,
    What is the Tcode for All plants under Specific company Code.
    I Know about EC01 Navigation..
    But is there any other tcode available or not?
    Is there any table for all plants under company code?

    Go to SE11.. Give table name T001K..Execute... Give the company code in the field BURKS.. the result will give u all the plants under it....(WERKS is the field name for Plant)..
    Karthick

  • What is the configuration step assigen 2 plant to one company code

    hi all,
    i want assigen one code to 2 plants, what is configuration  step
    what is the special roll in chart of a/c, document number range,
    thanks in advance
    milind

    hi
    Milind Patil         
    You can assign no of plants to one company code .you can follow below navigation path
    --Enterprise Structure
    --Assignment
    --Logistics - General
    --Assign plant to company code
    Doubble click on assign plant to company code
    Enter following entries
    CO-CODE     -     PLANT
    1000             -     1000
    1000             -     1100
    AND SO ON----
    there is no extra settings in chart of accouts and document number ranges for assign morethan on plant to co code
    REGARDS
    TRINADHNAIDU.A

  • Reassign Plants from one company code to another company code

    Hi Gurus,
    We need to move plants from the current company code to a new company code. I know this is possible in configurartion, however, I not sure on what implications this may cause to the new company code. We are looking for a way to not creating new plants under the company code, and we believe reassign plants to the new company is the best way.
    Could you please let me know what might be the impact on this? on Finance? etc...
    Thanks in advance,
    Richard

    To me, it is something alarming!!!
    You are trying to assign the plants to new company codes after removing the assignment from the other company code. In my opinion you need to first consult a MM and a FI specialist and not a SD specialist.
    In the old assignment, there might be transactions done (for example goods movement, different material documents etc..). If you assign the plant to new company code, then how will you retrieve the old historical documents? I don't think even if you archive the documents,  you could retrieve after assigning the plant to new company code.
    I would suggest, think twice before you do anything/do enough testing in development system, or consult with MM/FI personnel or consult SAP before reassigning the plant.
    Regards,

  • PO for Plants belonging to different Country under same Company Code

    Hi,
    We have created a Company      1000 (Country u2013 India)
    We have created two Plants 1001 (Location - Delhi, India), 1002 (Location - United Kingdom).
    We have created a pricing Procedure      ZDOMES & ZIMPOR for Domestic & Imports Procurement.
    We have created a Tax Code V0, Country IN.
    We have tested the Procurement Cycle for Plant 1001 (Location - Delhi, India) and it is working fine.
    For Plant 1002 (Location - United Kingdom) what extra configuration do I need to do? Can we use the same pricing Procedure, Tax Code?
    Please advice.
    Regards,

    Thanks for the reply.
    Here in our scenario, we have created only one Company Code and one of our Branch is in UK.
    we need to create only One Company Code & Branches (Plants) in Delhi & UK
    Please suggest .
    Regards,

  • Is it possible to differentiate one payroll area with different currency under same company code

    Hi experts ,
    MY client wants to pay in yemen currency for the employees who working in yemen, but it was comes under same company code created for india.we have differentiated yemen under different payroll area wise . so is it possible to  differentiate one payroll area with different currency under same company code.
    thnx,
    vamshi keshavapatnam

    Hi Vamshi,
    I don't think so what you have done is correct. It seems like Global Employment functionality. As I understood you have some EEs which are Indian but working in company branch of Yeman.
    If this is the case you should define a new company code for Yeman branch and use Global Employment functionality. By this you can make decision to pay in home currency or traget country currency.
    Regards,
    Omid

Maybe you are looking for

  • How do I send a photo file without embedding it in the email??

    How do  I send a photo from iPhoto as an attachment vs. having it embedded in the  email?

  • 27" Imac Order date vs Manufactured date - unrecognized serial number

    I received my 27" Imac I3 ordered February 24, 2011 shipped next day Fedex on February 25, 2011. The Apple weight sticker is dated 9/22/2010! There is another weight sticker under it which I can not read and I don't want to peel off the top one. The

  • Firewire to Thunderbolt Adaptor

    Is the Firewire to Thunderbolt adaptor good for both Firewire 400 and Firewire 800?

  • Video very slow

    Hi: Anyone ...  I could use some help. When I click to start a video on my web site, it seems to take a long time to start playing. Is there some HTML coding I can use to pre-load the video (speeding it up). Thanks for HELP, Jake

  • Icons appear as question marks,

    it takes forever to open my mailbox (I have dsl) and a long time to send email with an attachment. Everything with my email (.mac) is very slow, and it wasn't always like this.