PM Maintenance Planning - Task Hours Required

Hello All,
Our airport is using PM for their maintenance planning.  We are currently building a new terminal and they are asking for a way to simulate/project the additional work hours that will be required for the additional equipment. We are only concerned with the maintenance hours required for tasks...not materials.
I've looked at IP19 but when I add the work hours/duration, the values are only populated for lines that have a work order created.  Is there another report/method we can use to make headcount requirement projections?...maybe a workcenter capacity report????
Any help is appreciated!
Thank you,
Allison
Note: PM is a newer module for me...background is more in SD, WM, FI/CO...so I'll take all the help you can provide!!

Sorry...I realize now that I posted in the wrong forum.  Reposted in EAM.

Similar Messages

  • Maintenance Plan task loging

    Hi all. I am creating a maintenance plan which may have mixture of T-SQL task and build-in task like reorg, rebuild tasks...
    I would like to log each task output to seperate files. Is it possible to do so ?

    Only by having different schedules for each task. That would give you several jobs and you can define an output file for each job. This is not, however, the same as the report file, which is the same for the whole plan. 
    If maint plans doesn't do what you want, then consider more powerful alternatives. I, for instance, use Ola's procedures at ola.hallengren.com.
    Tibor Karaszi, SQL Server MVP |
    web | blog

  • Maintenance Plan - Tasks are not executing in the order they were created

    I've created a new maintenance plan to perform differential backups but the tasks I created don't necessarily seem to execute in order all the time.  These are the tasks and order assigned when I created the plan using the Maintenance Plan Wizard:
    Back Up Database (Differential)
    Clean Up History
    Maintenance Clean Up Task
    Here's the deal...When it executes in the order they were created (above), all my old backups are deleted successfully.  However, there have been instances where, for example, the Maintenance Clean Up task executes before the
    Clean up History task.  When this happens, only one of my backup files is deleted successfully but not the second (I have two .bak files needing to be removed).  Furthermore, I noticed that the backup that wasn't deleted when it should
    have gets deleted at the next increment when new backups are created.
    Again, this does not happen when the tasks run in the sequence shown above.  Only one old backup gets deleted (instead of two) when one of the above item is out of sequence.  Strange behavior to say the least.
    Any feedback on this will be appreciated!

    If you do not set up precedence constraints it runs all tasks at the same time.
    Please see "8. To define a workflow between tasks:"
    http://msdn.microsoft.com/en-us/library/hh710041.aspx

  • Table name with feild Duration of Task/Frequency , Change in Duration/Frequency for maintenance plan

    hi experts,
    i need a table for maintenance plan which has field
    1) Duration of Task/Frequency
    2) Change in Duration/Frequency
    below i have elaborated my requirements.
    among those fields i have got the table name mpos,mpla,plpo except the above listed two feilds.
    i have to create a report with these requirements.
    anyone tell me in which table can i get that 6 and 7th fields.
    Requirement1:
    Maintenance Plan Number 
    Operation Code 
    Standard Teode(assigned to Plan)
    Standard Text Key description
    Cost Center
    Duration of Task/Frequency
    Change in Duration/Frequency
    Created Date
    Created By 
    Changed On 
    Changed By
    Requirement 2: layout of the report should be modifiable with the existing fields.
    Requirement 3: A transaction will be created to access the report.
    Requirement 4: In the report, Maintenance Plan number will be hyperlinked which will divert to AMP screen (display view of maintenance Plan) once clicked on it.
    Requirement 4: Report should contain all created and changed Maintenance Plan details.
    Requirement 5: Initial selection parameter for the report will be only Date. Based on the entered date, records created or changed during the duration should be picked up in the report.
    Requirement 6: Change in frequency will only be picked for single cycle plan. Strategic Plan will not be considered in case frequency change made in it.
    Requirement 7: Change By and Created By should be the complete name instead of User ID.
    regards,
    priya

    can anyone answer for my above question?
    regards,
    priya

  • Plant Maintenance - Linkage between Task List and Maintenance Plan

    Sir,
    In Plant Maintenance, I have an equipment for which there are 9 maintenance activities that have to be performed every year. Out of these 4 activities will be carried out every month. 1 activity will be carried out during the months of February, June and October. 5 activities will be carried out only in the month of December.
    I need to create Task List for all these activities and subsequently create Maintenance Plans for all these Task Lists.
    Can I group all the 4 activites which will be carried out every month into one single Task List, with separate operation nos and time against each activity?. I don't know whether it is correct or not.
    If I use the above method I can create 3 Task Lists for this particular equipment with same Group no and 3 Group Counters.
    How to create Maintenance Plan for the above scenario?.
    Eventhough, 4 activites are carried out every month and they have been grouped into a single Task List (Group counter 1) and if these activites are carried out on different dates within a month how can I create Maintenance Plan and subsequently create a Maintenance Order?.
    I need some help in this regard. A detailed reply will be helpful.
    Can anyone throw some light in this regard.
    Regards,
    R. Vijayakumar

    you need to create one task list with a maintenance strategy with packages and hierarchy to outline the work requirements i.e. some tasks to be carried out 3 monthly some 4 monthly etc, and also if common tasks appear in 3 monthly package vs 4 monthly package then to suppress the duplicating task
    you would then define a strategy based maintenance plan and run it to get the respective maintenance orders

  • Running Hours Base Maintenance Plan

    Hi,
    I have a scenario in which I need to create maintenance plan on running hours base. e.g. There is a generator which should be scheduled to plan according to 2000 running hours, 4K run hrs, 8K run hrs, 16K run hrs, ......
    Now the tasks which are used in 2K plan will be repeated in 4K plan. and so on. How can I configure it in PM.
    Kindly help, I shall be grateful to all.
    Best Regards,
    Ibne Khalil

    First you will create a measruing point/counter for calculting the running hours. Now create a task list with maintenance strategies 2k, 4k, 8 k etc. now define the operations in the task list. In the maintebnance package define whcih operations you want to define for whcih operation. Suppose for 2k running hors you need only operation number 10, so select the maintenance package 2k only for operation 10. For 4k running hours you want operation 10 and 20 , then in maintenance package , for operation 10 select select 2k, and 4k and for operation number 20 selecct package 4k. SO operation 10 will come for 2k maintenance and also for 4 k maintenace and operation number 20 will only come for 4k running hours. Hope it will solve your problem.

  • Making task list field mandatory in creation of maintenance plan?

    Dear All,
    I need your help in configuration of Making task list field mandatory in creation of maintenance plan. I checked with sceen variant config but that also not giving me any option to make the field mandatory.
    Is there any note or user exit for it?
    Regards,
    Kaushal Rai

    Dear,
    Pls check the exit IPRM0004:Maintenance plan / item: Customer check for time "SAVE".
    Regards
    Sunil

  • Total hours booked against a maintenance plan

    Hi,
    How can I check how many hours have been booked against each maintenance plan.
    Many thanks.

    Hi
    Many thanks for the answer it was very useful.
    I went into IW38 and entered the maintenance plan no. and found all the maintenance orders against it.
    Then i went into IW49 and put all the maintenance orders in it and it gave out the actual work booked against each order.

  • Strategy in task list and Strategy based Maintenance Plan

    Dear Gurus,
    I have some doubt about
    is it same if we create a single cycle plan with a task list in which maintenance strategy let say A is being used and a maintenance plan strategy based let say A and task list without any strategy
    can some one explain use of strategy in task list and maintenance plan
    Regards
    Armaan

    Hi,
         In Strategy Based Plans :- When ur entering strategy in initial screen of IP42 then inside the plan system will allow u to select tasklists created with that strategy only ...
    In Single Cycle Plans :-  Here even though if u select tasklist of a particular strategy , system copies all the operations of the tasklist to the order...
    From your above example :- Single Cycle Plan if cycle is monthly is equal to strategy based plan having only 1Month package .
    further package in strategy allows u to select which operations of tasklist u want for 1Month..
    regrds
    pushpa

  • Complation Requirement by Maintenance Plan

    Hi PM Experts,
    Can i set Completion Requirement  as a defaut by maintenance plan?
    Regards,
    Aktolga

    Hi ,
           Yes you can do via SHD0 transcation variant ..for IP41/IP42/IP43/IP02 tcodes ...
    pls check this forum for steps as it has been discussed many times ...
    regrds
    pushpa

  • Maintenance plan every 3 hours

    hi all,
    i need to configure a maintenance plan with ip41 but i need to make its cycle 3 hours, i mean 4 times a day, system warns me that smallest cycle can be 24 hours? what can i do?
    how can i configure system that creates maintenance notif every 3 hours?
    thanks

    Hii
    It is possible to plan a cycle more than once in a day. This can be catered by using Single Cycle Maintenance Plan.
    1. First make Measurement Counter ( with DAYS Characteristics ) with respect to any reference object and also make its measurement documents.
    2. Then goto single cycle plan. Select the cycle unit of  like 3 Hr and also select a counter of days in the same plan.
    3. Only if you select the Counter of days it will allow you to select a cycle less than 24 hr ok.
    4. Now you can schedule the plan and it ll generate the orders with the interval of 3 hrs.
    Hope that helps. For any further clarification feel free to contact.
    Regards
    BK

  • Maintenance plan search for no attached task list

    Hello Experts!
         I have tried searching for an answer to this to no avail. Is it possible to execute a search for maintenance plans that have no task list attached to them? I have tried IP15 thinking their would be a status to include or exclude but have had no luck. Any thoughts?
         Thank you all for any help!

    If suitable to you, you can get this information in scheduling overview from IP19  by
    1.Selecting Tabular radio button
    2. Giving Tasklist Type  field value = blank as under.
    Also try Tcode IP24 with point 2.

  • Preventive Maintenance Plan Material requirement forecast

    Is there any way I get to know what whether the materials included in Tasklist of maintenance plan are  available or not , Just like forecasting or material requirement planning.
    Regards,

    I dont think this is possible. You may have to extend the standard simulation program for scheduling to include the Components. You will also have to call the material availability check FM to analyse the demand for the required date.
    Even then there is no guarantee for material availability when the Order is actually called.
    Regards
    Narasimhan

  • Report on maintenance plan data

    Is there a way I can see the list of maintenance plans by operation, # of people required & hours required

    hi
    can you check IP19 ,execute with tabular ,with task list and change the layout to incorporate work.
    regards
    thyagarajan

  • Mass Maintenance of Maintenance Plans

    http://help.sap.com/erp2005_ehp_03/helpdata/EN/a1/5959394ba2cd4ae10000000a114084/frameset.htm
    Procedure
    If you want to change maintenance plans with the mass maintenance function, proceed as follows:
    1. Choose Logistics ®
    2. Plant Maintenance ® Planned Maintenance ® Maintenance Planning ® Maintenance Plans ® Mass Maintenance for Maint. Plans ® Mass Maintenance for Maint. Plans or use the transaction code mch01 and choose Enter. The Mass Changes for Maintenance Plans screen appears.
    3. Enter an appropriate variant name or your selection data in the areas of the screen called Maintenance plan selection, Maintenance item selection, Hierarchy or Work scheduling/task list data.
    Note
    If you want to make similar changes to data often, you can create a variant to ease data entry.
    4. Choose Execute.
    The Mass Maintenance: Table View screen appears.
    (The Mass Maintenance: Field View dialog box appears if you choose Execute field view from the Mass Changes for Maintenance Plans screen).
    5. Choose the appropriate tab page according to whether you want to make changes to the maintenance plans, maintenance cycles or the maintenance items.
    6. Select the objects that you want to change.
    You can select the fields that you want to change using the Select fields function.
    7. You can check your changes by using the Test changes function.
    8. Your changes are saved to the database when you choose Save.
    9. The system displays all the changes you have made and any errors that may have occurred in a log. You can save this log if you wish.
    Result
    Your changes have an immediate effect on all the selected objects.
    I have a need to enable this program which was delivered in one of the enhancement packs.  We have thousands of maintenance plans that need to be modified.
    A couple of questions:
    1) how do I activate as little as possible to allow me to use this program
    2) With this enhancement activated, am I going to be putting myself on a new support pack line.

    hi,
    I just know go to transaction SFW5 to check whether all components required for the operation of system are activated (switched on). But I do not know exactly which component is affected for this function.
    Hope it helps.

Maybe you are looking for

  • AppleTV not showing non-synced content since upgrade to iTunes 8.1.0.52

    Prior to upgrading to 8.1, my non-synced content showed on my AppleTV (when iTunes was open on my computer). Following the upgrade, the only content showing on the AppleTV is content that is synced to it. iTunes can see the AppleTV and I can sync con

  • Calling a Stored Procedure with JDBC Adapter ?

    I'm trying to call a Stored Procedure in my XI 3.0 JDBC adapter, but I get an "...invalid number of parameters...." error. Does anyone have an example of a Query SQL Statement and the corresponding Stored procedure? This is my test code. Eventually I

  • IC Webclient: Blank Page

    Hello Friends, In last days, for the first time, we are trying to launch a 2007 IC Webclient application in a machine with SP2. However, when we try to load it and after we choose the profile, we get a blank page. We searched and searched in this for

  • Displaying Chinese characters in SQL*Plus

    DB version: 11.2 OS Version : AIX 6.1 DB characterset:AL32UTF8 To display chinese characters in SQL*Plus, I did the following: $ export LANG=zh_CN.UTF-8 $ export LC_ALL=zh_CN.GB2312 $ export NLS_LANG="SIMPLIFIED CHINESE_CHINA.ZHS16GBK" $ $ sqlplus /

  • Why do you need a credit card # if the app is free

    I do not have a valid credit card that I can remember a password for. What can I do to download Firefox?