Hi All,
We use the account assignment category  M and while creating PO from a Sales order.
It used to hit a Balance sheet G/L account but for some reason/change it is hitting a P/L consumption account.
Can anyone let me know how i can check in the system what has been changed?
Any input would be helpful.
Thanks,
Meghna,

Sorry AKPT -
We have 2 g/l accounts example:
12345 - Balance sheet account
56789 - P/L account assigned to a cost center
in OBYC against GBB > VKA > Valuation class combination we always had this entry 56789 but
somehow when the PO was created we always saw 12345 under the account assignment tab.
Starting today all the POs have the g/l account 56789 and the cost center in the account
assignment tab.
We want to see 12345 in the PO under the account assignment tab.
Thanks for checking.
Meghna.

Similar Messages

  • GR/IR clearing account is being assigned to a acct assignment object

    Hi there!
    My key-user asked me a question which I really don't know how to answer.  He asked me about the reason why in an accounting document automatically generated by MIRO the item which contains the GR/IR clearing acct is always assigned to an acct assignment object (such as WBS element or cost center).
    I noticed that all the acct documents generated by MIRO has this mentioned assignment but, unfortunately I don't know why it happens yet.
    That's I count on you to help me solving this issue I'm facing now. 
    Thanks in advance,
    Rubens Luiz
    SAP SCM Consultant
    +55 21 2141 0033

    Hello there!
    A friend of mine told that it's not a problem at all. And that the reason that the cost object was assigned (or appeared) when you displayed FI accounting document is that since GR/IR Clearing Account is treated as the balance sheet account (I would assume it is the same in your system) and given the Profit Center was appearing in both P&L and Balance Sheet Account Report, SAP will have to use the cost object to derive the ultimate profit center. 
    Thanks in anyway!
    Rubens Luiz
    SCM Consultant

  • Error of Specify Chart-of-Dep.-Dependent Screen Layout/Acct Assignment

    HI
    My previous asset error was cleared by assigning non-tax  While  using the option of Specify Chart-of-Dep.-Dependent Screen Layout/Acct Assignment the following error is coming ..... Steps are attached (File and URL)
    http://rapidshare.com/files/135200425/asset_error.doc.html 
    pls help me ....
    Thanks & Regards,
    Kalai

    Hi,
    There are 2 set-up parts:
    General setting that is working for all depreciation area's
    Chart-of-Dep.-Dependent Screen Layout/Acct Assignment (Tcode: ANK1)
    When you have only 1 area it don't have sense to create Chart-of-Dep.-Dependent Screen Layout/Acct Assignment.
    For me  20 Chart-of-Dep are using the standard one and for 1 is using his own Chart-of-Dep.-Dependent Screen Layout/Acct Assignment   
    This is the reason for the errors

  • Problem in multiple acct. assignment

    Dear cons
        While creating a pur. Req. (T-code- me51n) with  Multiple acct.assignment (p). The system gives an error message that Multi acct. assgt. not allowed for ind. cust. req. or engineer-to-order
    Message no. 06268
    Diagnosis
    Multiple account assignment is not defined for items with account assignment to "individual customer requirement" or "manufacture for individual project" (engineer-to-order).
    This means that you can only enter one account assignment item in the case of individual customer requirement or engineer-to-order. Pl. give me in details where can I MAKE SETTING SO THAT I CAN DO THE MULTIPLE ACCT. ASSIGNMENT.

    Hi,
    Please follow as shown below
    SPRO>MM>Purchasing>Account Assignment>Maintain Account Assignment Categories
    here select your industry sector and click Details on top  and in the field ID: AcctAssgt Scrn you can choose multiple account.
    Reward points if useful.
    Thx
    Raju

  • Acct assignment cat. of item not in user data; Inform system admin

    Hi all,
    We are on a SRM EBP 5.0 project and we are getting the following error when we try to create a purchase order from the purchasers login.
    "Acct assignment cat. of item not in user data; Inform system admin"
    The complete details of the screen shot are as follows:
    The following error text was processed in the system DS1 : Acct assignment cat. of item not in user data; Inform system admin.
    The error occurred on the application server lndnysap1_DS1_01 and in the work process 0 .
    The termination type was: TH_RES_FREE
    The ABAP call stack was:
    Form: ABORT_PO of program SAPLBBP_PO_UI_ITS
    Form: ADD_TO_MSG_LOG of program SAPLBBP_PO_UI_ITS
    Form: ADD_TO_MSG_LOG_MULTI of program SAPLBBP_PO_UI_ITS
    Form: SET_PRICING of program SAPLBBP_PO_UI_ITS
    Form: DETERMINE_EXTERNAL_SCREEN of program SAPLBBP_PO_UI_ITS
    Module: DETERMINE_EXTERNAL_SCREEN of program SAPLBBP_PO_UI_ITS
    We did the following steps :
    Created shopping cart- employer and WF triggered apprd. by manager.
    Purchaser did "Carry Out Sourcing ", and if we say "Create Purchase Order", the PO gets created with a information message that "Incomplete purchase order 11/1 is created "
    When we go to  "Process Purchase Order" for the completion of the same. If we see Follow-on documents "Purchase Order Held" occurs.
    In the tab Item Data details Pricing tab we get this error.
    Do any of the SRM gurus can suggest us what to do?
    In our admin logon it shows
    "Server for pricing is not running. Start Server"  occurs after every run of this process purchase order from the purchasers login, though our IPC is working fine.
    Will be of great help if somebody replies soon.
    Sincerely,
    Sridhar.

    Hi,
    IPC has to be configured.
    Please check the following threads :
    https://forums.sdn.sap.com/click.jspa?searchID=211089&messageID=2714527
    https://forums.sdn.sap.com/click.jspa?searchID=211089&messageID=2715019
    Kind regards,
    Yann

  • Acct Assignment Cat."P" of PR in ECC cann't be brought to EBP

    Dear everyone.
        when I create  PR with "P" of Acct Assignment Cat. in ECC, PR is transfered to EBP as shopping cart. but I found the Acct Assignment Cat. is "CC" ,not "WBS", this is not normal.
        Because in SRM IMG. the "CC" mapping to "K" ;the "WBS" mapping to "P" ; the "AS" mapping to "A".
        Addintional, if I create PR with "K" or "A", then related shopping car's Acct Assignment Cat. is "CC" or "AS", it is right.
        I have a test, I inactived "CC"mapping to "K", and make "WBS" mapping to "K",  while I creat the PR with "K" , PR cann't be transfered to EBP. the error message is "Account assignment category CC does not exist. Check entries"
        Why, doesn't the "cc" be fixed?
        Please help me ,it is urgent.I will reward for this.
    Jesse.

    Jesse,
    If I read you problem right, the problem is that inactivated 'CC' in EBP. How's that configuration done in ECC?  We are not using ECC at this time but it looks like you need to synchronize the account assignment configuration between the two systems.
    Just my 2-cents, I hope that the fix is that easy.
    Regards, Dean.

  • St. loc. for Acct Assignment category K

    Hi Team,
    We have come across strange scenario while creating PO for Acct assignment categoty "K".
    As we know, when we are using "K" means procuring material for Cost centre (free text mtrl). For this type NO st. Loc is required as material will be directly treated as consumed when you made GR.
    But in system, Storage location field is automatically getting filled after filling up the Line item information.
    Anyone aware of any settings where I can check why this is happening????
    Regards
    Sonia

    Hello Sonia,
    First of all, can i know if the Sto.loc can be remove after it is been filled automatically. {Guessing some userexit behind}
    Additional, you may also check if the setting for Acct.Assignment K is ticked for Good Receipt, if yes, this item line will required for Good receipt thus the Stor.Loc will be required too. But this Good receipt setting won't impact to the automated filled of Stor.Loc.
    If you really have no clue what is the problem why stor. loc is been filled automatically, then just go into debugger mode to check if any userexit there?
    Thanks and Regards
    Chee Wee

  • PO creation with acct assignment "A"

    Hi
    I created 2 internal order types - one for IOs for expenses and another one for IOs for assets.
    When I create a purchase order with acct assignment "O", the system correctly checks the IO available budget.  But when I create a purchase order with acct assignment "A", the system does not require the IO when it should.  And even when I did place an IO number, the PO amount is not being reflected as commitment in the IO report.  Please advise on how what should be done.
    Regards,
    Thess

    Hi,
    Even if u make mandatory the io number in PO.
    You cannot settle the asssts to that IO and budget control also not possible.
    Thanks

  • Acct assignment to be restricted based on Doc type

    Dear All
    I need to restrict Account assignments based on Document types,
    As of my knowledge there is not standard customizing possible.
    But i can restrict Acct assignment based on Item catregory. But this settings doesn't satisfy my requirement,
    I would like to know is there any standard customizing or any user exit availble .
    Kindly let me know
    Thanks & regards
    Madhesh Kumar

    hi,
    there is no sap standard  customising for this please go ahead with user exit in PO.
    create an doc type.
    when you select the perticular doc type system should take default account assignment.
    regards

  • Acct Assignment

    Hi,
    I have a problem while creating a PO, when i type material and other line item data and try to save it ,system asks for GL account and cost center from Acct Assignment tab.But this only for some items aand for some other items it wont prompt for CC.Why is it so ?
    Regards,
    Nandakishore

    Hi,
    I thing for every material belongs to some one GENERAL LEDGER ACCOUNTING NUMBER  and COST CENTER. So please check whether that material is created or not afterthat when those materials are created  by particular peoples know whether they had maintained G/L acct no or not?
    Thanks,
    Shankar

  • Acct assignment in customer Master

    Dear All ,
    We have Abc customer for which we have normal acct assignment grp : 01 for normal revenues. in customer master.
    but some times, we have to make invoice for labour revenues as well for the same customer .
    Then how to handle these two acct assignment grp for same Customer .
    Or we suppose to create two customer master for the same?
    Pl guide

    Hi
    but some times, we have to make invoice for labour revenues as well for the same customer
    This means for the same customer according to invoice GL account has to be different
    No need to change the records of the master and it is not advisable to change the master also
    Account assignment group is a modifiable field in billing doc creation for both customer and material
    So during the invoice creation itself you can change the Account assignment group which has come from CMR and take an another one and make it flew to another GL account by maintaining the relevant VKOA settings
    Solution is readily available in standard itself
    Regards
    Raja

  • PO (Acct assignment category)

    Dear Friends,
    In an attempt to avoid any mistakes by user (esp when creating PO for assets), i made the "acct assignment category" field mandatory in PO creation.
    Now for buying regular raw materials, i needed to enter something in that field, hence i used "U" - "Unknown"
    it gives error - Unknown account assignment not defined for use here
    where can i define this in SPRO?
    or is there any other alternative to my problem? creating a spcl doc type for asset does not seem to solve the problem.
    Thanks a lot
    Sanjay

    Hi,
    In the Field selection column, give any unique 3 digit key like  ZAC for your document type.
    Execute DEFINE SCREEN LAYOUT AT DOCUMENT LAVEL under Purchase order customization settings.
    system will display all the filed selection keys.
    Select your field selection key like ZAC and click on the Basic data, item ( Very first one)
    In that maintain Account assignment category field as mandatory
    Regards
    KRK

  • Query on acct. assignment category & availability check.

    Dear Friends,
    Can somebody tell me the significance of acct. assignment category, and meaning of  availaility check in material master.
    Secondly I have a material which I use as raw material in one plant and i do the trading of the same material in other plant, in such scenario what should be my acct. assignment category,as the acct. assignment category is dependent on sales organisation.
    Thanking you in advance.

    Material can be purchased with reference to Account Assignment Category or with out ref to Account Assignment Category.
    That all depands upon business requirement,if you wants to keep the material in inventory you can cretae PO for that material without Account Assignment Category
    and if you don't wants to keep the material in inventory you can cretae PO for that material with Account Assignment Category.in this case materail will consumed at the time of GR itself.
    When you procure Indirect or Non-stock material you need to maintain the account assignment category for which the cost of purchase will be incurred.
    For example when you select , Acct assn. cat "k" ( Cost center) you have to enter the COST CENTER and the G/L account number. In this case when you receive the material it will get consumed.
    SAP PO can have account assignment categories like
    Asset - A
    Cost center- K
    Order - F
    Project - P etc.
    Account Assignment Category: - A key indicating whether an item is to be assigned to an auxiliary account (such as a cost center).
    The account assignment category determines which account assignment details are required for the item (for example, cost center or account number).
    Generally used Account Assignment Categories are Cost Center (K) in case of Miscellaneous Purchases, Assets (A) in Capital Goods Purchases, etc...
    You can configure Account Assignment Category in Transaction OME9 OR you can go with following path;
    SPRO > MM > Purchasing > Account Assignment > Maintain Account Assignment Categories

  • Acct assignment po's to cost center

    Hello friends
    i need to know if a PO that is acct assigned to costcenter and there is no material master on the po it is only text item. will i be able to do three way compariosn for invoice verification. also please tell me if we can do gr for the text line item on the po.
    Regards

    hi,
    Yes you can do Gr for the PO...
    but the difference will be this that instead of stock account the posting will be for the consumption accountie. to the defined Valuation class for the Cost centre...
    When you do Gr the posting will be :
    GR/IR Consumption account - Credit
    Vendor account - Debit
    Atthe MIRO ie. at IR:
    GR/IR : Debit
    Vendor account - Credit...
    Hope it helps...
    Regards
    Priyanka.P

  • Req and PO Make Order Mandatory Based on Acct Assignement Catagory

    Is there a way to make the field order on the account assignment tab mandatory based upon which account assignment catagory is selected?  For account assignment catagory "F" we need order mandatory all others not mandatory.
    Thanks

    Hi,
    Check following path:
    SPRO>MM>Purchasing>Account assignment>Maintain acct assignment catg>
    Select F and go to details.
    Change field label CO/PP order from optional to mandatory entry.
    Regards,
    Pratap

  • Level One WBS Element as Acct Assignment Element

    Dear Friend's
    My user have created one project, In that there are various levels WBS Elements.
    Normally we never tick Level One WBS Element as a Acct Assignment Element.But User have made Level One WBS Element as Acct Assg Element and then Project is Released.So now I can't remove that tick because that field is Grayed out or Freezed.
    Now i wanted to Remove or Undo Release status and then I have to remove Acct Assg Element Tick.
    Pls guide me on this issue.
    Thanks in Advance.
    Regards,
    Sandeep N.Theurkar

    Hello,
             I had not seen this problem before. So i checked it in my system. But i didn't see this
    happening for me.
             I think once system status is in REL (released) status you cannot reverse it. According to me Acct.
    assignment field become gray only when posting is made against that WBS and not after release.
    Pls check it and inform.
    Regards,
    Ashish Kulkarni