PO creation from One Purchase Requisition

Dear all;
In standard SAP We can create multiple PO from A single PReq ,though the full quantity of PReq is taken first time of PO creation .Is there any restriction that After full use PReq quantity no one can use the same PReq for further PO creation.
Thanking You;
Regards;
Joydeep Mukherjee

Dear Joydeep,
In contrast to a purchase requisition, it is possible to create more than one PO in reference to a RFQ.
A RFQ only gives information about the price for which can be ordered from a vendor. The system does therefore not reject you from ordering again from the same vendor with the best conditions.
Once you create a PO with reference to an RFQ, if the quantity in PR to which the RFQ is refering is exhausted,
the user is prevented from creating further PO only with reference to the PR. But the user can create Purchase orders refering to a RFQ as long as the validity period of the RFQ is still valid.
Regards,
ian, Wong Loke Foong

Similar Messages

  • Two purchase orders from one purchase requisition

    Hi experts,
    i'm getting this strange behavior. How is possible to create 2 purchase orders from one purchase requisition ??
    If i look to sales order flow i see two purchase orders.
    Thank you.

    Hello Dan M,
    When u enter the material and qty in Item the system might be doing Availability check. Then u might be going to schedule line and then "check mark on "Fix qty/date". Here once again the system might be doing Availability check and then u press  "Dely proposal".
    I suggest u to check the Purchase Requisition Item No. (the field next to Purchase Requisition No.). Keep watch here after every step u perform. Watch before and after u press every button.
    Do carefully analysis step by step u will get the reason.
    Any thing required write on the forum.
    Thanks & regards,
    Shailendra Panhale

  • Purchase Order creation from closed Purchase Requisition

    Hi all,
    Please kindly help with the following questions
    1) Is it possible to lock a purchase requisition such that after a purchase order has been created, another purchase order would not be created from that purchase requisition
    2) also is it possible to assign a fixed vendor to a purchase requisition without an info record.
    Thank You.

    Hi,
    set the two message 06076 & 06400 as error so that no  more purchase order can be created with
    reference to the purchase requisition.
    And also refer the note 385002 for more information.....
    You can fix a source in source determination in source list thriugh ME11 not in info record.

  • One Purchase Contract from Several Purchase Requisitions

    Hi Experts,
    I have a problem, I want to make one purchase contract from several purchase requisitions. Here, some of PR's are of same material and some PR belong to different material. What we want that same Material should be clubbed together in one line and diffrenent material code should come in diffrent line.
    Regards
    GR

    Gi,
    if you are creating the contract manually and still want to see the PRs used.
    then i suggest you to maintain the detauils in the texts which are not used for printing and could be used for information purpose.
    one thing that this is manualy created so PR in system will not show the assigned and will remain open.
    regards,
    Adwait Bachuwar

  • FM or BAPI for  date and time for the creation of a Purchase Requisition

    Hi people:
    Does anybody knows about a FM, BAPI or table in which i have de detail for the date and hour of the creation of a Purchase requisition?
    Points for helpfull answers.
    Thanks in advanced

    Hi,
    If you want to get the time along with the creation date then use the tables CDHDR and CDPOS, but be careful while passing the data need to pass the entire primary fields data else it will fail in the performance test.
    Reward points if useful.
    Regards,
    Suman

  • During automatic creation of the purchase requisition to operation 0010

    Hi,
    Problem occurs in automatic cration of PR.
    Error : During automatic creation of the purchase requisition to operation 0010, an error (06 532) occurred:message c2325
    Regards,
    Vivek

    Hi ,
    I am getting error in CO01 Transaction.
    Message no. C2325
    For further proceedings, read the long text of error message (06 532) in transaction SE91. Check the operation affected and change or complete any missing data that led to the error message.
    Regards,
    Vivek Nehete

  • Automatic PO creation from Imported Approved Requisition

    Hi,
    Is there any setup to allow automatic PO creation from Imported Approved Requisition.
    1. Run Requisition Import to import approved Requisition with no workflow fired.
    2. Can we kick off automatic PO creation workflow without kicking off Requisition approval workflow?
    Any suggestion will be helpful.

    Hi,
    pl.review the MOS doc.
    How to Create and Approve a Standard PO Automatically From an Approved Requisition Sourced to Standard Quotations [ID 308470.1]
    HTH
    Sanjay

  • One Purchase Requisition for One Maintenance Order

    Dear Consultants,
    We have implemented mySAP ECC 6.0.   We have more than 20 line items in one Maintenance order for  Item category N. Curently system is generating Purchase requisitions by line itemwise for Item category N(Non-stock items). Our client requires only one purchase requisition for every Maintenance Order. Is it possible to generate one PR for one Maintenance Order? If possible please give us the solution.
    Thanks,
    Dev

    Dear Pete Atkin,
    With your help my issue has been resolved. Thank you very much.
    With Best Regards,
    Dev

  • Locating Planned order from a  purchase requisition

    Hi Gurus ,
    A purchase requisition has been created manually , by converting a planned order . Is it possible to find out the planned order , from a purchase requisition   Pls advise.

    Hi
    Once planned order converted in to Production order or Purchase requisition, we can't see any details of the planned order.Planned orders are stored dynamically in tables.once it is  coverted,Details can not be seen even in PLAF-Plan order table.
    In production order, you can see the planned order number but for PR , it is difficult to get the reference Plan order number.
    Regards
    Ramakrishna

  • Plan only releases one purchase requisition at the time

    has anyone seen this scenario? When the planner checks multiple purchase requisitions for release and then, when he attempts to release them, the dialog box shows that only one req got released?

    That is unusual.
    Has the planner saved the earlier records after checking the for release box? Was there any error/warning message?
    Have you checked on the Source side if 1 or more reqs. got created?
    Is it possible that the other records were Internal reqs or wip jobs?
    Sandeep Gandhi

  • Click a line in query created from SQ01 - Purchase requisition.

    Hi all,
    my problem is: Tcode SQ01, i've created a query where query's fields are:
    purchase order,
    purchase requisition,
    maintenance order.
    In change query phase, menu Goto --> Report assignment
    i've choosed two standard Tcode:
    IW32
    ME53N
    so that when i click a line of my query and chose iw32 i really can change the order clicked on my query but when i choose ME53n i can only display the last purchase requisition displayed e not that I really clicked on my query!
    So, how can i display the purchase requisition clicked on my query?
    Are there someone help me?
    Thanks a lots,
    Alex.

    Hi Phyllis,
    I face the same problem that Alessandro and I've changed the report assignment to the old transaction ME53. Unfortunately, when I click in the purchase requisition the new ME53N is called instead of ME53.
    Do you have any idea why is this happening?
    Thanks in advance for any help.
    Regards,
    Sara

  • SAp Inbox entries for each one Purchase Requisition Position.

    hi everybody,
    I made a workflow for a general release of a Purchase Request.
    When I asked for a request in my inbox appear as many entries as my position has ordered. I just need you to see one, because I need releas a document and not by position.
    Im using a user decision task.
    Can someone help me.
    Best Regards.

    Hi,
    the reason for multiple workitem in my inbox is because
    I used BUS2009.
    The workflow mapped to BO BUS2009 you dont want right, so deactivate the workflow.
    Now Im using BUS2105... but I have a new problem... the ReleaseStepCreated
    event not trigger my Workflow, in the SWEC set BANF document
    with BUS2105 and my WF... to create.
    PR your creating in ME51N right,  'ReleaseStepCreated' is the std. event it will trigger by default in swel once you create the PR.
    For picking the approver you can use, User Exit or from Table Entries.
    WS20000077 --> is the std. workflow for PR.
    Regards,
    Surjith

  • Creation of Single Purchase Requisition.

    Hi ,
    After creation of Multiple Planned order through MRP run with  MD02, can we convert all Multiple Planned order with External Procurement type to a Single purchase requisiton??????
    Pl. give your valuable  suggestion .........
    regards,
    YK

    Hi,
    Re: MRP PR creation control
    Regards,
    Pardeep Malik

  • Unable to create multiple Purchase order base on One Purchase requisition

    Dear All,
    I have problem to create multiple POs base on one PR.
    For example, PR is automatically created after a Sales order which contain 10 pec of Material A. A PO is created for 4 pec of Material A first which is no problem, but when it come to create second PO for the remaining 6 pec, the system respond with a error message. "Materials for PReq 10167146, item 00010, already partially ordered, Message no. 06 249"
    I have searched for the SAP Note to solve this problem, the Note number is 202011, to solve the problem I need to import
    SAPKB46B03 and SAPKB46B04 for my 4.6B system. However those two package had already installed into the system long time ago, and the problem is still not solved. The currect level of PS is SAPKB46B57. And I was advised not to re-import the PS (SAPKB46B03 and SAPKB46B04) again.
    Could anyone please tell me is there any other solution to get around this problem.
    Thanks for your time
    Alvin

    Hi
    Thank you very much for your quick response.
    As the same user is able to process the idocs of message type PORDCR which are in status 64 successfully previously.
    Regards,
    Phani Miriyala.

  • Purchase requisition creation (STO) from Sales order

    Hi Gurus,
    Read the following scenario:
    Sales order is created with delivery plant A. No stock on plant A.
    Purchase requisition is created from plant B to plant A (intra-company flow or stock transfer order).
    Problem is that the purchase requisition needs a price. It is not logical because intra-company flow (stock transfer in same company flow) is like a stock transfer without purchasing. So in my mind, I don't have to maintain price.
    Also if I use ME27 to create manually STO between both plants, price is not asked.
    Other question is: is it possible to create directly a purchase order when sales order creation (and not purchase requisition, newt convert into PO)?
    Many thanks.
    Stéphane

    Hi Stéphane Vituret, Did you manage to find a solution for this. I have a similar problem as well.
    Please find the scenario below.
    Cusotmer places order of Mat-XX to Company A. The Company A creates PO to Company B. Company B delivers to Company A and then invoices Company A. Company A receives the goods into own stocks. Now the Company A delivers to the customer from its own stocks and then invoices Customer.
    I decide to go ahead with the Individual Purchase order solution and since the Company A is buying from Comapny B, I decided to integrate the Cross Company STO flow in the procurement part. Hence the flow in SAP is like;
    Cusotmer placese order to Company A
    Comapny A creates a Individual Purchase order type Sales order. So the Item category is TAB.
    This sales order generates a PR. PR is conveted into a CC_STO as thenvendor is Plant B in this case . Now this STO appears in the delivery due list of plant B.
    Now I genreate the delivery to move stocks from plant B(of co.cd B) to Plant A(of co.cd A).
    Here is the problem. I am not able to do PGI as the system checks for "sales order" stock at plant B and throws error
    "Sales order stock 36637 000010 does not exist". This should not be the case as the stocks should get attached to the sales order only when recieved into Plant A. Hence system should not check for "sales order stock" at plantB while trying to deliver from Plant B to Plant A.
    Lets take a normal IPO scenario.
    CusotmerA places order of Mat-A to Company A. This sales order generates a PR. The Company A converts the PR into a std.PO to external vendor. The PO from the sales order will have a account assignment "M- Ind. cust. w/o KD-CO". The stocks will be received into Plant with spl indicator "E" while GR (MIGO). Now the system ensures that this stock can only be delivered against the particular sales order. Thus the stock procured for the customerA is delivered to customerA and not consumed by anybody else. In this case there is only one delivery involved, in SAP, which is 601 mvmt type from the Plant A.
    However if the vendor becomes another Plant (Plant B) belonging to another company code then there are two deliveries involved in the SAP system one with mvmt type 643, from Plant B to Pant A, and the second with 601 from Plant A to the customer. Hence the system should check if the stocks are attached with a spl indicator only during the second delivery of 601 mvmt type. I am facing a problem because the system does it for the first delivery itself. If you know the answer please do let me know. I really appreciate it. Thanks a lot in advance.