PO Error in Transfer for Direct Procurment

Hi All,
we are running SRM 550 and are at SP15.
We need to get SRM to order Direct Materials for a storage location in our ECC system.
So far all the config has been done,  materials transferred, storage locations defined in Org structure extended attributes.
Problem is when I create a PO from a SC for direct materials I get an Error in Transfer and the error in RZ20 says that the account assignment is not valid for the ECC PO doc type.
This all used to work in 2008 when we went live wih SRM but direct procurment was switched off because the business did not need it.
In PPB_PD for the PO there is no account assignment data so I think this is where I have a problem.
I must be missing some small piece of config somewhere that provides the account assignment GL for direct procurment but I can't find it.
Any suggestions would be welcome.
Thanks in advance
Allen

Hi Allen,
Please create wildcard entries for AccAssCat in IMG  table               
V_BBP_DET_ACCT, details see encl. file V_BBP_DET_ACCT.DOC                                                
The issue is that even for subtype DP Direct Procurement Account         
Assignment Category must exist, otherwise PO cannot be transferred       
Accounting is going to be eliminiated one step later after ordering,     
in background task, not visible to the user. Please realize!
I have uploaded V_BBP_DET_ACCT.DOC to SAPMATS, click on the following link.                                               
Link: [https://sapmats-de.sap-ag.de/download/download.cgi?id=LL0BCK4LD9DE7XZOG9M7WGGNG11AWE43UCBMUW1T05TKD1IOK2]
Hope this helps,
Kind Regards,
Matthew

Similar Messages

  • Rounding value for direct procurement

    Hi,
    I an sourcing the same material from another plant within the same client. The materiale is some times purchased as a standard material using rounding value and going to stock. But, in some cases the material is procured as direct procurement. When purchasing for direct procurement will it then be possible not to use the rounding value but just order the exact quantity?
    thanks,
    Anders

    Hi Andres,
    I think, you do not need to take any action on this requirement.  SAP works the way you wanted, by standard.  For example, you have a setup with a vendor (may be via info record or material master itself may have rounding qty etc)...not a problem.  The parameters you use in material master will control for procurement process either triggered from planning (or production ) or manual purchases.  When you create a SO# and if it triggers a purchase requisition, it sends exact quantity required only, into the preqs.  By standard SAP config, the message about rounding rules is just warning.  I don't think you will be stuck with this message when you try to convert the 3rd party Preq to PO.  Even if there is a message, it must just warning. 
    Let me know with these inputs, if you test both types of PO#s, how it goes.
    Regards

  • Error in BP for External Procurement

    Hi together,
    I've set up the BP for External Procurement 60.2 as described in the manual. From all pages only the iViews "Overview-Purchasing" and the iView Vendor Confirmations on the Overview works without error. The other iViews wouldn't displayed (Page cannot displayed).
    I'm using EP 6.0 SP13 and ECC 5.0. The BSP's are activated in SICF.
    If I test the iView i got in the default trace the error "java.lang.NumberFormatException: For input string: "10985373858"". I haven't any idea, from which point this number will come.
    Have anybody experince with this package?
    Regards Thomas

    Hi Olaf,
    please see Java-iViews-Errors in BP for CRM and CRMContextException (here especially Michael Healey's reply).
    Hope it helps,
    Detlev

  • Direct Procurement in Classic Scenario

    Hi Experts,
    We are on SRM 7 Ehp1, ECC 6 Ehp4.
    Classic Scenario.
    1. I have read in the forums , that in Classic Scenario, direct procurement is possible but the system behaves like Extended Classic and creates a Local PO. Just want to confirm this and if yes , does this happen as a standard or do we need to implement any BADI or anything to achieve this.
    2. Also , in Classic Scenario, PDP scenario , can we transfer stock items(Direct Materials) PR's into SRM system or are there any limitations.
    Thanks
    Aditya

    Hi Aditya,
    You are right. Classic system behaves as extended classic for Direct procurement scenario. Your PO will be created in SRM itself and a copy of this will be sent to ECC. This happens as a standard and no BADIs need to be implemented for this.
    Also in your classic system, you can transfer stock PRs into SRM. These will be available as shopping carts in the sourcing cockpit.
    Regards,
    Nikhil

  • Puchasing Org Error with Order as Direct Material

    Hello Experts,
                           We are running SRM 4.0 and Classic Scenario from last 6 months.  Now I have been requested to configure for Direct procurement. 
    We have one Purchase Org which is a backend purchase Org.  The plants for PORG is also maintained. 
    We have also defined the backend Purchase groups.  All of the groups have product category responsibilities defined.  The functional tab has the backend purchase group and the backend system defined. 
    In order to use Direct Procurement in Classic Scenario what configurations are required?  When I click Order as Direct Material I am getting the below Error.  Please advice .
    System LSYSED1400( SRM system) of purchasing organization O 50000004 differs from target system LSYSED1400  (Item  BrixWorx Engine for Sun Solaris (with em )
    -thanks in advance

    Hi Shilpa,
    are you trying to create classic PO for Direct Material?
    In SRM it is possible to create a classic PO for Direct Material, as this is only possible using the Extended Classic Scenario. In a classic scenario, SRM expects to create all PO docs in the backend (pointing to logical backend system). For Direct Material the logical system is set to SRM. That's the reason for the error message "... Differing System ...".
    With the settings local PO, local POrg, local PGroup etc. you are able to process and issue a local PO in SRM for Direct Material, but there is no linkage to the backend. One option to consider is a decoupled scenario - extended for Direct Material, classic for all other.
    Thanks,
    Claudia

  • Direct procurement in Classic

    Experts,
    Need your help once again.
    I have implemented direct procurement in Classic scenario (SRM 7/ECC 6.0) and after reading on this forum, I realised that Direct procurement in classic, functions as extended classic because a local PO is created in SRM and this is replicated to ECC. So far this is working for me.
    Now I want to make changes to this PO. It is not allowing me to edit PO in ECC which is right because PO was created in SRM and copied to ECC. But strangely, I am unable to edit PO in SRM also?
    Is this correct behaviour?
    Please suggest.
    Best Regards,
    John

    Hi John,
    For direct procurement, it will have nothing to do with CS or ECS.
    SRM will create the local PO for direct material and transfer the PO into ERP.  And you could not change the PO in ERP.
    Regards,
    Guoyu

  • Direct Procurement to own stock

    Hi,
    I have a material which has been directly procured to a production order. The production order is no longer valid and the material has to be transferred to own stock.
    How can I do that? Which movement type do I use?
    Please help me out with this issue.
    Sincerely,
    Puja

    Hi Rahim,
    I do not see an option in movement type 411 to transfer from direct procurement (production order) to own stock.
    These are the following options that I see for movement 411
    411          Transfer posting storage location (one-step)
    411     E     Transfer posting sales order to own
    411     K     Transfer posting consignment to own
    411     Q     Transfer posting project to own
    Can you please let me know how can I do it using movement 411?
    Thanks,
    Puja

  • Direct procurement always as extended classic -- why ?

    Hi ,
    As per SAP's specification , ' SRM Server is the leading server for direct procurement. This means the system behaves according to extended classic scenario' .
    Is there any specific reason on why the scenario would always be extended classic for direct procurement ?
    And does this also imply that in a classic scenario, if a SC is created for a direct material which refers to backend material , the PO created would be in accord with the extended classic scenario ?
    Reasons/Answers --- Anyone ?
    thanks-
    Harmeet.

    Hi Harmeet
    Yes, even in classic scenario, if a SC is created for a direct material which refers to backend material , the PO created will be in accordance with the extended classic scenario by default i.e. a local SRM PO would be created which will be replicated to ECC. However you can alter this behaviour and force the system to create a PO in ECC (like classic scenario) by implementing BADIs.
    Regards,
    Nikhil

  • Direct Procurement and Direct Production

    Dear all,
    Can you please explain to me what is "Direct Procurement", and "Direct Production" base on the following points:
    1 - What is the process about?
    2 - How and when business requirement will bump into and using these two processes?
    3 - Example
    Please don't copy and paste the SAP help portal explanation as I have read the SAP help-portal and am NOT understand
    thanks very much
    tuffy

    Dear Tuffy,
    Direct Production:
    1.The components for which individual production orders are created in a collective order concept are called as directly
    produced component.
    2.In my understanding these components are identified with the value 52 set for special procurement key in MRP2 view of the
    material master.
    3.Direct production cannot be set for the components that have any one of the indicator set for - by product, co-
    product,alternative item with usage probablity 0 or alternative item with strategy 2,discontinued material,follow up material,intra
    material.
    4.This concept atleast helps in understanding the cost breakup than the phantom assembly concept.
    5. Example:
    You want to produce a pump. The BOM for the pump contains a pressure regulating valve and a spiral casing. You want to
    enter these two components in separate production orders, but you do not want them to be posted to stock.
    You set the special procurement type to direct production in the material master record for the pressure regulating valve and
    the spiral casing, so that production occurs using a collective order.
    When you create a production order for the pump, a collective order is automatically created, which contains subordinate
    production orders for the pressure regulating valve and the spiral casing.
    Direct Procurement:__
    1.Direct Procurement is generally used for non-stock items that is defined with item category N or defined using special
    procurement key for direct procurement.
    2.This is widely used in the case of Make ot order or Engineer to Order production where the stock of such materials are not
    inventory managed.
    Regards
    S Mangalraj

  • Error while executing Initialize with Data Transfer for 0FI_GL_10

    Hello All,
    Post Pre prod refresh, our timestamp for the datasource 0FI_GL_10 got reset. Due to which our deltas did not bring any records to the BW system.
    First we did an Initialize without data transfer for all the BW related datasources. The deltas were then set properly for all datasources except 0FI_GL_10.
    We then raised a message to SAP and they suggested to run the 'Initialize with data transfer' for 0FI_GL_10 so that the timestamp is set and accordingly the deltas are fixed.
    The issue now is we are getting the following error message while running INIT with data transfer.
    Job terminated in source system --> Request set to red
    Message no. RSM078
    We have copied the data till July 1st week of 2011.
    Please advice. The issue is very critical.
    Thanks & Regards
    Sneha

    Hi Arvind
    Thanks for your inputs.
    Please find below the details of the short dump.
    Runtime Errors         DBIF_RSQL_SQL_ERROR
    Exception              CX_SY_OPEN_SQL_DB
    Date and Time          09/07/2011 11:25:32
    Short text
         SQL error in the database when accessing a table.
    What can you do?
         Note which actions and input led to the error.
         For further help in handling the problem, contact your SAP administrator
         You can use the ABAP dump analysis transaction ST22 to view and manage
         termination messages, in particular for long term reference.
    How to correct the error
         Database error text........: "ORA-01652: unable to extend temp segment by 128
          in tablespace PSAPTEMP"
         Internal call code.........: "[RSQL/FTCH/FAGLFLEXT ]"
         Please check the entries in the system log (Transaction SM21).
         If the error occures in a non-modified SAP program, you may be able to
         find an interim solution in an SAP Note.
         If you have access to SAP Notes, carry out a search with the following
         keywords:
         "DBIF_RSQL_SQL_ERROR" "CX_SY_OPEN_SQL_DB"
    Information on where terminated
        Termination occurred in the ABAP program "GP_GLX_FAGLFLEXT" - in
         "FETCH_TO_ISTRUCTURE".
        The main program was "SBIE0001 ".
        In the source code you have the termination point in line 903
        of the (Include) program "GP_GLX_FAGLFLEXT".
        The program "GP_GLX_FAGLFLEXT" was started as a background job.
        Job Name....... "BIREQU_4N3PZQ12IA0X0PYGEA85IG39S"
        Job Initiator.. "BIWREMOTE"
        Job Number..... 11203300
        The termination is caused because exception "CX_SY_OPEN_SQL_DB" occurred in
        procedure "FETCH_TO_ISTRUCTURE" "(FORM)", but it was neither handled locally
         nor declared
        in the RAISING clause of its signature.
        The procedure is in program "GP_GLX_FAGLFLEXT "; its source code begins in line
        840 of the (Include program "GP_GLX_FAGLFLEXT ".

  • Error while creating PR, 'No Procurement defined for material 150'

    Hi,
    I am trying to create purchase requisition.
    I am getting the following errors,
    'No Procurement defined for material 150'
    and 'Enter G/L Account'.
    Please help me to correct these errors.
    Thanks in adv.
    Regards,
    Eswar
    Edited by: Eswar K on Jan 7, 2008 8:29 AM
    Edited by: Eswar K on Jan 7, 2008 8:30 AM

    Hi Eswar,
    I think you have not extended the Purchasing view for that material.
    Goto MM01 and select the material 150 then select the Purchasing view for the Organizational level (plant).
    Or check the Procurement type in MRP2 view for that material.
    Check the cross Plant material status in Basic data 1 & Purchasing view for that material, whether the material is blocked for any procurement.
    Check all these you will find the solution.
    rgds
    Chidanand

  • Getting error while creating PO for direct material in SRM 7.0

    While creating PO in SRM for direct material,i am getting the error as :Backend error-No Funds center entered/derivedin item 00001(3000/2211100).Please suggest me the solution

    Hi,
    We are using PPS functionality with SRM 7.0
    Regards,
    Gopal
    Edited by: gopalthadi on Feb 9, 2011 5:01 PM

  • Error:-document is in transfer for purchase order..creation is not possible

    Hello,
    While doing confirmation of PO I am getting this error, saying "document is in transfer for purchase order..creation is not possible".
    can anyone please suggest me solution on this type of error?

    Hi,
    Is the PO in ORDERED status? Is there any confirmation posted for this PO which might be stuck (idoc failed to reach back end)?
    If it is a case of idoc failure, then reprocess the idoc and then do the next confirmation.
    regards,
    MRao

  • GR Error: Document is in transfer for PO, Creation not possible

    Hi Experts,
    While posting a GR for PO, following error is being encountered,
    'Document is in transfer for PO, Creation not possible'.
    I checked the PR - PO. There are multiple GRs for the PO and all earlier GRs are posted successfully.
    For posting a new GR this error is coming.
    Any pointers?
    Thanks in advance.
    -Dhananjay

    Hi Kiran,
    Please, use the report CLEAN_REQREQ_UP to clear the entry made for the GR in BBP_DOCUMENT_TAB. The problem comes because there is an entry for the GR in the table probably from the previous creation.
    Regards
    Saravanan.
    Please award if useful

  • Error log table for LSMW-Direct input

    Can any one tell me , What is the table for storing the error messages in LSMW-Direct input?
    Regards,
    Nagesh

    for LSMW-Direct input method you can use EXCUTE IN BACK GROUND. the job is running and see the job name in SM37 . after completion of your job , select you job name and press the  SPOOL button there you can find the you job error log.

Maybe you are looking for

  • Master VI Timer

    I have set up an instrument control project using the producer-consumer architecture. Now I would like to implement a "Master Timer" VI that can be started, stopped, and reset using the P-C VI. Furthermore, I would like to display the seconds and min

  • Keyword documentation

    In many of your responses, the folks from Oracle reference keywords like var thisform = ele.form; val = parseInt(ele.value); Where can I find documenation that tells me what ele.form is or what ele is? Is there a book, a white paper, or what???? Than

  • Both shifts and control appear to be stuck down

    So my mother brought me a 2010 macbook air and said "Fix it" the problem was said to be "I can't type anything" after two hours of troubleshooting I figured out it was that both shifts and the control key seem to be stuck down but it doesn't "feel" h

  • CS5 Flash and Photoshop painfully slow

    I recently moved from CS4 Master Suite to CS5 Master Suite. I work with all files on a home based network drive. The CS4 handled most all tasks easily. The CS5 is painfully slow. Publish Previewing a very small Flash file with no action script and 3

  • JFileChooser Questions

    Hi, I have 2 questions concerning the use of JFileChooser: 1. When you use "Details" option to see the details of the files; the "Modified" column seems to show the time in "United States" format even if the local regional setting is something else.