PO from Material Reservation

Dear Guru's,
I have maintained reorder level at storage location level and when stocks falls below this reorder level and i am running MRP system is creating Material Reservation from that storage location.I need to create PO fro that quantity.How do i get that.Kindly help.
With Regards.

Hi,
setup your data for reorder point planning. check this saphelp link.
[http://help.sap.com/saphelp_470/helpdata/en/f4/7d257044af11d182b40000e829fbfe/frameset.htm]
search in forum you will find many rlevant threads which talks on how to set up reorder point planning.
below is content from one of the thread.
Find bleow the set up following set up for automatic re-order point planning :
1.Material Master Set up : Maintain all the relevent parameters from MRP1 to MRP4 view , Forecasting View
1.MRP Type -VM , Lot Size -EX
2.Procurement Type -E for FG and F for ROH
3.Planning Startegy -10 or 40 in FG/SFG and 20 for componenet
4.Planned Delivery Time in MRP2 VIEW
5.Indiviaul/Collective Indicator - 1/2 based on your requirement in MRP4 View
6.BOM Explosion -Keep it blank
7.Service level percentage -MRP2 view
8.Maintain Forecastin view data like model selection , Histry period , period indicator , Forecast control pramaters ,
10.Make sure that you have min 12-8 monhts total consumption update in Forecasting view .
Configuration : InSPRO -MRP -Check MRP Type -VM-check the details like Re-Orde point .Safety Stock both the automatic calcvualtion box are marked .
Finally as a sample test , select any material -mm02-execute forecast in mm02-forecasting view -exectute forecast -then save .Run MRP in MD03-1,1,3,3,1.NETCH indicator and check the result in MD04
Hope it will help you to proceed further
Thanks
Ritesh

Similar Messages

  • Datasource for material reservation data from SAP R/3 (RESB & RKPF table)

    Hi,
    How can i take material reservation data stored in SAP R/3 RESB and RKPF table. I can create generic data source and full upload of data is possible but how to manage daily delta. None of these table having change date to extract daily changed record to BI. Please suggest.
    Please inform if any business content data source available for Reservation data?
    Regards,
    Manish

    Hi,
    Many times we face such situation, that we need to create a generic data source and there is no field to define delta.
    In such situations you can go for psuedo delta.
    Ask the client that at any point of time till which date will the data be changed.
    Eg. the client may say that at max we will change last three months data.
    In that case everytime you can do a full update and load only data of last three months.
    Instead of date you can consider any field as per your requirement.
    Regards,
    Mansi

  • Material Reservations and PO

    Hello,
    my question is at which stage of the network the material (components) reservations or Purchase orders, automatically trigger.
    when the project (with networks and materials) is created or released.
    because I have issue like the project is in TECO and for some reason we are planning to undo the TECO. if I undo the status, will it again creates the PO or reservation.
    Is there any document, which explains in detail about the configuration of PS -MM integration.
    Is there any concept like labor reservation just like material reservation. I am not sure is question itself true or not.
    Thank You

    Hi Gokul,
    My answer is correct considering the following in my perception and not in SAP functionality view.
    <<<<
    At what status of the WBS / network will this Material reservations or PO's get triggered. Is it at Created or Released.
    >>>>
    When WBS elements are in created status means project has not yet received the approval to go ahead from the project controller or whoever may be in the business.
    If some reasons, Management cancel the project or Customer cancel the project and its very easy to set the DLFL flag on project. But what will happen to the committed costs. Do the Management ready to take up unwanted burden and raise unwanted inventories in warehouse. Risk Mitigation is an alternate option but try to avoid inviting the risks which will save time and money.
    There are so many things to consider just not going by the SAP functionality. This is what I feel and you may not accept my statement but at the same time I respect your views and ideas.
    Regards,
    PSR
    Edited by: PSR on Nov 4, 2011 2:04 PM

  • Cant see Object Services Toolbox in MB23 Material Reservation transaction

    Hi all,
    The Generic Object Services Toolbox is not available in SAP MM transaction MB23 used for accessing Material Reservations. SAP version is 4.7/620.
    As its a standard SAP transaction referring to standard business object type BUS2093, so I was expecting that the Object Services will be enabled for this.
    Kindly help as to how I can configure the display of Object Services toolbox in this transaction to link attachments. (If its regarding changing some code like including cl_gos_manager or SWU_OBJECT_PUBLISH, then kindly explain in detail.
    With Regards
    Neha

    Also it is against the SDN Forum Rules of Engagement to cross post questions.  I can see from your posting history you have sent this same question to many different forums (several of which make no sense at all).  Please avoid this action in the future or risk having your forum posting privledges suspended.

  • Line item needs to be deleted from a reservation

    Hi Guru's,
    For a reservation, one of the line items has been created without any material number or
    plant. Actually while adding this line item, the material which was selected was discontinued.
    The message which popped-up after adding this line item was " This item is discontinued do you want to
    continue". Once 'Yes' was pressed, the reservation was completed. Now for this line item both the
    material number as well as plant is coming as blank becuase of which I am not able to delete
    this item.
    Please let me know if we can delete this line item from the reservation or not.
    Thanks,
    Swati

    Mark the Check box against Delete option which is beside Final issue in MB22 and try.
    Regards,
    Ashok

  • Material Reservation Process for Work Order

    I am new to the Plant Maintenance work order and material reservation process.
    Here is my scenario:
    I create a work order with a material that is maintained in WM and IM.
    Reservation is created.
    I got to MB26 to post goods issue
    Once I do this I see the qty of material moved as a negative amount to storage type 914 in IM (LS26) and stock removed out of WM (MMBE).
    Is this where the business process stops?
    Do I ever remove the stock out of 914?
    Does the material go from 914 to 916 and then get cleared out of inventory?
    Thank you

    Check [thread|PR Marked for deletion after Business Complete]  and [search|http://forums.sdn.sap.com/search.jspa?threadID=&q=PR+deletion&objID=f159&dateRange=all&numResults=15&rankBy=10001]
    -S.N

  • Network Material Reservation and MRP

    How does SAP know a Material Reservation created from a project has already been processed by MRP once ?
    For example; 
    If I create a Material Reservation in a project and then run MRP on that project a Purchase Requisition will be created for the Reservation.  If I run MRP again on the same project, the system will not create another purchase requisition from the same reservation.  Somehow the system knows this reservation has already been processed.  I canu2019t find the status field that identifies this reservation as being previously processed.  It is not anywhere in the Reservation record, it must be in the MRP tables somewhere.
    Thanks,
    Dave Flick

    Hi,
    Not sure if i have fully understood your report, but here is a suggestion which could help.
    Use the stock requirements FM stated in my prev posting & in addition to that use the FM - MD_PEGGING_NODIALOG.
    Now for each procurement proposal (STO or preq etc) read which element it is pegged to using the FM stated in this posting. Read these values into a internal table.
    Now you can compare the reservations with this internal table, if it exists you can choose not to display it, while displaying only those which does not feature in the internal table.
    Hope the above helps & meets your need.
    Regards,
    Vivek

  • Material Reservation List

    Hello All
    For the open material reservation after executing the transaction MB25 for the given Requirement period from date  to to date some of the Reservation are missing in the out put of report even tho their requirement date lies in between selection date & reservation are opened 
    What is the reason?
    is there any other transaction to see the open Material reservation?
    Please su

    Please put the exact error.
    as i dont see any system issue here...its must be manual issue only.
    Please post exact error you getting while determining the batch.
    and check might be other material may have same batch as selected 4 earleir material
    Regards,
    Pravin M
    TCS canada

  • How to Remove batch mangement indicator from Material Master

    Hi
    I am trying to remove batch mangement indicator from Material master..but system does not allow
    Before this .. I have done all activities also ...clear open SD documnets ,deliveriy documents ,PO documents ,Process order teco and . reservations and activae deletion flag in  batch  ... and made current period  stock an previous period  stock zero... i have cleard all documnets ...still system does not allow remove indicator..could you please guide in this issue ..how to remove batch indicator.
    Regards
    Sasi

    Hi,
    Please refer the below links.
    Re: untick Batch Manegement Indicator on Material Master
    Remove batch management flag and deletion of material documents
    How to remove Batch Management in the Material
    Re: How to remove Batch Management Check in the Material
    Thanks.

  • Storeage location from material master in PO

    I have maintained a store location of each material in Material master in view of "General Plant Data / Storage 1". Now my requirement is that whenever I create a PR or PO without PR with material, system will not take by default my store location since I have already maintained in the material master. Even the requirement is same while creating a reservation.. Can any one ans to this please.. Since it is general issue.. It should come from material master as this SAP is such good ERP package why it is not coming by default. It is a really challenging question?
    REgards
    TG

    SAP designed its programs the way it is, they have a field storage location EP to default a storage location to a PO. it just does not make sense for SAP (for perfromance reasons in big companies) to check first if there is only a single storage location maintained together with the auto storage location disabled.
    storage location EP field  is just located in MRP views.
    But with customizing you can move this field to any other view, e.g. purchasing view.
    It is probably in the MRP views, as you usually have MRP views only for materials that are stock managed, and only for quantity managed materials you need a storage location,  while purchasisg view need to be there even for materials that are not stock managed. So a proposal for storage location EP makes more sense in the MRP views, especailly while the planner defines where the materials are needed, rather the the buyer. And with distributed material master maintenance it makes then again more sense to have it in MRP views.
    But if you company does it different, then customize your material master views to your need.

  • How to extended Generated IDoc type of MRESCR01 (Material Reservation )

    Hi Experts ,
    My scenario :  I am receiving  Material reservation data from SAP PI team , There is some extra fields .
    My approach  1 . I have to extended the basic idoc MRESCR01 , here is problem 'Action is not possible for generated IDoc types'  .
    I have seen many posts for the same but  I did nt get proper post for the same .
    and also how to create ALE -BAPI interface by using BDBG , Please help this scenario .
    Thanks ,
    Jay.

    Solution : new Message Type (By reducing MATMAS)

  • Material reservation through Internal Order

    We have internal budget scenario and activated availability control.  However, at the time of material reservation, eventhough we are giving an Order as account assignment, budget is not checked.  Is it the standard behaviour ?

    Hi Nikitha ,
    System is working as expected and designed..
    Reservations do not generate any commitments in the R/3 system. Commitments are exclusively generated from purchase orders, purchase requisitions, funds commitments and funds reservations.
    As resevation is something you have booked for your future requirement, but not consumed.For budget anyway when you put actaul cost at that time system is cheking your budget.... that should be the correct approach...
    Regards
    Sarada

  • Creating Material Reservations for vendor consignment stocks

    Hi,
    Are we able to create reservations (Tcode : MB21) for vendor consigned-stocks? I tried but there is no option to key in the special stock type in the material reservation.
    Anyone can help?
    rgds,
    wl

    HI,
    vendor consignment is special stock . but in reservation your are reserving the material from your unrestricted stock to some particular operation so you will not get any special procurement type in MB21.
    regards
    suleman.

  • MB1B: Transfer posting from material to material

    hello,
    I would like to add material validation mechanism in MB1B for transfer posting from material to material, that is we can define only particular materials can be transfer to receiving material and validate in MB1B with specified movement type, how to do this?
    Is there any thing available in standard?
    we can do this using user exit but I couldn't find any exit relevant for this scenario?
    I appreciate your earliest responses.
    regards,
    Jawed Ali

    well I have checked all these exits but none was called during the process:
                                                                                    MBCF0002            Customer function exit: Segment text in material doc. item               
    MBCF0005            Material document item for goods receipt/issue slip                      
    MBCF0006            Customer function for WBS element                                        
    MBCF0007            Customer function exit: Updating a reservation                           
    MBCF0009            Filling the storage location field                                       
    MBCF0010            Customer exit: Create reservation BAPI_RESERVATION_CREATE1               
    MBCF0011            Read From RESB and RKPF For Print List in  MB26                          
    MBCFC003            Maintenance of batch master data for goods movements                     
    MBCFC004            Maintenance of batch specifications for goods movements                  
    regards,
    Jawed Ali

  • Material reservation and unrestricted Available qty report

    Hi
    SAP Buddies
    Please can anyone tell me how to get the lCollective list of Material Reservation with Available unrestricted stock??
    i.e.
    MAterial No.         Reserve Qty         Unrestricted Available Qty  
    These three parameters are must ?
    Thanks  in Advanve
    BV

    Hi,
    Please try MB25 MB25 or MF65.
    Regards,
    Mohd Ali.