PO Mass change for Net Price
Dear Experts,
Please help.
I want to change net price of POs, i tried to use MEMASSPO but there's no field for net price which is the one i want to change.
Kindly help and advise if there's another for PO net price mass change.
Thank you very much.
Zhie
Answer is in SAP note [501853|https://service.sap.com/sap/support/notes/501853] :
The ME_LIMIT_FIELDS_PO function module basically contains all non-changeable fields for the mass change of the purchase order. In addition, the following item fields cannot be changed with existing items:
Material number (EKPO-EMATN)
Material short text (EKPO-TXZ01)
Order quantity (EKPO-MENGE)
Order unit (EKPO-MEINS)
Net order price (EKPO-NETPR)
Purchase order price unit (EKPO-BPRME)
Plant (EKPO-WERKS)
As of R/3 SAP Release 4.6C, you can run the mass maintenance using the PurchaseOrder.Change method (BAPI_PO_CHANGE). For more information about this, read Note 545754.
Similar Messages
-
User exit for SO creation while changing the net price for item
Hi folks,
Is there any user exit or BADI to change the net price in the item label of Sales order??
My req. is that--- i need to change the net price of sales item if the cond type is 'ZUR1 ?
how can i achive this?
Regards
pabiHi
The user exits and badis for va01 tcode:
Enhancement/ Business Add-in Description
Enhancement
V45L0001
SD component supplier processing (customer enhancements)
V45E0002
Data transfer in procurement elements (PRreq., assembly)
V45E0001
Update the purchase order from the sales order
V45A0004
Copy packing proposal
V45A0003
Collector for customer function modulpool MV45A
V45A0002
Predefine sold-to party in sales document
V45A0001
Determine alternative articles for product selection
SDTRM001
Reschedule schedule lines without a new ATP check
V60F0001
SD Billing plan (customer enhancement) diff. to billing plan
V46H0001
SD Customer functions for resource-related billing
V45W0001
SD Service Management: Forward Contract Data to Item
V45S0004
Effectivity type in sales order
V45S0003
RP-relevance for incomplete configuration
V45S0001
Update sales document from configuration
V45P0001
SD customer function for cross-company code sales
Business Add-in
BADI_SD_SCH_GETWAGFZ
Scheduling Agreement: Read WAGFZ from S073
BADI_SD_V46H0001
SD Customer functions for resource-related billing
If it is helpful rewards points
Regards
Pratap.M -
Change active Net price in VA02
Dear Forum,
I need to change active net price in va02 for item 10.
But this is showing grey color and item is active.
Is there any way to change the price in item 10.
If poossible pls advice me on urgent.
Tks & B/R
Bishnu
23/03Hi,
You need to check your condition type for which you want to make any changes in sales order.
Steps:
1. First go to change mode of condition type for which you want to make any kind of change in the sales order
. ( V/06 )
2. now check whether manual changes are allowed or not.
3. next check mark field "quantity/value " in order to be able to make any changes in sales order.
because unless this field is not check marked you can't do any change. i.e. it will be gray.
I am sure it will solve your problem.
Please Reward if useful.
Akhilesh -
Cannot Change the Net price or currecny of a PO
Hi
When i go into change mode of a Purchase Order, I cannot change the Net price or currecny, when my collegaue is able to change this, is this a authorisation issues?
also, were can I see the PO history TAB?
Edited by: Ian Wong on Jul 4, 2008 4:53 PMHi
You must have the following Authorization Objects
with 02 Change Activity in your role profile
M_BEST_BSA
M_BEST_EKG
M_BEST_EKO
M_BEST_WRK
And for PO history tab, its at PO screen item part
but to be able to see it there must be some logistic movements
such as GR,IRetc.
After logistic movements the tab is appearing
Best Regards -
Mass Change for Service master
Dear Experts,
I've tried to do Mass change for service master.. in transaction MASS, i couldnot able to find the object for service master there..
Is there any possiblity to do mass change for Service Master
thanksHi,
I have tried ur scenario. Mass change for service master was possible using the TCode: MASS. But if u go to the Tcode:MASS, system asks object type. object type for service is not available in the match code/input help(F4).
At any time, if u want to know the object type for any transaction , goto the Tcode: SW02.(path: SAP Easy access: SAP Menu->tools-> ABAP work bench->overview->business object overview( SW02).
click on materials mgmt.-> external services mgmt.-> service master ( in the tree list).
Object type for service master: BUS1005
this business object is useful for list display for service master records(get list), read detail data for a service master record, create& change service, display object, check existance of object.
object type for attributes in service master: IFSAP
reference table: ASMD
goto SW02, to find object type for any transaction.
i think this information is very useful to u.
reward me according to ur uasge of this information. -
How create a replice "Mass Change for Quotation" from the "Mass..for order"
Hello everybody,
How create a replica "Mass Change for Quotation" UI object from the standard "Mass change for Sales Ordesr" UI object...
Way: SAP CRM==>Select a business role "SPL-Service part Management" ==> Sales ==> "Mass Change Sales Orders"
It needs a replica with the title "Mass Change for Quotation" .
Could you pleas help?
Mit freundlichen Gruessen / Kind regards,
Pavel BiarozkinHi Howard Brown,
Thanks for your suggestions about Windows user experience. Actually, we are glad to hear more feedback
about Windows operating system so that we can improve Windows to make it be more easier to
use.
As a suggestion for your current situation, you can use Windows Charm Bar to search Apps, it is also easy to use.
Alex Zhao
TechNet Community Support -
Hi All,
Is there any standard TCode for Mass changes for document managmen?
Regards
VarmaHi,
If u can specify what attributes u wish to change using mass change , then probably i can suggest some standard SAP functionality or by using Easy DMS.
Regards
Abhishek
PS:reward points if u find anything useful. -
Mass change for QM at operation level in routing
Dear Experts,
I have to carry out mass change for Quality Management at operation level in routing. The steps that I am carrying out for an individual record are as follows.
1. CA02
2. Inspection point 100 is maintained at header level
3. Go to operation level
4. At operation level work center and control key have been maintained
5. Double click on operation
6. When I scroll down here I go to Quality Management: Inspection Points view.
7. There by default in Insp.pointCompletion system shows the option as u201CQuantity, valuation (production) and radio button selected default indicates u201CQty-relatedu201D
8. I want to change these options as only u201CValuationu201D and u201CNo relationu201D respectively
My queries are,
1. Is there any T-code available to carry out these changes in mass?
2. Is it possible to do this without any Z development?
I am doubtful about using LSMW here. I would be highly grateful to you if someone can help me step by step.
Thanking you,
Anand RaoHi Sujit,
Thanks for your reply!
I tried CWBQM. Unfortunately could not succeed. I think may not be feasible through CWBQM.
But I came across T-Code CEWB . There I opted "SAP_OPERATION" as working area and it worked. Its quite useful T-Code.
Thanks again for your input.
Regards,
Anand Rao -
Mass changing for accrual object assignments part of the field profit_ctr
Hi Experts,
Does any one know about mass changing for accrual object assignments part of the field profit_ctr (profit center).
How can we do this?
Best Regarts.Hi,
I have equal problem. How did you save him?
Regards,Irena -
Massage No. 06217-Overflow for net price field during conversions
Can anybody tell me the S note for the error?
"Massage No. 06217-Overflow for net price field during conversions"
There is a S note in OSS ( 576188) which is Obsolete now. I would like to have the correct S note to apply.
thanks
SACHINHi,
SAP doesn't support item prices larger than 999.999.999,99. This is a limit of the system.
The field has a length of 11 and output length of 16 for the commas and dots. Therefore, values entered in that field cannot exceed the total length of the field.
Increasing the field length of the field is challenging. This would
cause inconsistencies in the existing dataset and more problems in
in Finance modules.
You have to look for possible workarounds to resolve this. You may
choose to split the documents, line items or quantities - what suits
your business requirements best.
You may choose to:
1. Split the line items.
This is applicable when your company wants to procure 1 single item
with say 1 Billion value.
for example:
Qty Unit Net price
1 EA 1,000,000,000.00
This may be cost of one machine or asset.
You may split this into accessories or mountings used for this as
separate line items, so that the cost of the line item will be less
than 1 Billion.
2. Splitting the quantities,
This is appliable when you are procuring more quantities with higher
value items.
For example:
QTy Unit Net price
1000000 EA 100000.00
You may split this quantity into 250000 EA * 4 = 1000000. With this
you may consider having four line items in the same PO or 4 differant
PO's.
3. Consider using pricing unit.
If you use currencies in which higher values become necessary, SAP
recommends to use smaller units of measure (for example "box"
"pallet").
For Example:
Qty Unit Net price
1 Pallet 1000000000.00
In this case you may split this into Boxes. May be the Pallet contains
more than 1 boxes. The net price of the box will be less than
the Pallet.
If your prices is not larger than 999.999.999,99 then please open a ticket in SAP, as this would be a bug and you would need a correction, that at the moment does not exist.
Best Regards,
Arminda Jack -
How change plant, net price, OPu, and Material Number from ME32K
Hi GURUs,
May let me know how I should configure ME32K in order to allow users to change:
- Material Number
- Net Price
- Order Purchasing Unit
- Plant
I have tried setting up field selections layout properly, even debug PBO, it is still greyed out for those fields.
Please help.
Thanks,
Tony Yuwonothere is no way to change the price in item overview in the contract.
The reason is explained in OSS note 685117.
........The problem is that Scales and/or validity periods may exist for the conditions, because contracts have time dependant conditions, just like info records do.
This is in contrast to e.g. Purchase orders which have Time independant conditions and so, NO scales nor validity periods.
A Purchase order has A price! The price maybe determined based on a source; a contract or an info record. Depending on the order quantity and the date, the PO price is determined.
The contract does not have A date, it might have several; indicated by the validity periods. Furthermore the price is dependant on eventual scales. Therefore it does not have A price either.......... -
ME52N : How can i change the net price ?
Dear guru.
The system allow to change only the valuation price (only relevant for release strategy) in ME52N.
Does exist a chance to change in the purchase requisition the net price of source of supply assigned ?
ThanksHello,
I doubt whether any other way is there to resolve your problem.
May i know why do not want to change the Info record?
MM -
MM - Pricing Conditions - Mass Change for Planned delivery costs
Dear gurus,
Is there way to mass change the value of pricing conditions of Planned Delivery costs in the PO? Also the supplier?
Any suggestion?
Many Thanks for helping,
MariaHi,
As far as I know, this can be done for condition type/vendor price maintained in info. record.
Transaction code: MEKP
Enter the condition type, enter the '+' sign if value is to be raised.
If you tick the 'Test Run' you can also simulate the condition (old v/s New).
Hope this helps!!
Reetesh -
Mass maintenance for standard price
please can u help me to mass maintenance standard price instead of mr21.
i have 65 sites and this is a big load to change price by mr21.
is any solution?Hello,
In MR21, you can enter several sites and articles for price change (click page down) under one company code. Alternately, you may develop a program by using the function BAPI_M_REVAL_CREATEPRICECHANGE for mass revaluation for several article/site combinations.
Thanks,
Venu -
Change of Net Price in Sales Order
Hello Experts!
I wanted to know how the "Net Price" of a sales order can be "changed" by the system or "indirectly" by the user. I have an issue with the net price that changed in the sales order, and wanted to know how this could have happened; <b>besides</b> changing the pricing conditions, price adjustments, and order surcharge. Is there someway the system could have changed it or user "indirectly"? Please advise. Thank you in advance!
WCNet price is not changed directly.
It's chanegd via changes to pricing only unless you have some code which updates this field AFTER SAP calculated it based on pricing conditions.
NOTE: if you reject line items it's vlaue is substracted form order net value, the same is true if any of your pricing conditions is made inactive due to various reasons.
Changes to pricing condiitons are not shown in order change history, you can see changes per condition record, but if any of your conditions in sales order was made inactive - you won't see it in change log. One of the options may be - if you generate any outputs (IDOCs) which send pricing info - you can check those IDOCs to determine when & what was changed in the pricing of your order.
Maybe you are looking for
-
I'm using an Ipod video 30gb on windows xp. It worked perfectly for a while, but then wouldn't store any videos or movies. i reset the ipod and unistalled/reinstalled I-tunes, and then synced my Ipod again. Now it doesnt store anything, but but 'sync
-
Need to customize the text displayed while sending payslip as pdf in mails
Gurus , monthly we will run a report which will send the payslip as pdf to the employees . Now we need to edit the text that is getting displayed in the mail while we attaching the payslip as pdf and send . how to achieve this
-
Synced audio in a file is out of sync in premiere/prelude
I have a file from a documentary film I'm working on that happened to be shot on the iPod Touch. When playing back the original files, the audio is perfectly synced. In Premiere and Prelude, the audio is fast (or the video is slow, I can't tell.) so
-
I have yet to figure out how to define a data range to use as my x-axis in a line plot. Sure, I could use an XY scatter (that can't have lines) but what if I have 4 Y variables? There is obviously something missing since, if you display the x categor
-
New MacBook Pro C2D Startup issues
Hi, I have my MBP for 3 weeks now and normally leave it on all the time (on and off the AC) For the most part it will wake up from sleep just fine. In the last 3 nights I turned the MBP off before I went to sleep. When I tried to boot in the morning