PO not showing in MD04

Hi
I created PR to PO. Po created with account assignment category c-sales order and item category s-third party. My question is PO or PR not showing in MD04.
Please can anybody suggest?

Hi,
Please check whether your PO and PR really exist for the plant, material you are speaking about.
You can check in VA03 in document flow whether the mentioned PR, PO really exists.
If it is so, you should see both PR and PO on MRP list. Start MD04 again > please check whether you gave proper material, plant, MRP area in MD04 > click on refresh button.
Please check organisational levels (used in MD04 and used in your PR/PO)! Please also check whether there's deletion indicator on the PO / PR.
Can this help?
BR
Csaba
Edited by: Csaba Szommer on Jul 22, 2008 2:12 PM
Edited by: Csaba Szommer on Jul 22, 2008 2:13 PM

Similar Messages

  • Sales Order number is  not showing in MD04

    Hi Gurus  ,
    I have got one case where  Sales order number is not showing  in MD04 screen  . This sales order , line item  has already delivered , PGI &  billing document also been generated  . Moreover accounting document is also been created .As cheeked & found that it is not shwoing in MD04 screen  because at  the time sales order creation  availability check “01” was maintained  which has sum up all the  requirement in one  particular day ( Also as
    per SAP note -70408) .
    Now because  all the subsequent document has been generated  for sales order so we can not mark it for “Rejection for rejection “  & to create new  sales order  with  availability check “02” in material master .
    Please let  me know the possible solution for the same or  if any  sap note would  be required to get the sales order number in MD04  .
    Thanks  ,
    Aman

    Hi Kiran ,
    Actually  before running the  report in “SDRQCR21”  in PRD I wanted to  run it in “Quality “ .
    In quality I am not able to simulate the same  .
    Please refer below points related to my testing result .
    1.Mainatined availability check group “01” .
    2 . Created Sales order 
    3. Check in MD04 screen & as expected  sales order  was coming blank  with negative Qty .
    4. Run the MRP which generated PR
    5. PR converted to PO  & GRN was done which updated the stock
    6. Created delivery  & checked the same in MD04  . It was also coming blank  . No delivery  document  numbe was showing in screen  but  it was coming with negative  Qty .
    7. Done the PGI  & blank  delivery document number  was removed & it become  normal .
    In PRD .
    There are 3 sales order
    One sales order is already marked reason for rejection & two sales order delivery , PGI has been done  .
    But still it is showing  blank sales order with negative Qty  & after MRP run it is generating the PR also  .
    I don't why it was  showing with negative values  .
    Please refer attacehed screen shot  .
    Thanks,
    Regards ,
    Aman

  • PIR visible in MD63 but not showing in MD04

    Hi,
    I have transferred SOP plan to demand management through mass processing...requirements are visible in md63 but they are not showing in MD04..
    Thanks
    Kumar

    Dear Kumar,
    The PIR is maintained for the version GP,which is not active,as suggested either you should maintain
    the PIR for this version as active or else  for the version 00(SAP standard).
    Regards
    Mangalraj.S

  • Schedule agreement not showing in MD04

    Hi All
    We have a schedule agreement created and its not reflecting in MD04. According to the thread i changed the avl check to 02.
    But its still not showing in MD04. So my question is do I have to do any other thing so that the avl chk change will get affected for same schedule agrmnt or I have to create a new one so that it will show in MD04.
    Thank You.

    First you need to identify what schedule line category is flowing in your sale order.  Normally, this would be CP.  So next go to VOV6, select the schedule line category and execute.  There tick the box for "Req./Assembly"
    thanks
    G. Lakshmipathi

  • PIR not showing in Md04 after certain date

    Hi
    The PIR's are coming from LTP.
    The PIR's which are created after 03/2015 are not showing in MD04
    MRP run back ground with NETCH still why PIR's are not showing?
    What settings I have to check..
    Regards,
    Srihari.M

    Please check the following  :
    1.If you have done splitting of the required qty during PIR creation . , please check in MD62  whether , you have un-checked the Active Version for some of them  .If those qty. are falling after 03/2015  , then it will not pop up in MD04
    2.While creation of PIR , if the planning period is beyond planning horizon , it will flag you a message and requirement will not display in MD04 , then check the same in OMPD and compare with planning period.
    Regards
    JH

  • Reservations not showing in MD04

    Hello,
    I have three reservations with movement type Transfer within plant 311 which is transferring stock from storage location A to B.
    These three reservations do not show up in MD04 stock requirements screen but show up in Transaction MB25(Reservation list Inventory Management) as open reservations.
    I have checked that both the storage locations are not excluded from MRP through MMSC and in "Define storage location MRP per plant"
    Can you please help me out with this issue?
    Sincerely,
    Puja

    HI
    As Vivek said  transfer requirements b/n Sloc's are seen in MD04 only if the Sloc is excluded or planned seperately i.e. have 1 or 2 in MRP-4 view for Sloc MRP indicator as it is deducted from one storage location and add to the second one.in such case
    as i have same scenarion and in MD04 it is showing.
    check in MMBE
    Regards
    Anupam Sharma

  • Demand for Partial Schedule line not showing in MD04?

    Hi All,
    An SO with around 1200 line items, having problem with one line item, ordered qty is 20. Shipped a partial line of 6qty.Schedule line was showing order qty of 20, confirmed qty 6 but no second schedule line for the balance of 14 and the demand for the open qty 14 is not reflected in MD04. Tried manually and also manually running MRP for the item but neitger created a second line or triggered the demand to show in MD04.
    Thanks in Advance.
    Thankyou and Regards
    Hatti.

    Try creating the schedule line in the order and then running MRP for the demand to show in your stock requirements.

  • Manual Reorder point planning stock is not showing in MD04

    HI,
       Would any one help me when i plan for reorder point planing the details furnished below.
    Mrp type: V1
    Lot size :HB
    ROP : 30
    Max stock level :1000
    in Material master settings.But when i run the MRP using MD03 system is not showing available stock in MD04.It is showing 0 stock rather it would show 4 (MMBE un restricted stock..)
    What are thesettings required or any thing missing in IMG. Please help me in this.
    Regards,
    Srini

    Srini,
    You may also want to check if the Unrestricted stock is in a storage location that is excluded from MRP.
    On MD04 you will then see a separate line item at storage location & the Qty =4 should appear as shown below.
    12/02/2009     Unrest Stock                                                       12           12      
    12/02/2009     SLocSt     QANN StLoc: not plnd          0           8     QANN
    12/02/2009     SLocSt     VEND StLoc: not plnd          0           0      VEND
    Hope this helps. Good lcuk.
    thanks,
    Ramm

  • Ordered item is not showing in MD04

    Hello SAP Gurus,
    My requirement is like one material is in the sales order but dose not show as ordered in MD04.
    Could someone please help me on this.
    Thanks
    Sha

    Go to your sales order and note the schedule line category of the line item which you want to check
    In t code VOV6 for the schedule line category there is a check box for transfer of requirements near to Availabilty check tick box, If you tick that then this order for this line item will appear in MD04

  • Customer Order Qty not showing in MD04

    Dear Sir,
    Customer has booked an order for 5000 Nos of one FG. The Order is very much active. But when we see in MD04, Requirement Qty is showing (-)5000 but there is no qty coming in available qty column. Practically it should be (-)5000, as plant stock is zero. Due to this error, planned order is not coming on planning run.
    I believe some thing missing in material master. As other material booked against same sales order is coming in MD04.
    Can anybody help me. Full points for helping answers.
    GR

    Hi,
    I think you should do what was told you by Ganesh. If planning strategy is e.g. 10, 11 the SO has only informative role, no PldOrd will be generated for it - this is MTS environment.
    If planning strategy is 40 you may have PldOrd for SO based on IndReq qty&date.
    In MTO environment you should 'always' get PldOrd for SO.
    BR
    Csaba
    Edited by: Csaba Szommer on Jul 23, 2008 2:21 PM

  • Sales orders not showing on MD04

    Hi Gurus,
    Last week we had copied production environment into quality system. Now when the users are creating sales orders in Q system, they are not able to see the sales orders in MD04? What is the reason for this?
    Thanks
    Anusha

    Go to your sales order and note the schedule line category of the line item which you want to check
    In t code VOV6 for the schedule line category there is a check box for transfer of requirements near to Availabilty check tick box
    If you tick that then this order for this line item will appear in MD04
    Check :
    MD04 - Configuration Points
    http://sap.ittoolbox.com/groups/technical-functional/sap-log-pp/md04-issue-sales-orders-2584812

  • Demand not showing on md04

    Hi All,
            I am in a critical situation , so could you please guide me to solve this issue will be grateful.
    My issue is
    Sales orders  are creating a planned orders for Top level materials [Material A] but it's not creating a requirements for low level item [Material B].
    Low level item is buy part so , I am looking for PR needs to be created after MRP, but in MD04 nothing is visible.
    So please help how to get the demand on MD04  for low level items.
    Thanks in Advance.

    Hello Madhan,
    Please check with below points.
    1.MRP type of low level material = PD
    2. Stock of low level material
    3.BOM validity of Low level material.
    5.Any Exception message for Header material planned order
    6.Is it Multi level planning (Md01 or MD02)
    Regards
    Pradeep

  • RE: GR Processing Time not showing in MD04 and Exception List

    Hi,
    Just a quick question on GR Processing Time.
    A sales order has been raised and delievery day is for lets say 05/04/2010. MRP runs and it creates a planned order to be finished on the 05/04/2010 but it should finish on 04/04/2010 and as I have a GR time for 1 days.
    All data is correct but it doesn't seem to give an exception message saying reschedule in for the 04/04/2010 based on the GR Lead time build in material master.
    Regards
    Adeel Sarwar

    Dear ,
    Please note that while you are Carrying out MRP in MD02 you might have selected scheduling indicator -2  which triggered Lead times Scheduling based on the sales Order Delievery date , Scheduling Margin Key Timings , GR Processing Time  with an infinite capacity (MRP system does not carry out any Capacity Avalibility check where as does it does Scheduling for Planned Order  considering infitinte capacity in WCs) .As the system calcualtes the Planned order Deleivery date based on those parametrs  with in the planning and re-scheduling horzon , so result is not exceptional from MRP scheduling ponit of view .
    Now if you re-schedule the order as per your delivery requirement date , you will get the exeception messgae as applicable in MD04.
    Otherwise , please check in SPRO-Material Requirement Planning ---Evalution -Exception Msg -Select Key  U1-MSG 10-Double click on that -Check wether the "No Exception Msg " is ticked .Remove the same .
    Regards
    JH

  • Sales Order not showing in MD04

    What could be the possible reasons?
    The order is for a procurement type E HALB with strategy 40.

    Check:
    1. If reason of rejection is maintained in SO, if yes, then check with the concerned sales personnel why it is there
    2. In schedule line tab for that material, check to see if schedule line catg. is CP (if not, check with sales personnel as to why they do not want to transfer it to MRP)
    3. Check if the SO has been delivered completely
    4. Also check if there is some credit block on the SO.
    If the above does not resolve, then revert with more details.

  • Open PO item is not visible in MD04

    Dear Expert,
    We have one scenario that one PO contain 3 line item which having Open PO Qty. but for line item 20 we have completed open qty i.e.40 & PR is also there. but it is not showing in MD04 & Also not visible in MIGO while doing GR
    so please suggest what we need to do this will be visible.
    Regards,
    Ishwar

    Dear Subhash,
    Thanks for your reply
    Status of line item is OPEN
    Changes has been done in PO & also Version is set with Completed Indicator
    Plz suggest
    Regards,
    Ishwar

Maybe you are looking for

  • I am facing error while running Quickpay in Fusion payroll that "The input value Periodicity is missing for element type KGOC_Unpaid_Absence_Amount. Enter a valid input value". Any idea?

    I am facing error while running Quickpay in Fusion payroll that "The input value Periodicity is missing for element type KGOC_Unpaid_Absence_Amount. Enter a valid input value". Any idea?

  • Cameras no longer recognized

    I just ran the Security Update and now none of my cameras show up in the Finder, or Image Capture, or iPhoto. Plug them in and turn them on, nothing happens. I've tried two different cameras and a card reader, all of which worked fine last week. Now

  • Automatic creation of InfoObjects

    Hi, In order to develop a test scenario, i have a need to create around 3000 InfoObjects following our naming conventions. So is there a way to do this automatically? for example like batch job? what is the normal procedure for the QA guys? waiting f

  • SIGSEGV on linux

    We have a stand alone Java application that is a J2ee client. The client runs on a linux box running the 2.2.18 kernel. We are using the IBMJIT for 1.3.0 I have the ulimit -s 2048 set in the shell script that launches the java app. I am running it wi

  • Output as WebM or HEVC

    A client asked me to output project as WebM or HEVC.  What is the best way to do it ? FCP7 (neither FCPX , Compressor ) don't support these formats yet. By the way,  someone can tell me if Apple will (and when) support WebM and HEVC?  I tried using M