Hi experts,
PAM03 comes with default icons/labels for vehicle pooling. For example in the tool bar there is a filter for 'licence plate' or 'vehicles' for sorting. As you know the PAM can be used for variety of assets such as IT. I wanted to know if you've ever attempted to update the planning board to be used for assets other than vehicles.
I believe in note 1272432 there is mention to this functionality using function module PAMS_GRAPH_UC_OTHERS. I'm still trying to figure out how this works so any input is appreciated.
Thanks

Hi PAM user, the steps necessary for PAM are described in the following places, at the sap Help portal
http://help.sap.com/erp2005_ehp_04/helpdata/en/2b/1a73268dd74a0988c00a90171294f7/frameset.htm
http://help.sap.com/erp2005_ehp_04/helpdata/EN/0b/5ad2c9e2f249abad4df1479243a001/frameset.htm
Make sure you activate the SAP Business Function for PAM, which is LOG_EAM_PAM (via transaction SFW5). This will also provide the right settings within config for the planning board and Pool Asset Management.
Only thing that does not automatically gets updates, is table PAMS_VSTAI, which needs to have the following entries:
Pool Asset Management   ABGH    04      Productive Split        I3908   Picked Up
Pool Asset Management   AUFE     02      Completed Split I3910   Settled
Pool Asset Management   DISP       01      Productive Split        I3902   Assigned
Pool Asset Management   GELA              Completed Split I3905   Deleted by requestor
Pool Asset Management   GELD              Completed Split I3903   Deleted by planner
Pool Asset Management   NDIS      01      Reqmt   I3901   Need
Pool Asset Management   RESM    06      Productive Split        I3907   Reserved
Pool Asset Management   RGBE    03      Completed Split I3909   Returned
Pool Asset Management   STAN    05      Completed Split I3906   Need revoked
Pool Asset Management   STOR    05      Completed Split I3904   Planned need revoked
Pool Asset Management   SY01    08      Absence         Maintenance/ Repair
Pool Asset Management   SY02    07      Absence         End of Leasing
I hope this helps you in setting up the solution. Feel free to provide feedback on if it worked.
Cheers,
Hanneke

Similar Messages

  • Pool Asset Management- Planning Board

    Hi Guys,
    We are in the process of implementing PAM in our company.
    I have done the config based on the note ; 1272432 up to certain extent. When i go to PAM03-planning board, the following message is appearing " Illegal number of columns in chart(231, 1, 0), Sum of columns in chart is not equal".
    I could not able to find the configuration part for this.
    Also in the planning table, i could able to see the request, but i am not able to see the equipments assigned to Pool (functional location category).
    Kindly provide your valuable inputs.
    Thanks&Regards,
    Pavan

    Hi PAM user, the steps necessary for PAM are described in the following places, at the sap Help portal
    http://help.sap.com/erp2005_ehp_04/helpdata/en/2b/1a73268dd74a0988c00a90171294f7/frameset.htm
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/0b/5ad2c9e2f249abad4df1479243a001/frameset.htm
    Make sure you activate the SAP Business Function for PAM, which is LOG_EAM_PAM (via transaction SFW5). This will also provide the right settings within config for the planning board and Pool Asset Management.
    Only thing that does not automatically gets updates, is table PAMS_VSTAI, which needs to have the following entries:
    Pool Asset Management   ABGH    04      Productive Split        I3908   Picked Up
    Pool Asset Management   AUFE     02      Completed Split I3910   Settled
    Pool Asset Management   DISP       01      Productive Split        I3902   Assigned
    Pool Asset Management   GELA              Completed Split I3905   Deleted by requestor
    Pool Asset Management   GELD              Completed Split I3903   Deleted by planner
    Pool Asset Management   NDIS      01      Reqmt   I3901   Need
    Pool Asset Management   RESM    06      Productive Split        I3907   Reserved
    Pool Asset Management   RGBE    03      Completed Split I3909   Returned
    Pool Asset Management   STAN    05      Completed Split I3906   Need revoked
    Pool Asset Management   STOR    05      Completed Split I3904   Planned need revoked
    Pool Asset Management   SY01    08      Absence         Maintenance/ Repair
    Pool Asset Management   SY02    07      Absence         End of Leasing
    I hope this helps you in setting up the solution. Feel free to provide feedback on if it worked.
    Cheers,
    Hanneke

  • Pool Asset Management - Assign Driver from Planning Board to equipment demand

    How to assign a driver in sap pool asset management, using Planning board , since opening the demand through graphical board i need to assign an equipment & drive to the demand created

    hi , you can use partner function to assign driver name.

  • Pooled Asset Management

    Hi Friends,
    We have configured  PAM with the request as Notifications and other related configuraiton settings as available in SPRO.
    But when the request is created through Notification Type MF and the same is triggered in PAM03 - Planning Board Profile but the Y axis nothing is getting displayed.
    To add more the Equipments confgiured are not getting displayed in Y axis for scheduling the demand. What more settings need to added.
    Can anyone have come across a similar issue during your implementation?
    Regards,
    Selva
    Mob: 0091 9620207596

    Hi Friends,
    I configured the 'PAM' in my company, but save the note appears an error in abap, Could you please help me?
    Follows step by step the held configuration, where the dump was presented.
    Notification Types ->
    Define Notification Types:
    Copy standard M1, create MF notification – Pool resquest
    Overview of Notification Type -> Screen Areas in Notification Header:
    Screen type hdr: H100
    Scrn type object: O100
    Screen Structure for Ext View:
    10\TAB01 (screen area) 850, 065
    10\TAB23 (screen area) 850 (Pool Asset)
    Priority Type: PM
    Transaction CL01 – Create class
    Class: ClassPam
    Type Class: PAM
    Pool Asset Management
    Basic Settings for Pool Asset Management:
    New Entries
    Application: Pool Asset Management
    Reservation TXT: Test
    Class Type: PAM
    Class: Classpam
    Edit Object Processing
    New Entries
    Application: Pool Asset Management
    Actv.Entry: flag
    typ: MF
    Transaction PAM01 – Create pool test
    PAM Pool: 01
    Category: T
    Description: Pam Test
    Fac.Calendar ID: none
    Holiday cal. ID: none
    Functional Loc: Enterprise
    Test:
    Transaction IW21
    Notification type: MF
    fill the required fields (ex: Text, PAM Pool and Maintain account assignment)
    Clicking save, dump is reported.

  • Pool Asset Management

    Dear all,
    I am implementing SAP PAM , i have configure all the configuration as per the Configuration guide which i downloaded from the service.sap.com side
    but still when i execute the PAM03 the planning board i not showing the correct result there is no drag and drop facility coming and also there is no functionality like ( issuance , reture , etc ) options.
    If anybody know about the name of the BC sets which need tio be activated for the configuration of Demand Notification and the PAM planning board that will also be very helpful.
    We have activated the SAP Echancement package in the system ( log_EAM_PAM).
    Kindly if anyone can help i will be very thankful to him / her.
    Regards,
    Haris Khan

    Dear Haris ,
    Please refer the below link also maintain the table PAMS_VSTAI  using t-code SM30 as this will not get updated on Config.
    Pool Asset Management ABGH 04 Productive Split I3908 Picked Up
    Pool Asset Management AUFE 02 Completed Split I3910 Settled
    Pool Asset Management DISP 01 Productive Split I3902 Assigned
    Pool Asset Management GELA Completed Split I3905 Deleted by requestor
    Pool Asset Management GELD Completed Split I3903 Deleted by planner
    Pool Asset Management NDIS 01 Reqmt I3901 Need
    Pool Asset Management RESM 06 Productive Split I3907 Reserved
    Pool Asset Management RGBE 03 Completed Split I3909 Returned
    Pool Asset Management STAN 05 Completed Split I3906 Need revoked
    Pool Asset Management STOR 05 Completed Split I3904 Planned need revoked
    Pool Asset Management SY01 08 Absence Maintenance/ Repair
    Pool Asset Management SY02 07 Absence End of Leasing
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/0b/5ad2c9e2f249abad4df1479243a001/frameset.htm also refer Note: 1272432 for PAM tips.
    Regards
    Ajaysingh

  • Configuration-Pool Asset Management

    What is the purpose of configuring PAM class for pool asset management?How these characteristics are helpful during raising demand notificaiton for pool asset? Where I can get the building block for pool asset management?
    Regards,
    Tehsin

    Hi Friends, I am new to SAP fans, Well I am also configuring SAP Pool asset management in my org, I have configured complete scenario and its working fine, the only problem i am facing the cost calculation part for TRIP based on time and running kms when you return the vehicle back to original pool.
    In service type configuration i have configured relevant activity types with rate maintained in KP26 for fleet cost center, in PAM03 on demand notification screen , when i click the button 'settle', and ask me to select the counters for time and kms based on readings , it create a Service order in back ground which has status TECO and there are no cost is posted on my service order,
    Here i want help from all PAM experts, Am i missing some thing why my cost are not getting calculated and why my Notification status not updating as 'Settled' and why my service order status is TECO
    Any help would really be highly appreciated
    How this calculation scenario works for PAM for trip cost,
    Rajeev

  • MRS (Multi Resource Scheduling) - Manager Planning Board

    My understanding of the MRS Manager Planning Board is that it will only display those orders that have operations that have been assigned to a resource.  If true, this would mean that the Manager Planning Board would be of little value to an organzation that is only using MRS to schedule to a work center because there would be no demand that had been assigned to a resource.  It would only start to be of some value once the organization began to assign demands to resources.  Is this correct? Or, do you see other value in the Manager Planning Board for an organization that is only scheduling to a work center?
    I've also found that when I run the Manager Planning Board that the resources are displayed, however, I have to hit "refresh" in the Planning Board to get the orders/operations (demand) to display.
    Mark
    Edited by: Mark Scott on Aug 18, 2009 1:15 PM

    Hi Mark,
    As you already figured out correctly that the Manager planning board displays the resources (in display mode). It displays all the information about the resource: Its availability and assignments. since assignments are displayed, obviously the (related) demands are also displayed.
    If the fine grained planning ( planning at resource level ) does not happen, then obviously it does not make sense to use the manager planning board transaction.
    PS: As the name suggests this transaction is for managers who are not authorized to change anything but only for display. So they will see the resource availability and assignments in this transaction.
    Regards
    Varun

  • Error in Class Assignment in Pool Asset Managment

    Hello Team,
    I am facing problem in IW21 during creation Notification type MF which is used for Pool Asset Management. if possible give me solution
    After Click on Equipment below window will open
    and in this window if i do next, no processing will happened. If i wish to save this notification system will give error Like Error in Class Assignment.
    I checked entries in PAMS_FSET table also.
    Thanks and Regards,
    Sweta

    Hi , Please check whether class PAM is defined for class type PAM in CL02 . If it is not defined please maintain some characters in it.
    Regards,

  • Pool Asset Management - e-mailing

    Hi
    In the help document, it says : "When the planner assigns a demand to an available pool asset, the asset is reserved and the employee automatically receives an e-mail confirming the reservation." I think I am missing something. The demanding user is not receiving any messages from the system although his user id is set in the partner list a s a user and as a requester also.
    Is there any functions or any settings that I should do in order to send messages?
    Thanks in advance

    hi , you can use partner function to assign driver name.

  • Pool Car management - (Pool Asset Mangement)

    Hi
    We have implemented Enhancement Package 3 in order to make use of the functionality available under Pool Asset Management.
    Various additional customising options become available, but there are no default settings. In the SAP documentation it says "A BC set is available for these settings and is imported automatically". I understand the basic concept of a BC set and would obviously prefer to use this than to go and make all the customising settings myself. I have however not worked with BC sets before and so I am not sure (1) where to obtain the available BC set for the various customising tables and (2) how to go about importing them.
    I would appreciate any assistance anyone could provide.
    regards, Lara

    Dear Lara,
    Please see the following link, it may help you to some extend.
    [http://help.sap.com/erp2005_ehp_04/helpdata/EN/6f/3c3f88fbef11d2958c00a0c930dcc1/frameset.htm]
    Sundar

  • PAM - Maint. Planning not creating Reservation in Graphical Planning Board

    Hi All,
    I am implementing Pool Asset Management for the booking in and out of plant.
    Everything seems to be working well apart for the maintenance part. In the SAP Documentation [Repair Measures|http://help.sap.com/erp2005_ehp_04/helpdata/en/0b/5ad2c9e2f249abad4df1479243a001/frameset.htm] it states that a reservation is automatically created for the asset in question for the period it is in the workshop.
    I have found no other guidance other than what is in the above link. So far I have tried the following:
    Maintenance Plan creating M1 Notification for the relevant asset. Does not appear on the Planning Board.
    Maintenance Plan creating a Demand with no PAM details. Doesn't show up on the Planning Board.
    Maintenance Plan creating a Demand with PAM details including the specific PAM Pool. A demand is held in the Planning board but requires manual intervention.
    I have searched hi and low but still haven't found any answers for getting the Maintenance Planning of Assets appearing in the Planning Board.
    Any Help would be much appreciated.
    Thanks,
    Dean

    Hi All,
    I have now found a solution to the issue I posted below.
    It is simply a case of setting a maintenance notification in the IMG Edit Object Processing and setting it as Direct Entry.
    Thanks to Udo Schumacher for the [solution|Re: Maintenance schedule not visible in PAM03 Planning table].
    Dean

  • Settlement issue for Pooled asset

    Hi all,
    I created a notification (type MF) for pooled asset in IW21. I was able to view the notification in the planning board (PAM03). I was also able to do the planning of the demand and was able to reserve, issue and return the pool asset.
    Now, I am facing an issue during settlement. Which I try to do the settlement, system is giving an error 'Unable to determine the pool category for requirement'. Message No. PAMS145
    Below is the detailed message:
    Diagnosis
    In Customizing for PAM, you define activity types for each pool category for
    each controlling area.
    When settling a PAM requirement, the system calculates the service performed
    for the activity types defined for 'Rental price' and 'Price/unit.'
    The pool category is determined using the equipment or message (in this
    order) for the requirement
    The controlling area is determined from the equipment.
    Unable to determine a pool category for the requirement.
    System Response
    The settlement of the requirement is terminated.
    Procedure
    Depending on the business process, store a pool category in the equipment or
    the message.
    I think I am not able to tie up the pool category which is there in the configuration of PAM with the equipment I created. Has someone faced similar issue before? What could be the possible way to resolve this error?
    Thanks,
    Tajinder

    hello Gandalf ,
    Create an IO Through KO01 with extra Create AUC........
    Then post the exp to AUC........
    Then assign the settlement rule as Fixed assed and enter the Asset number and give % or amount....
    Settle the IO through K088
    Hope this will resolve your issue............
    Regards
    Kumar

  • Pooled connections management

    Hi,
    I am using the api which can found in oracle.jdbc.pool.* (OracleDataSource,OracleConnectionPooledDataSource) and connection caching.
    From the documentation, I understands that we can create a number (say conn1, conn2, conn3 - each getConnection request was done sequentially) of pooled connections for one physical connections. When the program that uses conn1 releases conn1, does conn2 will be automatically be able to presume its operation as though it was put into an execution queue.
    Regards.

    Hi Friends,
    I configured the 'PAM' in my company, but save the note appears an error in abap, Could you please help me?
    Follows step by step the held configuration, where the dump was presented.
    Notification Types ->
    Define Notification Types:
    Copy standard M1, create MF notification – Pool resquest
    Overview of Notification Type -> Screen Areas in Notification Header:
    Screen type hdr: H100
    Scrn type object: O100
    Screen Structure for Ext View:
    10\TAB01 (screen area) 850, 065
    10\TAB23 (screen area) 850 (Pool Asset)
    Priority Type: PM
    Transaction CL01 – Create class
    Class: ClassPam
    Type Class: PAM
    Pool Asset Management
    Basic Settings for Pool Asset Management:
    New Entries
    Application: Pool Asset Management
    Reservation TXT: Test
    Class Type: PAM
    Class: Classpam
    Edit Object Processing
    New Entries
    Application: Pool Asset Management
    Actv.Entry: flag
    typ: MF
    Transaction PAM01 – Create pool test
    PAM Pool: 01
    Category: T
    Description: Pam Test
    Fac.Calendar ID: none
    Holiday cal. ID: none
    Functional Loc: Enterprise
    Test:
    Transaction IW21
    Notification type: MF
    fill the required fields (ex: Text, PAM Pool and Maintain account assignment)
    Clicking save, dump is reported.

  • Ability to display multiple texts within graphic planning board Gantt chart

    I have been unable to change the planning board Bar Chart Graphic Profile (OPG0 and OPG9) to be able to display both material text and a user field within the Gantt chart graphic.  I have copied the SAPSFCG011 profile and created my own.  The profile is displayed below from CMCH.
    Overall prof: ZBWSFCG011           SFC: View work center/capacity (3 graf.)
    ...... Select.profile:                     ZBWSFCS001      SFC: View work center -> cap.(3 graf.)
    ...... Control profile:                    ZBW___C002      Gen: Planning table
    ...... Time prof:                           ZBW___Z002      Gen: Medium-term (3 months)
    ...... Evaluation prof.:                 ZBW___A001      Gen: Standard evaluation profile
    ...... Strategy prof.:                    ZBW___T001      Finite scheduling forw./all functs.activ
    ...... Capacity planning table:      ZBWSFCL010      SFC: only main cap. (3 graf.)
    .......... Graphics profile                      ZBW___X002      BARC    1  Default profile 2 Capa. planning board
    .......... Chart sequence                      ZBWSFCT002      SFC: Main caps. (3 graph.)
    .......... Layout ID                                 ZBWSFCLA10      SFC: Work center view     (graphical)
    .......... LineRepresSelection                 ZBW___ZR02      SAP standard 2
    .......... Scale time axis                         SAP___M031      Stand. weekly per. split rough
    .......... Graph.object.select.                ZBW___OA02      Pool group order path
    .............. DStat Sq Structur Field na ROp Comparison val NStat Struct
    .............. 00000 01 KBED     TYPKZ    NE  1                      00001
    .............. 00000 02 AFVG     OBJNR    ST  SAP005         00000 SAP002 Standard operation partially confirmed
    .............. 00000 03 AFVG     OBJNR    ST  SAP006         00000 SAP003 Standard operation completely confirmed
    .............. 00000 99                   DEF                                  00000 ZJB000 Standard operation
    ................... Graphical object type               ZJB000          Standard operation
    ........................ Form type                           22              Plan. board:Graphic obj. w. ordNo matTxt
    ........................... Form group                          ZBW001
    ............................... Form definition                     PLTO22          Planning board graphic order and mat.txt
    .................................. Layout definition                   [[$a//$b]]
    .................................. Layout definition
    .................................. Layout definition
    .................................. Layout definition
    In addition to the profile change, I have configured the graphical object type ZJB000 (in OPG9) to look as follows:
    0     AFKO     Order header                          MATXT     Material description                                                                     
    2     KBED     Capacity requirements     A     SSTAD     Latest start / date     SSTAU     Latest start / time
    3     KBED     Capacity requirements     A     SSSBD     Latest scheduled start: Processing (date)     SSSBZ     Latest scheduled start: Processing (time)
    4     KBED     Capacity requirements     A     SSSAD     Latest scheduled start: Teardown (date)     SSSAZ     Latest scheduled start: Teardown (time)
    5     KBED     Capacity requirements     A     SENDD     Latest finish / date     SENDU     Latest finish / time
    6       AFVG    Order operation                       USR08    User field for date                                                                               
    I have found that the 2nd text field (USR08) must be added as the last step (#6).  When I had it as #1, the planning board did not display the USR08 value.
    Now both are displayed in the Gantt chart graphic.  However, it is difficult to see this long string of data as the bars in the Gantt chart may not be long enough to display the data. 
    Therefore we would like to use the "hover over" text which is displayed in the status line at the bottom of the screen.  We have tried using both the Info Text and the Quick Info options within the Bar Chart: Options Profile (OPG0).  Only the first text (the material descirption) is dislayed within either the Quick Info or the Info Text.
    Is it possible to have multiple object values appear in Quick Info or Info Text?  Or is it possible to control which text is displayed in the Quick Info or Info Text?
    Any help in this area would be greatly appreciated, as this is a make-or-break issue for the business to use the planning board.  Thank you!

    I'm also looking for a standard customizing alternative to do the same thing.
    Still, if you're interested, I've already done it successfully with user exit PLAT0001.
    Hope this helps.
    Best regards.

  • CM25 planning board

    Dear experts,
    I have been working on the CM25 graphic planning board. So far I have not been able to show if a production order is scheduled to be finished in time.
    Do you know if it is possible to show this somehow?
    I am thinking in two directions:
    1) The planning and scheduling log gives a warning message if the "scheduled finish date" differs from the "basic finish date" (also when it is produced too early). Can I change the settings of the scheduling and planning log?
    2) I know how to link different colors in the planning board depending on a user status. Is it possible to determine a status which compares the "scheduled finish date" and "basic finish date"?
    Are there any other solutions?
    Will definitely reward points!!!
    Regards,
    Tim

    Dear Rachael,
    One thing I learned is that CM25 is full of surprises. In the end I did manage to compare the "basic date" and "scheduled date" and assign different colors to them. Our customer requirements are converted via MRP which calculates the basic dates of our planned orders. As long as the basic dates are correct, the colors of the planning board will indicate if an order is still on time or not.
    The problem is that if a planned order is firmed or if a production order is created the basic dates will no longer change even if the customer requirements change...
    It turns out that we will be able to use this solution for our client, but I did not find a real solution to compare production with the customer requirements.
    If you need more info, please come back.
    Regards,
    Tim

Maybe you are looking for

  • Whoops! That's annoy the wife! (She can no longer surf the net)

    I gave her my old eMac to organize her music and photos. I wasn't supposed to touch it. (She's had too many of my "computer fixes" that didn't quite work.) Since she only downloads songs about once a month, my brilliant plan to save money was to just

  • Unable to save in logic pro 8

    I know this sounds like I'm a dope but I've just purchased the latest Logic Studio package and after enjoying this great bit of software for the first time, I've found that I can't save the song file!!! In 'save as' I've included assets (and these fi

  • Can I use the iPhone 5S that I bought in Italy,  also in Korea without problems?

    I bought iPhone 5S in Italy. Can I also use it in Korea without any problems?

  • Fragments - How to reference them in JS?

    Hi, We have a subform that is being used in about 20 places in a dynamic PDF form and basically showing/hiding this subform and setting it's internal object values based on user's selection somewhere else in the form. Using the normal way of scriptin

  • 2 very basic sql questions (I hope)

    Hi; This is for the ADO.NET 2.0 MS Oracle driver. Is there a standard way to do either of the following: Sql Server has the concept of getting the first N of a select only using: select top 1 * from Schedule where deleted = 0 order by runNext Does Or