Portal Approvals Process Questions

I have a few questions about the approvals process. These may just be beginner questions, or I am missing some of the point of the way that the approval process is designed to run.
1) Should all users in a group that has Manage with Approval rights be able to see changes made by other users in the same group?
2) If a user is part of group in the approval process, as well as being the next step in the approval process, the user has to approve the item twice.
3) When a user is done modifying an item and clicks "OK" there is no way for any user to make any changes to the item until it is approved/rejected.
4) Approval history is lost when an item is approved, then edited.

hi ian,
1) only the user who makes the changes should see the changes, independent from the other users in this group.
3) in the next major portal release there will be a draft mode for items that allows an user to work on an item as long as he wants before sending it to approval.
4) this is correct. it is only available for items that have been rejected and erased once the item has been approved.
hope this helps.
regards,
christian

Similar Messages

  • Approvals Process:  Cannot promote a Planning Unit

    Hi, Am new to the Approvals process in Planning 11.1.2.2
    Have set up a Planning unit and assigned owner and reviewers to entities. Approvals template is set to "Bottom Up". Have also assigned a version and scenario to the Planning Unit H. When the Planning Unit is Started , the current owner changes to the user assigned as the owner and all is good. However when the owner attemptes to promote the planning unit to the next reviewer the promotion action fails with the message "Change status cannot change ownership to the new owner due to insufficient access". For my testing, have assigned the owner and all reviewers "Approvals Administrator" access to the planning application.
    Any ideas as to what access the error message is talking about ?
    Thanks !

    Dear,
    -Please check with the Provision that you have given to the USER,
    -Use file based export and checke wheater you missed any user to mention that hierarchy.
    -IN the approval hierarchy check  every node weather you have given the user there or not, chances are that even if you miss one member you will get
    this error.
    -We faced the same issue and we got resolved it by checking the Provision of the User and following the above steps
    Thanks
    Bejagam Naveen

  • WAAS Application Requests - Process Question

    Non Technical Process Question
    We all have forms we have our users complete when a firewall rule or change is needed.  You may even have a similiar documents for when load balancers or DNS changes are required.  Does anyone have document they can share that outlines what pieces of information are needed for intergrating applications into WAAS?  What about ongoing changes?
    Source, destination and TCP port information is really a very small portion of the what needed to maintain a clean a defined methodolgy within the WAAS manager.  Does anyone have an example or can describe how you collect the initial information to set up WAAS but how do you keep track of changes that may be needed as the application charaterics change or the server farm expands horizontally?
    Thanks - Sam

    Sam,
    the general answer for detailed information on how to configure WAAS for certain applications is described here:
    http://www.cisco.com/en/US/docs/app_ntwk_services/waas/waas/v501/configuration/guide/policy.html
    In general, WAAS comes preconfigured for the most widly used applications in the industry.
    In order to understand, which configuration is necessary for a new application, one needs to understand the basic options WAAS offers.
    These are two options:
    1) Use an Application Optimizer (AO) if you need some dedicated protocol know how. ( e.g. (e)MAPI, CIFS, SSL, HTTP, ICA, to name some)
    2) Generic TCP traffic is optimized using TCP Flow Optimization (TFO), Data Redundancy Elemination (DRE) and Lempe Liv (LZ) compression.
    The in terms of processes, the question is:
    1) Is there a policy preconfigured for the new application?
         a) yes
              If an AO is used, does the AO need configuration? ( example: SSL AO requires certificates)
              Do we have specialities which require further fine tuning? ( Answer is mostly: no, Example: non-standard ports)
         b) no
              You define what you need for the application based on the protocol characteristics.
              If you have defined these characteristics you can choose one of the AOs, or define which of the "generic" options fit the traffic. For example, for traffic that is already compressed, it does not much benefit from LZ, so choosing only TFO and DRE. Another example is traffic that has not much of dublicate data, perhaps it does not benefit a lot from DRE, so you configure TFO only.
    Does that answer your question?
    Thanks,
    chris

  • Question related to my previous "background process" question.

    Hello Folks:
    Can I start a "Notification Service Subscriber" process through the
    normal startup procedure for other servers---i.e. by adding it to the
    config(ubb) file. If so, can I implement the background process as two
    different CORBA servers calling each other asynchronously to accomplish
    the work. Please let me know if there is any other way to accomplish
    what I have stated in the "background process" question.
    Thanks,
    Ram Ramesh
    678-358-3581

    Go to your forum preferences and set the email options.  You may also need to unsubscribe from forums / topics you are currently subscribed to.

  • How does the Approvals process work in Oracle Hyperion Planning v 11.1.2

    Hi,
    I have recently upgraded to Oracle Hyperion Planning v 11.1.2 and the way that the application handles budget / Forecast approvals appears to have changed.
    Is anyone able to direct me to a user manual or provide me with some guidance on how to set up the approvals process in the upgrade Oracle Hyperion Planning v 11.1.2.
    Currently I have the approvals hierarchy set to allow all approvals and have the approvals template set to bottom up, I have not put any values on the hierarchy and sub hierarchy tab as I want to drive approvals by entity only. I have set the correct Scenario and assigned the owners/approvers however when I start the approvals process the current owner is let sitting at no owner? Should this not pull though the owner set up under assign owners.
    When I log in as the owner of the planning unit I do get the option to promote the unit as set out in the assign owner hierarchy however when I attempt to do this I get the following error:
    Failed: Unauthorized New Owner
    I am relatively new to planning so any help you can provide me with would be much appreciated.
    Edited by: Bestie 279 on Aug 9, 2011 4:16 PM

    You might want to have a look at "Hyperion Planning Process Management Features explained By Example [Document 1226783.1]" in MOS.
    HTH-
    Jasmine.

  • Approvals (Process Management) question

    Hi everybody,
    In approvals (Bottom Up mode) we have an ability to set promotional path for Entity like Owner->Reviewer1->Reviewer2->etc.
    As I understand Owner can edit data for the Entity and Reviewers can't.
    Is it possible to give Reviewers ability to change data and to keep the promotional path like it was described?
    Thank you.

    Reviewer will not be able to write data to the intersection.
    Reviewers can only review the data and follow-up with a Reject, Promote, Sign off, Delegate, Originate or Freeze.
    Refer: Hyperion Planning Process Management Features explained By Example (Doc ID 1226783.1) in My Oracle Support.
    HTH-
    Jasmine.

  • Portal Approval Process

    Hi all,
    Problem:
    I have a lot of editors building pages for their individual departments but they need a approval from the administrators before they can publish their pages. I know there's a available portal in portal builder for "My Notifications" , "My Approval Status" and "Pending Approvals Monitor" to check whether is being approve a not but I can't find anywhere for editors to submit their pages for the administrators to approve.
    Question:
    How do I let editors to send their pages to the administrator for approval after they have newly finished their pages?
    Thanks for your help in advance!!

    Hello,
    in my opinion, the approval process can only be used for content item modifications, for example, adding a new document to a page, but not for pages themselves.
    Hope it helps,
    Felix

  • General Ledger - Revaluation/Translation Process Question

    Application Release Version: 11.5.10.2
    MRC: Not turned on for new entities. (See details below)
    My customer has been using oracle from around 2001 and went through a process at the end of 2008 to setup a new chart of accounts and approx 6 different companies with multiple entities for each across different functional currencies. (The initial setup for these entities was done prior to my joining and I have no supporting documentation on what decisions were made and why.)
    Setup info:
    Set of Books - 'Cumulative Translation Adjustment Account' defined as an 'Owners Equity Account'.
    Revaluation - Gains and Loss accounts using the same account number as 'Cumulative Translation Adjustment Account'. Accounts being revalued are accounts that have outstanding Payables and Receivables balances as well
    as our intercompany accounts that have outstanding balances. (Balances that need to be payed or received.)
    Question:
    My question refers to the revaluation and translation process for the new entites that have a different functional currency from the reporting currency. (All under the same chart of accounts structure.)
    For instance entity1 - Functional Currency = 'CAD' and has 'USD' transactions.
    I understand that at the period end we need to revalue the 'USD' transactions to there 'Current' worth in 'CAD' as exchange rates will fluctuate. But shouldn't the 'Difference', revaluation amounts, be pushed to the Unrealised FX Gains/Loss account, not the 'Cumulative Translation Adjustment Account'. (I think this is normally only used when a company is using MRC?)
    This obviously affects whether the period balance appears on the Balance Sheet or Income Statement report for the consolidated monthly report.
    Also should these 'Revaluation' journals ever be reversed or just left to accumulate?
    Then looking at the 'Translation' process, if value is pushed to the 'Cumulative Translation Adjustment Account' then the balance is translated based on the 'Average' period rate as the account is an 'Owners Equity Account', but this seems wrong for the 'Revaluation' balance to be converted at another rate?
    Any help on this subject will be greatly appreciated.

    Firstly, why would there be any difference between the total of customer/vendor sub-ledger balances and the balance on the reconciliation account(s)?  The posting to the reconciliation account is happening automatically right, when you are posting to a customer/vendor (basing on the reconciliation account assigned in the customer/vendor master)?  And system would not allow direct postings to reconciliation accounts, which eliminates the threat of reconciliation GL account going out of balance as compared to the sub-ledger accounts.
    However, you can run FBL3N or FS10N for the reconciliation account(s) and match it with the total balance on all customers/vendors using transaction FBL5N/FBL1N.

  • Snow Leopard Time Machine process question/possible problem

    For starters I want to say that I am not dealing with my own machine, but a friend's, so there's some missing information. Any help would be greatly appreciated!
    Ok, so my best friend bought a 15" MBP thru me during my short time as an Apple retail employee, which is how I got called in to "fix" it, although I'm still better with PCs than Macs. Anyway, it was purchased around December 2010, has at least Snow Leopard, intel i5 processor, 500 GB HD, not sure if 5000 or 7200 rpm, 4GB RAM. A day or so ago it started acting "weird" he says, like when closing google chrome the color wheel spun forever and took forever to close, and from then on every program acted the same; took forever to open and close. He said it was like there was some major process running in the background that was just using up all of the RAM and processor, leaving him with nothing to use for anything else. He shut it down and restarted it several times, but it acted the same. Sometimes he'd even have to force power it down. He then decided to do a wipe and restore with Time Machine. Thanks to google images I know for sure that he went thru all the bs with selecting what exactly to do, what restore to use, and where to install it, and that the transfer screen with the finder-to-fnder-like image and the progress bar appeared and completed fully before it automatically restarted itself. White screen with Apple logo appeared, he heard the boot up chime/BONG/WALL-E noise before the spinner wheel came up under the logo, which is where it stands now.
    The only question/concern is that it has been here for 10 hours, literally. Now the spinner is STILL spinning, that has not frozen that either of us are aware of, but both of us being so new to Macs we are completely unsure if it's ok. I did some online research and I've seen where people have had their macs freeze on boot up, but they usually don't chime; or it took like 14 hours to do the entire restore process, but they were significantly older and slower machines. Like I said, this could be status quo for this process, but I honestly do not know that. Feel free to just say "depending on the amount it's restoring, it could very well take that long, be patient" if that's the honest truth. I'm looking for verification.
    PS - his time machine backup is on an external USB hard drive, which is plugged in, and it's from November as he forgets to plug it in, but he has like photoshop and aperture, takes lots of pictures (yes we know those since November are gone), and honestly is on his MBP so much the only way I can think to describe it is that he literally uses it like a cheap whore.
    Thank you all!

    delete all drivers using the correct un-indtstall software, re-instalthe mac softeware and in stalll. GO TO SYSTEM PREFS, and select the printer and add the printer to the left side for install
    , then select that partictular printer.

  • Exception Processing Question -Reply

    I don't use Forte (yet--that's why I joined the mailing list), but since your
    question is a generic "engineering practices" question, I'll chime in. I do
    use exceptions both in C++ in Delphi, and have developed some opinions
    about how to use them:
    - Use exceptions for handling "behavior unexpected in the normal course
    of your algorithm". In other words, instead of returning error codes
    when something goes wrong, throw an exception.
    One example of this is in a parser: if you get an illegal token, just throw
    an exception.
    - When you need to make a choice based on a return status, don't throw
    an exception. In the parser example, if you get token 'A', you need to do
    one thing and if you get token 'B' you need to do another.
    - There's a fine distinction between "handling an error" and "making a
    choice", and there are cases where you could argue one way or the
    other. I'd say that an error throws an exception when it would normally
    terminate the normal flow of execution. For example, "out of memory" or
    "illegal token".
    - Catch exceptions at "high level" process start/end points, or where it is
    required to clean up resources held and rethrow.
    - Don't catch exceptions in every single method--it defeats the purpose.
    User Interfaces:
    - If your user-interface dictates a logical place to unwind no further,
    catch exceptions there. For example: In the Windows world most apps
    are a window with a menu. If you pull down and pick a menu item to
    execute a command, and that command throws an exception, the
    exception should be caught, a modal message box indicating the error
    should be presented, and then when the user clicks "ok", the program
    returns to its normal waiting state with the window intact.
    - If you have a modal dialog up, throwing an exception should either stop
    at the dialog's event loop or take the dialog down with it.
    I'd say that on-screen data validation should NOT use exceptions
    because "user typing invalid data" is expected behavior for a UI.
    Besides, the UI designer should be smart enough to deal with giving you
    a good model for data validation. OTOH, if you take the data out of the
    dialog and then pass the information as parameters to a function, and
    that function can't handle one of the parameter values, it should throw an
    exception.
    Nevertheless, if your dialog runs out of memory for some reason, it
    should throw an exception and the dialog should come down.
    Hope this helps.
    -- Conrad Herrmann
    Jerry Fatcheric <[email protected]> 07/24/96 03:29am >>>
    I have a toss up question for 50 points -
    We have finished the first phase of our project and have place
    exception processing in the places where we saw exceptions could be
    raise. But what about those other exceptional exceptions?
    Is this just good programming practice to have a high level generic
    exception handler (and what should it really do??) or is it critical.
    In addition, when handling data validation on specific widgets on a
    screen (e.g. the account number entered must be one of the existing
    10,000 valid ones), should this be handled via exception processing or
    should it just be handled with code in the event loop?
    Any opinions - please I don't want to hear the Forte Party line.
    I would like to hear opinions based upon real experience.
    Jerry Fatcheric
    Relational Options, Inc.
    Florham Park, New Jersey
    201-301-0200
    201-301-00377 (FAX) [email protected]

    We have finished the first phase of our project and have place
    exception processing in the places where we saw exceptions could
    be raise. But what about those other exceptional exceptions?
    Is this just good programming practice to have a high level
    generic exception handler (and what should it really do??) or
    is it critical.IMHO, you need to program for these ones that could occur because
    if you don't the exception will still happen except without
    your normal graceful (or standard) approach manner. I think it is good programming
    practice to trap on the ones you think can possible occur if they require
    something different in how they react. Otherwise, use of GenericException
    with a proper response is called for.
    >
    In addition, when handling data validation on specific widgets
    on a screen (e.g. the account number entered must be one of the
    existing 10,000 valid ones), should this be handled via exception
    processing or should it just be handled with code in the event loop?
    I use event loop processing because most of the time I am also
    keeping the user on the same widget after cancelling all events
    posted. So, in effect they are back where they started from.
    Any opinions - please I don't want to hear the Forte Party line.
    I would like to hear opinions based upon real experience.
    Jerry Fatcheric
    [email protected]@Sagesoln.com
    my 2 cents, or should I say my attempt at 50 points, Jerry.
    Len Leber
    ATG Partners

  • [BPM] Screenflow and Killing Interactive Process Questions

    Hi Guys,
    I have the following questions:
    1. How to kill an interactive activity? I tried to kill a process in an interactive activity via PAPI but it throws an exception:
    samplePAPI.activityAbort(target.getActivityName(), target.getId());
    AxisFault
    faultCode: {http://schemas.xmlsoap.org/soap/envelope/}Server
    faultSubcode:
    faultString: Operation exception.
    faultActor:
    faultNode:
    faultDetail:
         {http://bea.com/albpm/PapiWebService}OperationException:<message>Operation exception.</message>
    Operation exception.
         at sun.reflect.NativeConstructorAccessorImpl.newInstance0(Native Method)
         at sun.reflect.NativeConstructorAccessorImpl.newInstance(NativeConstructorAccessorImpl.java:39)
         at sun.reflect.DelegatingConstructorAccessorImpl.newInstance(DelegatingConstructorAccessorImpl.java:27)
    2. How to close a custom JSP in a screenflow through javascript. I have a cancel button which once clicked it will close the window.
    I hope someone can help me out with this.
    Regards,

    Hi,
    Sory, but I'm still not sure, how ADF comunicates with BPM (I know that it uses EJB services and hwtaskflow.xml). But a still don't have an answers for follwowing questions:
    1) I know ADF quite good. Having method in data controls (in our case getTaskDetails()) we need to invoke it somehow. I don't see anywher invokation of this method.
    2) In generated task flow there is some managed beans and params - what is role of them ? Having over 50 task flows , do I need it in all of them. Where can I find description of those beans and params
    3) In our approach we use BPM , ADF RC for UI and Business Components to persist data into database. Only data from payload we need is ID of master-level row. My question is - do I have to generate data controls for all human task ?. In my my opinion it should be only one communication point between BPM and ADF but not the same for all pair human task --> task flow.
    All infomation I need from BPM is:
    - task ID
    - task flow name (to open apriopriate tab in my application)
    - available outcomes
    - to know is BPM operation is enabled
    Kuba

  • OLAP Universe creation process questions and proposals

    We have created an OLAP universe based on a BW-Query. The automatical creation of the OLAP universe does not produce a satisfying result.
    We are working with the latest available releases (BOE XI 3.1 SP2 and SAP Integration KIT SP2, SAP BI 7 EHP1).
    We have detected that all dimension objects store the name instead of the key field.
    Example:
    Customer Dimension Object (L01 Customer) = Customer Name
    Customer Key Detail Object (L01 Customer Key) = Customer Number
    Customer Name Detail Object (L01 Customer Name) = Customer Name
    This is not usable for end user because of the following reasons:
    1. The detail objects can not be used for merge dimensions, so it is not possible to merge on the supplier number.
    2. If you filter on the dimension object you will only see the text in the list of values (LOV) and it is not possible to edit the list of values in the universe to add the supplier number to the LOV as it is possible in relational universes
    3. If the user select the detail object always the dimension object in inserted into the report query
    4. The "Business Explorer" general setting "Display" of an InfoObject has no effect on the OLAP universe dimension object. If you change it to key always the text is shown. Even if you change the "ValueDisplay as" in the underlying BW Query to "key" is has no effect.
    5. The renaming of the L01 object to blank is not possible. You need to rename to " " and then remove on each object the blank.
    So we need to modify manually every universe to change the "detail key object" to a "dimension object" and the "detail name object" to reference the new "dimension object" with the key. This manual process has a huge work effort in time. Is there a better solution or enhancements planned in the next releases?
    Additionally there should be an option to disable the automatic creation of each characteristic as a subclass in the universe. A wizard should ask if a subclass should be created or not for each characteristic. Currently there are to many subclasses generated which were mostly not needed.

    Hi,
    First of all I would say u are lucky to start with SP2. Because whatever modifications you do in Universe those are retained.
    We had a big trouble in using BOXIR3.1 FP1.7.
    Anyways.. Back to your Questions and My asnwers for those:
    1. The detail objects can not be used for merge dimensions, so it is not possible to merge on the supplier number.
    Ans: True, Dimension object always shows Short text values by default. but if you can create the logic at SAP BI query level to map short text with keys then your problem will be solved.
    2. If you filter on the dimension object you will only see the text in the list of values (LOV) and it is not possible to edit the list of values in the universe to add the supplier number to the LOV as it is possible in relational universes.
    Ans: True u cannt edit LOV, but alternate solution to it is create the variable in SAP BI Query, that will appear as prompt in universe which will display the List of values with Key as well as Description.
    3. If the user select the detail object always the dimension object in inserted into the report query.
    Ans: Logically its correct, because Detail object is always associated with Dimension. Buit if you dont want that dimension in query you can remove that dimension by dragging back.
    4. The "Business Explorer" general setting "Display" of an InfoObject has no effect on the OLAP universe dimension object. If you change it to key always the text is shown. Even if you change the "ValueDisplay as" in the underlying BW Query to "key" is has no effect.
    Ans: In Query designer even if you ValueDisplay as "Key", but at Object level  if there is Text and Key associated for perticulat Infoobject, then so by default the dimension will show the Text and there will be seperate Detail object in universe for Key.
    5. The renaming of the L01 object to blank is not possible. You need to rename to " " and then remove on each object the blank.
    Ans: Yes this is a big trouble.
    Regards,
    Nisha

  • Planning approvals process in 11.1.2.2 - "approved" to "Not started"

    Hi
    We are on Planning 11.1.2.2.Last year we have used a planning unit  hiearchy with "Custom" for Enable approvals and "Free form" template options. Now the planning unit is in "approved" status as budget process is completed last year.We are planning to kick off our next year budget.
    How can i change the workflow status to "Not Started".
    Please suggest
    Thank you

    You will be using the same planning units and same approval process, wont you? all you need to do is to start them again.
    Remember: Once an administrator excludes a Planning Unit, all annotations and history associated with the Planning Unit are discarded. The Planning Unit's status is returned to Not Started and the owner is set to No Owner. However, the data values are retained. The data retained will include the Supporting Detail.
    Cheers..!!
    Rahul S.

  • TR Background processing question

    To All
    We currently receipt stock in MIGO and get a GR slip. Then we use LB10 to putaway using TO in Foreground. My question is what config do I need to set up to use TC in Background? What paperwork is generated to advise staff where to put stock if TO in Background is used? Is there a 'putaway' list when the background processing is selected.
    We currently have no other warehouse stock strategies. (No fixed bin management, no capacity check, etc)
    We currently use the material master default bin (which is printed on the GR slip) to suggest the putaway location.
    I want to get away from using TO in foreground to speed up putaway processing
    Regards
    Darren

    Darren,
    TO or TC or both ?
    For immediate TO creation:
    In config.
    LE \ WM \ Interfaces \ IM \ Define Movement Types
    In the second table, according to the parameters you want e.g. Movement Type, set 'A' in the 'Immediate' column
    Alternatively consider background generation (by prog. RLAUTA10) by setting per movement type.
    In config.
    LE \ WM \ Activities \ Transfers \ Set up Autom. TO creation
    And step through the settings.
    Regards,
    Nick

  • Sales process- questions

    Hi SAP Prof,
    Iam a fresher and joined in SAP Company. and we r dealing with power batteries , The client is sells the batteries to other customers , for govt bodies, export sales, OEM Sales r there.
    My question is that
    I want a list of questions on the topic , sales process, From Inquiry to Billing.  i.e., inquiry, quotation, order, delvry, PGI, Billing.
    Here in this sales process. , what might be the questions can be asked nearly 10 questins r expected as per clients reqt.
    I think u have to understood my question

    Hi SAP Prof,
    Iam a fresher and joined in SAP Company. and we r dealing with power batteries , The client is sells the batteries to other customers , for govt bodies, export sales, OEM Sales r there.
    My question is that
    I want a list of questions on the topic , sales process, From Inquiry to Billing.  i.e., inquiry, quotation, order, delvry, PGI, Billing.
    Here in this sales process. , what might be the questions can be asked nearly 10 questins r expected as per clients reqt.
    I think u have to understood my question

Maybe you are looking for

  • My swing application is too slow

    Hello my application is an add-in swing application. It is connect with a posptgres database to show and edit data in this database. The application has about 10 frames and dialog. It run very slow. It may take 20-30 seconds to close a dialog or fram

  • FLVs created with ADOBE MEDIA ENCODER CS6 do not display thumbnails in ADOBE BRIDGE CS6

    Could you please attempt to shed some light on why FLVs created with ADOBE MEDIA ENCODER CS6 do not display thumbnails in ADOBE BRIDGE CS6, yet apple finder is able to display thumbnails for these same FLVs without issue? I'm running CS6 Production P

  • On outer Join Query

    Hi All, I have a outer join query which is creating bottlenecks and increasing the cost of the query, the plan of the query is pretty awkward with multiple nested outer loop joins. Though its the requirement for me to write such a query. I would like

  • Business Partner : Mass upload

    Hi Experts,      I have to upload some15 million Business partner through BP transaction . I want to know what will be the most suitable method to attain that. Should I use BAPI, BDC , LSMW ?? I am not clear at all, what should be the most appropriat

  • Error reading memory - W3WP.exe after running rpt