Posting of semi finished products

Hello Everyone,
I had an issue regarding posting of semi finished products. Earlier during production, Production executives had created some production orders for semi finished products and had not transferred the corresponding quantities to the store. Still production continued for the top level finished products and GR has occured for the same. Later these production orders for finished products were also set the status TECO.
Now upon analysing the system still shows the production orders open for the semi-finished products. Now its practically  impossible to trace back against which superior level order this semi finished order is raised.
Moreover since these orders are still open, the system does'nt raise additional orders for the corresponding quantities wheras these orders were raised earlier for previous orders.
I would greatly appreciate any help to tackle this issue.
Sincerely,
Aji Kurian Mani
Edited by: Aji Kurian Mani on Jan 11, 2010 6:48 AM

Hi,
Pls run the optimiser with prod = A and Loc = A+B
It should work fine. Also in the t code /sapapo/mvm, check if the check box for 'No planned orders without source of supply' is clicked or not. If it is clicked, then you need to maintain a PPM for prod A at loc B. If it is unchecked, optimiser will create planned orders for A at loc B even without a PPM.
Pls let me know if this helps.
Regards
Manotosh

Similar Messages

  • MIC's of finished product should get transferred to Semi-finished product

    Hi all,
    I have the following requirement
    Based on the Customer requirement, sales order will be created. Two line items will be created in the sales order.
    First item: 100kg
    Second item: 5 kg (this will be the sample to be sent to the customer for approval)
    first item and second item will have different material codes.
    Now the process order will be created,released and confirmed. 04 inspection type will be activated for the material.
    The MIC's of the finished product ( A) should get transferred to the semi-finished product (A1)
    For X customer the MIC's for finished product (A) is a1, a2 and a3 and same should get transferred to semi finished product (A1 )
    For Y customer the MIC's for finished product (B) is b1, b2 and b3 and same should get transferred to semi finished product (A1 )
    The material code for the finished product will be different, but the semi-finished product (A1) will be same always.
    When ever inspection lot gets generated the MIC's of the finished material should get transferred to semi finished product
    Kindly provide your valuable inputs to address this scenario
    Regards
    Hari

    I think I understand what you are attempting to do.  The bottom line is that you are trying to use one material number to serve as the "sample material" for all your products.  Lets call the sample material mrtrl# 9000122.
    You have a make to order process so you first create a process order for the product and inspect it according to the customer's requirements.  You make the UD.
    Now when you make product A, you want those characteristic MIC values to copy to the sample material 9000122 inspection lot which is created from a separate process order using product A as the raw material.
    When you make product B, you want those MIC charcteristic values to copy to the same sample material 9000122  to an inspection lot created from a separate process order using product B as the raw material.
    I am guessing the intent is to keep the batch number the same between the FERT product batch number and the sample material.
    I would like to suggest to you two other alternatives which I'm not sure will work for your design but I think it is worth a try and might save some work. 
    1)  Have you looked at setting up your sample product as a by-product of the first process order?  You can confirm the finished qty and the sample qty from the same original process order.  This will then create your two 04 inspection lots.  You would recrod results on the first primary product. Then enter results recording and I think you'll be able to have that set up to copy over the resutls from the primary product.  If you can't with the standard SAP, I beleive you'll find the ability in copy inspection results to add your own custom FM that would do the copy for you that you are looking for.
    Of course the inspection plan for the by-product sample will have to have all the characteristics in the plan that could ever be expected from any primary product using this process.
    2) The other possibility would be to just have the person making the UD on the primary inspection products inspection lot, to post a sample qty "to other quantity".  They would always of course post to the sample material.  If the characteristics in the lot match up to general characteristics in the batch class for the sample, the resutls will be transferred to the batch.  Report your sample reuslts from the batch record and the specs from the inspection lot in the COA.
    FF

  • Transfering Semi finished products

    Hello Everyone,
    I had an issue regarding transferring of semi finished products to stores. Earlier during production, Production executives had created some production orders for HALB and had not transferred the corresponding quantities to the store. Still production continued for the top level finished products and GR has occured for the same. Later these production orders were also set the status TECO.
    Now upon analysing the system still shows the production orders for open for the semi-finished products. Now its impossible to trace back against which superior level order this semi finished order is raised.
    Moreover since these orders are still open, the system does'nt raise additional orders for the corresponding quantities wheras these orders were raised earlier for previous orders.
    I would greatly appreciate any help to tackle this issue.
    Sincerely,
    Aji Kurian Mani

    Hi,
    A suggestion:
    Since you mention the children were not issued to the parent orders, but yet the parent orders were completed & TECO'd in the system, run COOIS report by selecting Components as the list option & entering the components for component & tick the checkbox reduced reading for which you're facing this issue.
    Now using filters, exclude components which are deleted & issued completely. This should give you a finite list of orders for which these components havent been issued. Now you will know to which orders these components need to be issued. Having said that, before proceeding to post these components to the SFO's check with your finance personnel as many of these SFO's could have already been settled.
    Regards,
    Vivek

  • Automatic creation of purchase requisition for semi-finished product HALB

    Hi Gurus,
    We want the MRP to generate automatically a purchase requisition, instead of a planned order, for a semi-finished product.  Of course, we still want to be able to convert it to a planned order.
    thanks
    Jean-Francois Millaire

    Hi Jean-Francois Millaire,
    You want a purchase requisition after MRP run & you should also able to convert that purchase requisition to planned order,If i understood correctly, hope this is your requirement
    First one is possible -in MD01/MD02 maintain create purchase requisition as "1"
    Second is not possible,its not possibel to conver a PR(purchase requisition to Planned order where as vice versa is possible
    confirm my understanding,pls revert if you differ
    Regards,
    SVP

  • Valuated Sales Order stock for Semi-Finished Products

    Dear Gurus,
    One of my client faced the issue that the semi-finished products is valuated-sales order.  We are in Mill Industries, downstream (steel processing).  The situation is:
    1.  We use configuration material for both finished and semi-finished products. Both are valuated at standard costs with valuated sales order stock.
    2.  Once the sales order is created, the cost estimates are created for both Finished, and semi-finished products.
    3.  The production orders is created for the semi-finished products.  During production, several semi-fg and fg can be manufactured at the same time.   We are using the co-products feature to cover that.
    4.  During the goods receipt of semi-finished products, instead of using the standard costs in sales order cost estimate, it use the planned costs in production orders which against our design.
    I tried to use the user exit COPC002 and influence the standard costs.  But it seems that the routine is not called for semi-fg at all.  Anyone has any light on this?
    Regards,

    Hi
    I think you are talking about Special Stock "E"...ie) Sale Order Stock...
    If my understanding is correct then,
    If you go and see the Table T156....For the
    Movement Type: 101,
    Special stock Indicator : E,
    Qty. Updation Checked,
    Val. Updation Checked,
    Movement Indicator : Against PO,
    Consumption Indicator: Sales Order Stock.....combination....the transaction Event Key....GBB only has been Assigned....these  settings you cannot change...
    This linkage you can view in OLMW-----> Account Determination -
    > Acc. Determination W/O Wizard -
    >Account Grouping....also
    Reward if useful
    Regards
    S.Baskaran
    Edited by: baskaran srinivasan on Dec 20, 2007 12:18 PM

  • Creating a production order for a semi finished product

    Hi
    I am having a multi level bom scenario over here.
    one of the bom components of the header material is a semi finished product.
    I am using the planing stratagy 40 for that material.
    in standard sap when i create a production order for  header material. the requirement gets transerd to all the components. if the components are not available then only  a requirement is placed. when i run MRP that requirement gets converted in to a planned order. which converts in to a purchase req or a production order,
    well for my semi finished product. its a Work in process item. there wont be any stock for that item in the storage location any time.
    what my requirement is. when i create a production order for my finished product it should automatically create a production order for the semi finished product.
    is this possible with some configuration settings.

    Dear Deepu,
    for ur requirement u need to maintain MRP type PD for FERT material and also for ur HALB.
    If u run  MRP  only, it will create planned order for FERT and for all its dependent requirement(for PD).
    If u create order manually for FERT material then it will not create order for HALB material, u need to create manualy for this also.
    sree

  • Creating  finished-product with necessary semi-finished product with BAPI

    Hi,
    I really need help to be able to save materials made up of several parts with BAPI.
    Let me show you the idea by using the example of car (finished product):
    Car is built from a lot of components, for instance:
    - 1 engine
    - 4 tires
    - 2 front lights
    etc.
    My task is to implement a method responsible for creating a finished product and all necessary semi-finished products which are connected with ready prod and save them in SAP. Furthermore I've got to create a bill of materials.
    Has somebody faced such a problem? How have you solved it?
    Looking forward your answers.
    BR,
    Rafal

    ok....but do u know which option I am supposed to enable to create BOM?
    According to my best knowledge there is no BAPI to create BOM...i tried to find.
    I found out that I have to create material master record for trading goods(type: HAWA ) and create Semifinished products (HALB) by using BAPI_MATERIAL_SAVEDATA (hopefully I'm right), but I still don't know how to connect them with each other and then use to create BOM.
    Every help will be warmly appreciated.
    If somebody may provide me an example it will be great.
    BR,
    Rafal

  • STO for semi finished product along with returnable package

    Dear Experts,
    I am transferring semi finished product along with returnable package from Manufacturing to depot, for that i am creating purchase order (two line items in po, one is semi finish and other is returnable package) and creating delivery through VL10B.
    system creates delivery, showing the item category NLN for both line items i..e semi finished and returnable package and billing(vf01) is coming for both item.
    my requirement is billing to be only semi finished, returnable package should be update only qty billing should not coming for returnable package
    for that which item category have to maintain and where it maintain for returnable package and how it flows from mm to SD?
    Regards
    sai krishna

    The packaging’s material master record should use the material type VERP for packaging and the item category group LEIH. The item category group LEIH is the SAP standard for returnable packaging.
    TAL (the item category for returnable packaging) in the shipping unit
    header, then when you create the delivery, SAP will also create an item TAL for that shipping material in the delivery. When you goods issue the delivery, SAP will record that this shipping material has been issued to the customer and must be returned. Note that you only have to price the returnable packaging in the returnable packaging issue order document. It does not need to
    be priced in the sales order and cannot be in this method.
    Check if this all ok, rest please note returnable packaging material behaves in same way as packing material

  • Authorisation for Semi Finish Product Only....

    Hi Experts,
    I want to give authorisation for MM01 transaction and for only material type 'Semi Finish'. How to give only for Semi Finish to create?
    For display I want to give full authorisation ?
    YAB
    Message was edited by:
            YUSUF BHORI

    1. Use transaction MMB1 which is specially designed for creating semi-finished products. However I don't know of this really blocks the road for creating materials of another type.
    2. If you really want to authorize on Material Type you need to set an authorization group on the material type. In SPRO: Logistics - General --> Material Master --> Basic Settings --> Material Types --> Define Attributes of Material Types. Select Material Type HALB and type in a ctext of your choice in the Authorization Group field (tip: just use the name of the Material Type: HALB).
    Restrict on Authorization object M_MATE_MAR as follows:
    M_MATE_MAR
      Activity                    01, 02
      Authorization Group  HALB
    M_MATE_MAR
      Activity                    03
      Authorization Group  0-HALA, HALC-Z
    Good luck!
    Points are always appreciated!
    Kind regards,
    Lodewijk

  • Moving average price for semi finished products

    Hi
    Could anyone light on this issue,
    Our client maintain moving average price for the semi finished material, need clarification on below points
    1)  What is the advantages and disadvantages due moving average price,
    2) Which price in the material master after the production order settlement,
    3) Is there any impact of this on WIP calcaultions
    Thanks in advance
    Mohan M

    Hi
    there are no advantages of it, ONLY Dis Advantages!!!
    That will ruin your inventory valuation forever.. Consider the eg below if your price control is V
    1. Your moving price in mat master is 100 USD
    2. You Mfr on Jan 1 @ Actual cost = 110 in Prod order and Qty = 1.
    Upon GR, GR will happen @ 100 and at period end if Qty is lying in stock, 10 variance will also be inventorized
    BUT, now consider this
    1. 1. Your moving price in mat master is 100 USD
    2. You Mfr on Jan 1 @ Actual cost = 110 in Prod order and Qty = 1.
    Upon GR, GR will happen @ 100 and variance lying is 10 in prod order
    3. You Mfr on Jan 10 @ Actual cost = 110 in Prod order and Qty = 1.
    Upon GR, GR will happen @ 100 and variance lying is 10 in prod order
    4. On jan 15, you consume Qty 1 and qty lying in stock is 1
    5. In period end, when you do settlement, following will happen
    a. For prod order 1: Qty Mfd 1 and Qty lying in stock 1 - Result: variance 10 will be inventorized.
    Mvg Avg price will shoot upto 110
    b. For prod order 2: Qty Mfd 1 and Qty lying in stock 1 - Result: variance 10 will be inventorized.
    Mvg Avg price (MAP) will shoot upto 120
    System wont check whether the qty lying in stock pertains to prod order 1 or 2... It will simply check if the Qty of prod order matches with qty lying in stock. hence, it will keep on inventorizing variance in this case.... and your MAP will touch the sky
    Regards
    Ajay M

  • Scheduling semi-finished products

    Hi Gurus,
    Am working on a food industry implementation.
    The scenario is that bulk quantities of product manufactured are packed in cans. Cans are part of BoM-semi-finished material.The cans are produced simultaneously and fed into the packing lines to pack the bulk material into cans.
    The requirement is to schedule the can production simultaneous to the finished product production.
    When am carrying out backward scheduling the system presumes that the cans should be readily available before packing operation starts - this is not the case.
    If forward scheduling is carried out the requirement date is taken as the order start date for both the finished goods as well as the cans.
    Have tried to use the lead time offsets in the BoM item details. But not getting the desired result.
    Any help on the subject will be appreciated.
    Tarang

    Hi,
       I have not worked with this.. Just check with the below:
    Take takt time=1 (in days only)  and check if the Production Order-1 overlaps with Production Order- 2.
    Also, check the foll: (taken from help.sap.com)
    You can define the overlapping for each lot-sizing procedure. Here, you must maintain the following additional parameters in the material master record:
    You must maintain the cycle time (MRP data screen) for all lot-sizing procedures. The cycle time defines the number of days that the planned orders are to overlap each other.
    For the fixed lot size, you must enter the partial quantity to be used for splitting in the field Rounding value.
    For all other lot-sizing procedures, you enter the partial quantity in the field entitled Maximum lot size.
    -Thaila Shree

  • Initial Stock Posting for Semi Finished Goods

    Dear Friends,
    I have a small doubt in Initial Stock Posting.
    Is Initial Stock Posting for Semifinished Goods (HALB)?
    Or Initial Stock Posting available only for Finished Products?
    Please answer this.
    Regards,
    Rajesh L

    Hi,
    MB1C + 561 can be used for all of your goods from which you want to keep stock. So, raw materials, SFGs, FGs can be uploaded based on your business requirement.
    Your material masters should be extended to the suitable organisational levels (plant, SLoc, WH), so suitable material master views should exist at proper organisational levels.
    Regards,
    Csaba

  • Incorrect Initial Stock calc for Semi-finished products in SNP PBook

    Dear all,
    Situation is as follows:
    The Stock list on /SAPAPO/RRP3(Product View) matches the Stock in ECC (MMBE) perfectly. Also when we load the product in our SNP planning book, right click on the Stock on Hand and then Display Stock, it matches the RRP3 and the ECC stock.
    Still the actual Initial stock displayed in the Planning book Cell in the initial column and thereafter is different from what the actual sum of stocks should be. This quantity is huge (in millions!). There is no Receipts planned which can contribute to this!!!
    Is this a known bug in SAP? Can we rectify by running any programs?
    Note: Already tried CCR, OM17, everything looks fine (which actually is because RRP3 view matched ECC perfectly.)
    Kindly help.
    Regards,
    Rimjhim
    Edited by: TEAM BASIS on Dec 18, 2008 4:00 PM

    Hi ,
    I couldn't find any problem with the macro.
    One more observation:
    The UOM in ECC is KG (in transaction MMBE). The base UOM in APO is ZUN (customized Tonnes).
    The conversion in Prod Master is 100 ZUN=7484 KG
    If we change this conversion to 1 ZUN = 1 KG then in the planning book the Initial Stock start showing as OK.
    The random value shown earlier doesn't seem connected to the UOM conversion, it's just a very very high value. How can there be a connection between UOM conversion and the Initial Stock display.
    Any ideas?
    Regards,
    Rimjhim
    Edited by: TEAM BASIS on Dec 19, 2008 12:47 PM

  • Semi finished products

    Hi all,
    I have the following issue that I am working on.
    There is a situation where there are two plants in two locations. When there is a demand in plant A for semifinished product A the demand is propagated to plant B for production(though the two locations are plants it is a business requ). So the situation is tested and working well in ECC. Procurement type for loc A iF and special proc type 71(procured from loc B) is maintained). When the demand is created for plant A and when MRP is run, purchase req and planned orders are created for material A in plant B.
    The same situation is to be simulated in APO SNP using optimizer. To plan the mat A for loc A and B in APO and convert the planned orders to production orders in ECC.
    I have cifed, materials, BOM,created trans lanes , maintained SNP optimizer settings in APO and ran optmizer for loc A and material A combination. This generated planned orders in rrp3 view. Now the issue is that I cannot see the planned orders and purchase req for mat A in loc B. And also no planned orders are seen in ECC.
    Please provide a detailed explanation and further steps.
    Sai

    Hi,
    Pls run the optimiser with prod = A and Loc = A+B
    It should work fine. Also in the t code /sapapo/mvm, check if the check box for 'No planned orders without source of supply' is clicked or not. If it is clicked, then you need to maintain a PPM for prod A at loc B. If it is unchecked, optimiser will create planned orders for A at loc B even without a PPM.
    Pls let me know if this helps.
    Regards
    Manotosh

  • Transfer Semi-Finished to Storage in No Production Plant

    Dears Experts:
    I have the following scene: I need to send semi-finished products manufacturing anticipatedly to be stored in another no productive plant (transference between plants) for problems to storage. Comming soon the date to manufacturing the finished product (final assembly), these semi-finished products will be brought for the productive plant. The problem consists that in the sending the semi-finished for the no productive plant the reservation still open (final assembly order not confirmed ) and generates new planed order in the next MRP run. I tried to use special procurement type (transfer and production to another plant), but the system identifies recursivity, or modifying the plant in reservation manually, or mark field final issue, but it is with too many manual alterations. If somebody will have some suggestion, is thankful.
    Ricardo Siqueira

    Mario:
    Thanks a lot for your repply. I need use the stock to transfer material for other plant in MM standard business process "Transfer Between Plant" (create transfer purchase order - ME21N, create delivery to transfer purchase order - VL10B, etc...). This process create the legal document to transit with product, that in brazil call "nota fiscal". In its your suggestion, it would be necessary creates NF Writer, and it would also occurs phisical inventory problems, a time that the material would be physically in storage plant and logically in productive plant, in the case of auditorships.
    Best Regards,
    Ricardo Siqueira

Maybe you are looking for