Hi Guru,
Can someone advise me on how SAP can handle this scenario?
1) PO created
2) GR
3) Invoice received.
4) Email received that there is a price increase for this material. No PO reference is given as this is an intercompany purchase
How do i pay the vendor and at the same time adjust the inventory value only(quantity not adjusted) in this case?
Initially, I was thinking of doing the subsequent debit. However, subsequent debit needs PO reference or some documents reference which I don't have.
Thanks in advance on the help.
Regards,
Zhulk

do you really pay just on email notifications?
Isn't it a legal requirment to receive a debit note?
Further ask your vendor (especially if it is an internal vendor it should be easy) for which POs the price increase takes place.
Further you can search for POs with various transactions in SAP.

Similar Messages

  • Post Goods Issue without reference to order

    Dear All
    We are using both Account and Costing Based COPA. We do post goods issue without reference to order. Now our problem is that at the time of post goods issue there is no Profit Analysis document posted in the system  and Profit Segment field is not modifiable. We have marked the field profit segment optional in movement type 601.
    Please let me know what can be the problem.
    Regards
    Farhan Qaiser

    Check the field status variant on GL (OBC4)

  • Posting Subsequent Debit via EDI(MIRO)

    Hello All,
    Any idea how to post the subsequent debit or credit via EDI using transaction code MIRO. We were able to post invoice/credit memo through EDI but not subsequent debit/credit.
    Advance thanks for the reply.
    Thanks
    MP

    Hi
    Posting of subsequent debit and subsequent credit is not possible using EDI for invoice verification.
    When you transmit invoice information via EDI, you
    Cannot create subsequent debits
    Cannot settle planned delivery costs
    Cannot post with varying purchase order units of measure
    Cannot post invoices for blocked purchase order items
    Please check the link
    http://help.sap.com/saphelp_erp60/helpdata/en/44/f50abcea3b11d194dc0000e83dd751/frameset.htm
    Thanks & Regards
    Kishore

  • What is SAP procedure to post credit memo without reference

    Hi,
    I was wondering what is the standard SAP solution for posting a credit memo to a customer without referencing the original sales order.
    The goal is to not have to create a return sales order or post only a credit memo invoice against the original order. I was wondering if this procedure exists? I just need to be able to post the credit to the customer, no refernce necessary.
    Also, Let's say we want to issue a partial credit back to the customer. Is there a way to do this without reference. I would actually like to know what are the best recommended ways for using both with and without reference to the original sales order.
    Last item. After the credit is posted. What is the best way to reverse the payment. Should I use txn FB08?
    Thanks for your help,
    Best, Erik

    Thanks G. Do you happen to know how to reverse out the payment with or without reference to the original order?
    For instance. I want to reverse multiple payments out together by grouping the a total. So basically i will group the total credit memo balance and post in FB70..Then i need to group the total payment balance and post. Is there a procedure for the payment portion.
    Thanks again for your help.

  • Posting Inbound Delivery Without Reference using IDOC_INPUT_DESADV1

    Hello Experts,
    We have a scenario wherein we are required to post an IDoc into SAP which represents an Inbound Delivery without any reference. We tried using standard FM IDOC_INPUT_DESADV1 with below details to post an IDoc for an Inbound Delivery without any reference-
    Message Type    DESADV
    Basic type      DELVRY07
    However, we are not able to do it. Can you please advise any inputs how this can be achieved?
    Regards

    Have a look into OSS note 666591 - DESADV with text items without material number not postable
    It is actually older and fixes a certain issue, but the solution describes how it is designed. And there is it very clear that in case of material with  material number you need to have a purchase order reference.

  • Revaluation run (MRNB) v/s Subsequent Debit / Credit (MIRO)

    Hello Experts
    We are working on ECC 6.0.
    I'am aware how to use MRNB & posting subsequent debit / credit note through MIRO.
    I want to know when to use MRNB in comparison to Subsequent Debit / Credit?
    Suppose vendor has suppiled certain goods at Rs 100 per unit. Invoice have already been posted against the GRs. Now the vendor asks for additional Rs. 2 per unit.
    In such a scenario should MRNB or Subsequent credit is to be posted?
    I've noticed that when MRNB is used material MAP remains unaffected unlike posting a Subsequent Credit / Debit. Why it remains unaffected during MRNB run? If the material price is changed then its impact should also come on inventory which doesnt happen in MRNB.
    For both the cases is excise claiming to be adjusted through J1IH manually ?
    Regards
    Kapil

    Hello,
    Subsequent Debit and Credits
    After an Invoice is successfully posted and the transaction is completed, Vendor approaches with additional amount invoice or correction in Invoice.You would like to post this additional invoice with reference to the original PO and item. Subsequent Debit / Credit functionality allows you to capture this difference without canceling original invoice.
    Please check this link
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/a8/b99890452b11d189430000e829fbbd/frameset.htm
    Regards,
    Shailesh

  • Subsequent delivery and subsequent debit

    Dear All,
    material type: NLAG
    account assignemnt (PO): cost center, non valuated GR
    Scenario:
    1. GR (MIGO) - material_document1, qty 100
    2. IR (MIRO) - invoice1 for material_document1, qty 100
    > vendor makes correction because qty is more or less than the original
    3. GR (MIGO) - material document2 - qty 20 (sum qty for PO item is 120)
    4. IR (MIRO) - subsequent_debit1 for 20 pcs
    These connections / links should exist:
    Material_document1 - invoice1
    Material_docuemt2 - subsequent_debit1
    My question
    How can I solve this? Is it posible to book the subsequent debit with reference to material_docuement2?
    If I create the subsequent invoice it is valid only for material_document1 EVEN IF I do material_document2 as SUBSEQUENT DELIVERY in MIGO (in this case the two material documents are connected). SAP expects an additional invoice for material_document2 (but it is linked to material_docuement1!).
    In my opinion it cannot be solved since the debit/credit memo refers to the "original" material document (1) and invoice (1).
    Thanks,
    Csaba
    My question was a little bit incoherent...
    I wanted SAP to suggest the to-be-credited qty&value automatically in case of returns to vendor - but it's not possible in standard system as per my best knowledge .
    Edited by: Csaba Szommer on Mar 4, 2009 9:18 PM
    Edited by: Csaba Szommer on Mar 4, 2009 9:22 PM

    Hi Bala krishnan,
    when there is a price difference this entry would takes place. while reversing the same should be reversed, in your case the system is posting to another account.
    please check the account key against the wrong line item ( this you can see with the help of changing layout), then goto OBYC and check the gl accounts assigned against that. To check either it is right or wrong compare with the standard/default company codes settings i.e 0001 co.cd.
    Thanks & Regards,
    Shashi Kanth.

  • Subsequent debit

    Dear experts
    Below is my company scenario,
    We did the GR in reference of PO in Dec.
    but now we received a Debit note (stated 1 material is free of charge).
    SAP only allow us to post LIV followed by Debit note. but the problem is that vendor only gave us the debit note instead of invoice.
    Any idea how to resolve this issue?
    Thanks in advance.

    Hi,
    you are trying to post subsequent credit for the PO for which you have not posted the invoice .That is why you are getting this error.
    It is mandatory that inovoice must have posted prior to post subsequent debit/credit .In your case you have not posted any invoice ,then you have to use direct posting option to post directly to material or GL account
    or First post invoice then post subsequet credit .
    hope it clarifies

  • Subsequent debit Vs FI invoice

    Hi,
    I have posted an MM invoice against vendor PO.
    But now venddors sends me  an invoice for some additional charges he incurred .
    What is the impact if I post an FI invoice directly through FB60  for additional charges instead of Subsequnet Debit?
    Which one should be prefered?

    Hi Harikrishna,
    thanks for your reply.
    We observe that there is no limit for amount whihc we can post with subsequent debit.
    I mean if PO value is Rs 10000, PO is released then invoice posted for Rs. 10000.
    But then user can post subsequent debit for any amount. Is there any way to restrict this subsequent debit amount whihc can be posted with reference to PO?
    thanks
    Manoj

  • BAPI or FM to create Invoice in SRM , without reference to PO ?

    Dear Colleagues,
    We have a situation where we have to create invoices in SRM from a file from a legacy system, that means we have no POs in SRM.
    Which process, BAPI or Function Module would you recommend me? Is it possible to create "standard" invoices in SRM with a BAPI, and have those invoices be displayed afterward in the standard SRM functionality/transactions, plus have a subsequent invoice created in the backend?
    Will award point to helpful answers.
    Many thanks,
    David

    Thanks for your help, but I still dont know which FM is best, or what is the difference.
    Can i use this FM to post an invoice without reference to a PO? How do I fill/pass the vendor and item data? Do you have any example on how to pass the data to the FM?
    Which FM are called by the system when a vendor creates a NON-PO Invoice? Any idea?
    If I use the FM to transfer to backend, will the invoice go through all standard verifications in SRM and R/3?
    Thanks again, regards
    David

  • Invoice without reference in SRM not viewable in R/3 controlling

    Hi All,
    I am on extended classic scenario in SRM 4.0. When I post an invoice without reference to a PO in SRM, the invoice gets created in R/3. However in R/3 when I view these entries in controlling reports such as transaction KOB1 or KSB1, I am unable to drill into the line items to display the document. I get the error message "Original document is not in the local system".
    This seems to be only for controlling reports, as I can drill into the line items in finance reports such as FB03.
    I have applied note 682441 in R/3, but still face the same problem.
    Can anyone tell me if they have the same problem?
    Thanks,
    Paula.

    Hi Paula,
    Sorry to intercept.
    I am facing an issue while creating the Invoice without reference to PO. My system is SRM 5.0 with Extended Classic scenario active. May I request you to share your insight on the settings to be made to achieve this functionality.
    Also, I would be glad to have few words on creating the invoice with reference to local SRM contract.
    Thanks in anticipation.

  • Subsequent debit for a vendor before invoice??? (URGENT!!!!!)

    hi all,
    i want to post subsequent debit for a vendor before invoice.  but the system is giving a message "The quantity to be debited/credited cannot be any greater than the quantity invoiced so far."
    can anybody tell me how to post subsequent debit before posting the invoice (i haven't got the vendor invoice yet but i must pay the freight cost).

    Hi,
    Subsequent debit : Rarely, you receive from your vendors invoices or credit memos that refer to transactions that have already been invoiced. Your company wants to use subsequent debits/credits to process these documents. A subsequent debit/credit changes the total invoice value only of a purchase order item but the total invoice quantity remains unchanged.
    The processes are:
    1)     Subsequent credit or even subsequent debit is done when total “VALUE" of invoice is changed.
    2) Total invoice Quantity is remained same.
    3) Only value based transaction takes place & not quantity base.
    4) If credit memo is received from memo then subsequent credit is done in MIRO.
    For example vendor has submitted invoice of 100 Qty for Rs 1000 & we have posted the invoice & subsequently he realized that he has invoice for higher price i.e. it should have been actually 900 Rs as against Rs 1000 .In this case he will send a credit memo of Rs 100 for which we will be doing subsequent credit.
    5) This is done for PO items if an invoice is already posted
    6) cannot refer to particular invoice
    7) Listed separately in PO history
    8) In PO total values is updated but not Quantity.
    For ur case you can pay to Vendor(freight cost ) by selecting Planned Delivery Cost instead of Goods/Services items in MIRO T.Code
    Regards,
    Biju K

  • Subsequent debit issue

    Hi,
    I ma faicing an issue with subsequnet debit posting.
    I have been charged by a vendor for transporting material to my plant from one of other plants of our company code.
    we have posted invoiuce for that.
    but there was delay while unloading the truck so vendor is charging for idle time truck has while unloading.
    i want to post that as subsequnt debit.
    buy system is throuwing error as " tax coede 2A doesnot appear in any G/L line items."
    Strange thing is that we can post the invocie with same data.
    Where could be error while posting subsequent debit.?
    thanks

    A subsequent debit /credit arises if  a transaction has already been settled  and a further invoice or credit memo is received afterwards
    You must enter an invoice as a subsequent debit if a PO item has already been invoiced and further costs are incurred.

  • Invoice value including subsequent debit

    Hi Friends,
         I have posted an invoice for a material. Later i have posted subsequent debit for the extra value.
    Now i would like to see, how much i have spent for that material including subsequent debit amount. Where can i see that value, kindly help me.
    Regards,
    Prasath

    in purch order history tab - item detail of PO

  • MIRO Subsequent Debit

    HI,
    Below is the situation of what happened
    1) Limit PO created for 1000 GBP
    2) GR Posted for 600 GBP
    3) Invoice posted for 600 GBP
    4) Subsequent credit posted for 200 GBP
    again..one more
    5) Subsequent credit posted for 200 GBP
    Now I am trying to post
    6) Subsequent Debit for 200 GBP and system is not allowing to post
    Getting below error
    Tolerance limit of only 25 GBP will be allowed
    7) If i am going to post Subsequent debit for 400 GBP there is no error
    Wanted know Concept behind this
    Thx,
    jai

    Resolved the issue, Thanks..
    Subsequent debit posted for full 400 GBP due to tolerance limit
    Then after Subsequent Credit posted for the 200 GBP
    Regards,
    Jairaj

Maybe you are looking for

  • Line item text in BOM

    Hi , I am trying to upload the BOM from the excel and also i am trying to change the BOM based on the data in the Excel. During this process , i have to check the line item text for each component of the BOM to see wheather there is any changes in th

  • DBMS_JAVA Package in Oracle 8.1.5.0.0

    I manually installed JServer using the initjvm.sql script but it did not install the grant Policy table permission procedures. I have looked at the initjvm.sql but the procedures required to grant permissions to the Policy table does not exist there

  • Multipexed channels in MODBUS with memory tag?

    Hi I have setup where an analog input module multiplexes it's four channels into one MODBUS address. I do this with the following procedure: - channel one is written to a certain MODBUS address (e.g. 30016) - then I write a number (e.g. 12) to an oth

  • Simple state machine Where to begin?

    Hello Got a question that is simple for the experienced people here I guess. But don't know where to start..... Here is what I want to try to do: I have got a lot of inputs, to keep the question simple I have only drawn a few of them but eventually t

  • SAP Portal server node identifier

    Hi: We have SAP Portals installed in two server nodes with a load balancer. I know SAP gives a unique internal identifier (number) by server. I want to know, where can I find this identifier ? Thanks, Felipe Mendivil Ortiz