PP confirmations Goods movements ONLY allowed when final confirmation.

Dear All,
Transaction CO11N.
Is there a possibility to do the goods movements of components which are on back flush only on final confirmation of the operation?
Any help is more then welcome!
Best regards,
Luc Knuts

Thanks for the quick reponse!
I will explain the problem a little bit more in detail.
Every operation is executed on a different work center.
We deliver the components to the supply area which is assigned to the work center.
For this reason it's not possible to do the component allocation on the last opereation.
We also produce by-product which should be available on stock when the final confirmation of an operation is been done.
To start and stop activities on an operation we are going to use a scanningsystem which is going to transfer, the hours spend on the operation, via PP-PDC to SAP R3.
The confirmation of the goodsmovement will be done manually via a final confirmation of the operation because it's necessary to adjust the qty of the components.
These are on backflush and the business here does not want to use transaction Migo for this process.
I'm going to check the user exit's that you wrote down to see if I can solve the problem via these.
User exit - CONFPP05 or CONFPP06 or BAdi - WORKORDER_CONFIRM
Best regards,
Luc Knuts
SAP PP-MM-QM-SD
Belgium
Inxites nv

Similar Messages

  • Goods Movement Not allowed(XWAOK) check box - for SRM Reservations.

    Dear Experts,
    We are working on Extended Clasissc sceanrio however certain materails we are creating reservation switching from ECS to Classic Scenario. System is Creating Reservation successfully in backend but Goods movement reservation allowed (FIELD XWAOK) check box not checked only for SRM Reservations
    Please note that ECC reservations checking this checkbox automatically based on Configuration. Is there any setting we have to do in SRM to pass the check box value to ECC? or How Can i check what data is passing from SRM to ECC......
    Thanks
    Ravi

    Dear Ravi,
    Could you please check if you have added the value '201' against the attribute movement type (forgot the attribute name) for the purchasing group or user group who created the shopping cart in SAP SRM. Once you have added the attribute, the problem should be resolved.
    Thanks and regards,
    Ranjan

  • Automatic goods movement at the time of confirmation in IW42

    Hey gurus,
    In a maintenance order i ve reserved some materials to be issued from the stores. Now i am not issuing the reserved materials from the stores and going to iw42 for confirming the operations of the order. If i select the item overview of the operation line against which we have booked the material, in the goods movement section i can see my reserved material which hasn't been issued from the stores. Now when i'm saving the confirmation, goods movement of the unissued material is automatically taking place and the cost of the material is getting booked in the order. How do i stop this automatic posting of material?
    Regards,
    Abhishek

    Hi friend
               in spro
    Plant Maintenance and Customer Service-Maintenance and Service ProcessingMaintenance and Service OrdersCompletion ConfirmationsDefine Control Parameters for Completion Confirmations
    you can define the setting of goods movements
    jitender

  • I have an iPad 4th Gen with Retina Display.  I want to watch movies on an airplane.  I downloaded downloaded one movie successfully from digital copy, but my next movie only plays when I am connected to wifi, and the other one is the same way now

    I have an iPad 4th Gen with Retina Display.  I want to watch movies on an airplane.  I downloaded downloaded one movie successfully from digital copy, but my next movie only plays when I am connected to wifi, and the other one is the same way now

    Hi there slogrown,
    You may need to download these purchases directly to the device. Take a looke at article below for more information.
    Downloading past purchases from the iTunes Store, App Store, and iBooks Storehttp://support.apple.com/kb/HT2519
    -Griff W.

  • Goods movement 101 in Production Order Confirmation.

    Hello Gurus,
    I do the production confirmation via CO15, but when I press the 'Goods movement' button, there are only the components existing on the Goods movement item.
    I can not see the material which I produced with the Movement type 101 'Goods receipt for order into warehouse'.
    Can anyone tell us how to maintain it to allow us do the goods movement for the product?
    Regards,
    Tiger

    Hi Ranga,
    Thank you for your answer.
    I resolve my question according to your solution.
    Select 'Auto Goods receipt' in control key via OP67
    Also thanks to Benny.
    Regards,
    Tiger

  • Restrict user to delete item in good movement at the time of confirmation

    Hi ,
    I have one requirement i.e. When user confirming the partial confirmation and if he selected the goods movement button i have to restrict the user not to change the material quantities in the goodsmovement screen.How i can do it .Is there any user-exits to do so, if any plz give me more info .
    Regards,
    Anand

    Hi
    Try any of the below enhancements
    CONFPP01
    With this customer enhancement you can determine your own default values
    (ones that deviate from SAP logic) for a confirmation. The confirmation
    can be changed in the customer enhancement.
    The following are copied to the interface: the operation in the order
    (AFVGD), the order header (CAUFVD) and the confirmation (AFRUD) as well
    as the confirmation parameters (TCORU). The confirmation is copied back
    from the customer enhancement to the SAP standard program.
    CONFPP02
    With this customer enhancement you can make your own checks of the
    confirmation after the SAP checks have taken place. The confirmation
    cannot be changed.
    The following are copied to the interface: the operation in the order
    (AFVGD), the complete order header (CAUFVD) and the confirmation
    (AFRUD).
    CONFPP03
      With this customer enhancement you can make your own checks once an
      operation has been selected for confirmation. The data cannot be
      changed.
      The following are copied to the interface: the operation in the order
      (AFVGD) and the complete order header (CAUFVD).
    CONFPP04
    With this customer enhancement you can carry out your own checks on the
    confirmation. The confirmation can for example be changed depending on
    the user's entries.
    The following are copied to the interface: the operation in the order
    (AFVGD), the complete order header (CAUFVD) and the confirmation
    (AFRUD). The confirmation is copied back from the customer enhancement
    to the SAP standard program.
    CONFPP05
    With this customer enhancement you can update your own data once you
    have saved the confirmation. You cannot change the confirmations.
    In this customer enhancement it is strictly FORBIDDEN to send error
    messages or other messages because otherwise there is the danger that
    data will be inconsistent. SAP takes no responsibility for this !!!
    The following are copied to the interface: a table with all the
    confirmations (AFRUD) created in this transaction and a table with the
    order headers (CAUFVD) that belong to it.
    CONFPP06
    With this enhancement you can determine which data from a manually
    entered confirmation is transferred to the automatically created
    confirmations, for example, when a confirmation is entered for a
    milestone operation.
    In addition to the order data (IS_CAUFVD) and operation data (IS_AFVGD),
    the confirmation type (I_CONF_TYPE) is also transferred. The data from
    the manually entered confirmation is imported via the structure
    IS_AFRUD_MAIN and the data determined by the system for the
    automatically created confirmation is imported via the structure
    IS_ACT_DATA.
    The data from the automatically created confirmation can then be
    modified and exported via the structure ES_ACT_DATA.
    CONFPP07
    With this enhancement you can define your own detail areas (screens)
    that can be issued for the single screen entry of time ticket
    confirmations.
    Two function modules are available to implement the flow control for the
    customer-defined screens. While the function module EXIT_SAPLCORU_S_100
    transmits the data from the confirmation, order, operation and work
    center, the entered confirmation data can be exported using the function
    module EXIT_SAPLCORU_S_101 and the structure ES_AFRUD.

  • Goods movement tab in production order confirmation

    Hi Gurus, please suggest me with the solution for my requirement.
    while performing production order confirmation, some user should be restricted to see goods movements and some can. how is can me done?
    Thanks in advance.

    Dear,
    Please refer my reply from this link,
    [CO15/CO11N  Goods Movement Screen Hide or Non-editable  |CO15/CO11N quantity column should be non editable in Goods Movement Screen]
    Regards,
    R.Brahmankar

  • 161 goods movement not allowed

    Dear All,
    Here when I am trying to return goods through 161 movement type, I am getting the error "movement type 161 is not allowed"
    Message number is M7873.
    please provide your inputs.
    Regards,

    Hi,
    Hope 161MT is not set for MIGO ,goods receipt T.code
    Now use T. Code: OMJJ
    Select the movement type check box and enter, in the next screen choose the movement type 161 both in from and to and select enter .In the next screen choose allowed transaction from the dialogue structure at the left corner and double click on it. Choose new entries and here enter movement type as 161 and with other T.codes as MIGO, MB01 respectively & save.
    Now try your transactions.
    Regards,
    Biju K

  • HT201272 Why is downloading of previously purchased movies only allowed in the US?

    I had a hard drive fail after a purchase and I'm being asked to pay again in the UK? This can't be right. Is there no way to get it back? If you can do it with programs, apps and music, why not movies?

    Because the US movie studios are the only ones thus far to have granted the necessary permissions (and not even all the US studios have). Making backups of your content is highly recommended, even for items that at present can be re-downloaded, since the content owners can remove any item at any time with no warning.
    If you didn't make a backup, you may have to buy the movie again, but you can contact the iTunes Store and explain the situation:
    http://www.apple.com/support/itunes/contact.html
    It's possible they'll make an exception for you.
    Good luck.

  • TS2634 My apple I'd confirmation email doesn't allow me to confirm

    Apple have sent me 7 or 8 emails asking me to verify my account but the email don't contain a link to click on in order to do this.

    I'm very glad that helped!
    It's good you looked in the Manual first. Certainly not everyone does that.
    With Apple products, I've found that not everything is completely documented, but sometimes if you try something that seems like it should work, it actually does work.
    That's how I personally learned about this feature.
    Enjoy your Apple gear!

  • Goods movement not shown automatically if backflux indicator is not assign

    Dear Gurus,
    If in material master or Routing I am not assigned Backflux indicator to that material then at that time of confirmation - in Goods movement screen is blank.
    How I come to know that what quantity of material in Bom that is assigned according to confirmation & which plant also.
    So pls suggest how without BF indicator that material with quantity should show in that screen..
    Thanks Alok

    Alok,
    You will see materials respective quantity, UOM, SLOC and plant in confirmation --> goods movement only if backflush indicator is set. Similarly, the material being received will appear in this screen only if 'Auto-GR' is active.
    As Mario has suggested, if you have not set this indicator then you have to post GI manually using MIGO or MB1A only.
    Regards,
    Himanshu

  • Goods movement during operation confirmation

    Hi Gurus
    Currently My system is backflushing all the components when i partially confirm the operation through Co11n T-code, which i dont want. I want the backflushing should happen only after the final confirmation of the operation.
    Is there any configuration change required to stop the backflushing only during partial confirmation.
    Thanks in advance,
    Quantum.

    Hi
    In SAP U can do backflush in 3 ways
    Indicator: Backflush
    Determines whether the backflush indicator is set in the production order. Here, a 3-level hierarchical logic is applied:
    1. In the routing, the backflush indicator is set in the component assignment.
    2. In the material master record, the backflush indicator has the characteristic "Always backflush".
    3. In the material master record, the backflush indicator has the characteristic "Work center decides",
    the indicator being set in the work center.
    If at all u dont want to Backflush at the time of Confirmation in CO11N, partial confirmation , dont set any backflush indicator in any level, u can go for Manual Goobs issue Using MB1A, So that u can confirm Goods issue , and final component u can confim By setting Auto goods recipt with the help of Control Key for the last operation in routing.
    i Hope this will help.
    madhu

  • Goods movement in Confirmation IW42,

    Hai all PM gurus,
    I have activated the back flush indicator in the Material master record.I have maintained the components in the task list also.In the maintenace plan for that the particular task list, the componetns also copied - flagged the check box back flush indicator manually in the components screen. While doing confirmation by IW42, the goods movements are not posted?. In the components over view screen also, the material is not copied?. What might be the problem?. Any configuration required.

    hi
    how you came to know the goods movement has not posted.while confirming definitely it will show message as confirmed and goods movement posted.
    kindly read the sap definition for ALL components
    All components on goods movements overview
    Specifies that in the goods movements overview, all components are to be displayed that are assigned to the operation in question. The system posts the withdrawal of all components displayed in the overview as a backflush.
    Use
    You use this indicator to decide which components are displayed in the overview for individual time confirmation:
    If you set the indicator, the system displays all the components regardless of whether or not the backflushing indicator is set for the component in the order.
    If you do not set the indicator, the system only displays the components for which the backflushing indicator is set.
    In addition, the material produced appears in the goods movements overview if it is to be placed into stock using an automatic goods receipt. You specify whether or not an automatic goods receipt is to take place in Customizing for the operation control key or in the production scheduling profile.
    Dependencies
    The indicator has no influence on the overall completion confirmation.
    regards
    thyagarajan

  • Goods Movement After Order TECO'd

    Hello All - Question is part MM and part PM.  It involves a TECO (technically complete status) on a workorder and the ability to perform a goods issue to the workorder.
    Is there configuration to allow a goods movement (GI) to a TECO'd workorder if the material in question has been reserved/requisitioned on the workorder prior to it being TECO'd?
    I'm quite certain that goods issues to TECO'd workorders are permitted PROVIDED the material request was on the workorder prior to it being TECO'd.  There must be configuration somewhere that allows/disallows this because at this client site, NO goods movements are allowed after the order is TECO'd.
    Any help would be much appreciated!
    Thanks
    Susan Page

    hi susan
    read this... u will understand
    Technical Completion of an Order 
    Use
    You usually complete an order technically once the maintenance work planned in the order has been performed.
    Features
    You use the technical completion of an order to define the following information for the order:
    u2022     The order obtains the status Technically completed. The order is marked as complete for Plant Maintenance.
    u2022     Now you can only make the following changes:
    o     Lock and unlock the order
    o     Set the deletion flag
    o     Post goods receipts for the order
    u2022     You can still enter confirmations for a technically completed order. In order to prevent this, you must create a user status that does not permit confirmations.
    u2022     The storage location and account assignment data entered for the order are fixed and can no longer be changed. However, the order can still receive costs, for example, through incoming invoices for materials delivered and used.
    If no settlement rule has yet been maintained for the order, the system creates one automatically. If missing data makes this impossible, the system takes you to the screen for maintaining the settlement rule.
    u2022     All the existing purchase requisitions for the order are flagged for deletion.
    u2022     All the existing reservations for the order are cleared.
    u2022     All outstanding capacities which have been scheduled for the order are cleared.
    u2022     All the notifications for the order are also completed, unless prevented for one of the following reasons:
    o     The Complete notifications indicator was not set in the Complete dialog box.
    o     One or more tasks have not been completed.
    o     A user status in the notification prevents it from been completed.
    u2022     If the order was created using a maintenance plan, the date of the technical completion will be used for the further Scheduling of the Maintenance Plan.
    You can make changes to the maintenance process procedure when completing orders. You can, for example, prevent all users that are allowed to complete orders and notifications from using this data simultaneously to change the scheduling of maintenance plans. For more information, see Separate Completion of Maintenance Call Dates.
    - pithan

  • Production order status - Finally Confirmed

    Dear Team,
    I would like to know the date on which the production order has got the status 'Confimed' (no more confirmations are possible on this order). In which table the final confirmation (last confirmation for this order) date is stored?
    Also i would like to know for a given production order, weather goods movement is allowed or not? In which table this info is stored?
    your input required
    regards
    psk
    Edited by: psk.psg on Jan 18, 2012 11:22 AM

    HI PSK
    All confirmations of production orders are stored in table AFRU - details fields are - AUFNR- order no, BUDAT- posting date, RUECK- confirmation no & all activities etc.
    Goods movement allowed or not is controlled through order status ( say if the order is not released it wont be allowed) , further if the order is locked no goods movmt, then if the orders are TECO goods movment may be allowed or not depending on config setting. If order status is business completed no movment alloed
    shakti

Maybe you are looking for

  • Yosemite Apple apps crashing

    I have a problem in Yosemite where many but not all Apple apps crash when launched. This only happens for one user and includes Messages, Pages, Dictionary, Notes, and Text Edit among others. Not effected are Mail and Safari. There is also a problem

  • Reader 9.0/9.1 problem

    I have install in a window vista OS Adobe Reader 9.0, which will not initiate, error message enternal error.  Downloaded version 9.1 and attempted to install got error message 1606 could not access %APPDATA%\.  Attempted to uninstall 9.0 and got same

  • Disconnected when creating a materialize view

    when i try to create a materialize view from a "big" select (a select from several other selects), it doesn't create the view and i get disconnected from the database.

  • DAQ Problem when migrating to LV8.0

    Hallo, I have a piece of code which was originally written with LV7.1.1. It deals with a NI6289PCI card. This code has been verified. Now I've migrated from LV7.1.1 to LV8.0 and trying to load this code returns an error. A VI called "Get Terminal nam

  • Issue of updation of j2iun

    while saving the j2iun data for monthly utilization cenvat amount it is given message "ERROR IN FI POSTING 20080826. MESSAGE NO: 8i280. FI period is open for posting ie 04 & 05 posting periods open in ob52. let me know how to saved the data.