PR Delivery Date Issue from Maintenance Order
Hi All,
We have a scenario -
- Create Maintaince Order (IW31)/Assign Basic Start Date and Basic Finish Date.
- Auto PR Generated from Maintenance Order but the delivery date in PR is Basic Finish Date.
My client's requirement is Auto PR will pick up the Delivery date as Basic Start Date. What settings do we need to Do for this scenario and on wht basis the delivery date is decided in PR wrt to Maintenance Order?
Regards
Pankaj
Hi SAP Gurus,
Any updates how to solve this issue?
Regards
Pankaj
Similar Messages
-
Unable to change requested delivery date in the sales order at item level.
The issue is when I create order with one material (linked to network and project is created automatically in the background), I am able to change (in change mode) req delivery date for an item, but when I create order with 2 materials (linked to network and project is created automatically in the background), I can not change (in change mode) the req delivery date of any item. Req delivery date is then copied from the header req delivery date.
Is this a standard SAP functionality or a defect?Req del date is the date requested by customer and can be changed at item level. Probably the confirmed date in the schedule line is derived from the network scheduling after ATP check. (ATP check is not activated in this case)
I am able to change the req del date at item level if there is only one item (Linked to network) and not when there are two line items (Both are linked to 2 diff networks belonging to same project)
I tried to change the date in the network, scheduled and saved but that didnt change the date in the sales order. On the contrary, if I run ATP check, netowrk dates get back to original dates derived from sales order. -
Hi All, Please help in the below issue,
there's a spare part material valuated with split valuation as follows:
Defected avg price 10/EA
Used avg price 20/EA
New avg price 30/EA
From PM module, one EA from defected valuation type issued and the accounting doc shows value of 10 (correct), after finishing maintenance work on this part it will receipt in the same sloc but with valuation type Used,
the issue is when GR from order the accounting doc shows value of 20 (debit stock with 20) the current price in master data while the actual cost from maintenance order is 200 how to make the GR valuated with actual cost from maintenance order which is 200.
Your help will be highly appreciated, Thanks in advance.Greetings Hossam,
Looks like what you are trying to achieve is to implement the Refurbishment Order process.
In the standard system, you can use the Order Type configured as a refurbishment order to settle the actual cost to your stock value.
Say that you have the material master created with split valuation, as you mentioned.
Defective avg price 10/EA
Refurbed avg price 20/EA
New avg price 30/EA
Say you have 1 EA of Defective material at €10 , your refurbishment Order actual cost total is €15 , your material price is Moving Average, and you have no other stock. You would then issue the Defective part to the order with mvt type 261 (Order total cost goes up to €25). Then you would receive the 1 EA Refurbed part from the refurbishment Work Order with movement type 101. (Order total cost drops to €5). You would subsequently settle the Work Order total to the stock of the Refurbed valuation, raising the moving price from €20 / EA to €25 / EA.
Please refer to the documents on Refurbishment process, search the SCN, and feel free to ask any specific questions.
Refurbishment Order - Customer Service (CS) - SAP Library
Creating a Refurbishment Order - Customer Service (CS) - SAP Library -
Delivery date on the sales order
Hi frnds
I am facing an issue here. When the sales order comes of credit hold the system proposes a new delivery date in the sales order. How can i change the settings to avoid the system from assigning weekends(Saturday & Sunday) as the delivery date????
I have checked that the factory calendar is set for weekdays only and also the propose del date is check marked in VOV8, OVX5 & OX10 have factory calendar asssigned but i am not able to figure out how to restrict the delivery date to weekdays to be proposed by the system.!!!
Am i missing something???
Will appreciate your suggestions.
nullHi,
The fields needs to be activated in the filed group in accounting.
The path is SPRO -> Financial accouting -> Accounts Receivables and Accounts Payables -> Customer accounts -> Master data -> Preparations for creating Customer master data -> Define account groups with screen layout.
Shiva -
Create Outbound delivery with QCI from Sale order
Dear experts!
Now, I'm getting some issues about searching function to create outbound delivery with QCI from Sale order.
Note: My sale order have two item (10, 20) and when i create outbound delivery I also want to create QCI for them.
Help me, Please
Best regards, Huy.What is QCI?
-
Material Gate Pass from Maintenance order?
Dear SAPIENTS,
Is there any system to issue returnable material gate pass from maintenance order in case of sending material outside for repairing. I want to keep track of material through maintenance order i.e the reason.
Regards,Hi,
There is no STD SAP Functionality Available but You can Develope the Customising Smart Form to get this fuctionality.
Also You can get The information about the Outgoing Material in TC MB51 if your making The Reservation Of that Material agianst the Vendor,while sending that material outside.
Regards,
Rakesh -
Plan Component from Maintenance Order
Hi,
When i plan a component from maintenance order I use item category N with key MATE.
But i woul plan component for purchase requisition on project stock( account assign Q) directly from Maintenance Order. Allow I insert item category N in the field ad near insert the value 2 for project stock.
When i release the order the system blank the field and i don't create a Purchase requisition with project stock but i purchase requisition with account assignement F
Because the system put away the field blank?, I must done another customizing, or i must utilize another KEY?
Thank youHi,
When you make Item cat as N it means they are non stock .
For non stock & with F order as account assignment system creates PR.
if you want this componenet as Project stock them there are following ways
1.Make PR with item cat as Q & make PR on WBS or PS System.
System will post direct entries.
2.Make normal stock PR then issue against WBS by order
Settle the maintenance order to WBS element
3.Get material as normal stock material issue with 221 mvt against WBS or PS system.
Systme will make enties to WBS.
Ramesh -
Catalog procurement from Maintenance Order
Hi Gurus,
My client is implementing Punchout Catalog from SAP ECC 6.0. we are not into SRM server. I made the settings in Web services ID and Description and i am able to do shopping from Vendors URl and return back to SAP ECC.
Now 1) they want to populate the Vendor name automatically into SAP, which is not getting carried.
2) I want to link the Punchout Catalog to Work order scenario also. For that i need to define the Order type and Catalog in the Link "Interface for Procurement Using Catalog" under the node Plant Maintenance and Customer service which i am not getting.
Please advice me what needs to be done or what settings or any BADI needs to be activated on this issue.
Thanks for your response in advance,
I am not sure is this the right place to post this thread. Please advice.
Thanks,
Saakithyan.Hi,
I already have plan component from maintenance order but when i insert item category N for create a Purchase requisition and insert item category 2 for stock project Q the system blank the field and Don't create a purchase requisition with account assignment Q.
Because the system put away the field blank?
There are any way for create purchase requisition with account category Q?
The BAPI that you suggest me can avoid this problem?
Thank you. -
PR delivery date calculation for TAB orders
Hi All,
1) The PR which is created via TAB item in the sales order - the delivery date for such PRs is equal to the delivery date in the sales order. This is happening only for TAB orders without BOM explosion in the sales order.
2)In BOM exploded sales order - (meaning the parent item is entered in the sales order with item category TAP. ) -The sub components of this parent item is auto populate in the sales order. If any one of these sub components have item category TAB...then it creates a PR which has the delivery date equal to the "Planned delivery time" in the info record.
Can anybody please explain why the PR default delivery date is different in the two cases explained above. Both are TAB items...the only difference is one is a stand alone TAB item and the other is via BOM explosion.
Your help will be highly appreciated.
Thanks
AshokHi Sasy
Delivery date calculation for MRP generated PR will follow the below settings
1) Purchasing processing time in the Plant parameters in the customization and is calculated based on the Factory calendar days.
2) Planned delivery time maintained in PIR and is calculated based on Normal calendar days
3)GR Processing time Maintained in Material master record, calculated based on Factory calender.
If you add up in the following sequence then you will get the exact delivery date.
Purchasing Processing time + Plnd delivery time + GR processing time.
Hope it will solve your issue.
Thanks / Karthik -
PR from Maintenance Order - Material Purchase
Dear Experts,
Likewise we can generate Servide PR against Maintenance Order, also it picks service data frrom Maintenance Order....Similarly can we generate PR for Material Purchase against Order also it should pick Material from component that we have enetered in Maintenance Order ..is it possible??
Thanks
DMHi
Deletion of PR from Maintenance Order is not possible because the PR is created automatically
This PR will get deleted automatically when you cancel//teco/complete the order
Otherway around is you can always block the PRs
Regards
Kartik -
Sales Oreder Delivery Date Issue
Dear Experts,
In Sales Order Doc. i want that the Delivery date of two Sales Orders should not be same.
While generating New Sales Order the Doc. Delivery Date should not pick same date of any Sales Order given before.
e.g.
I have a Sales Order with No. 1234 & Del. Date 30-03-10
If i create a new Sales Order with No. 5768 and if by mistake i fill same delivery date as given above, then it should occurs error as date not available or this date already exists.
Regards,
Ravi JhaI think you want to restrict the sales orders, not the deliveries.
So try this:
if (@object_type = '17' and @transaction_type = 'A')
BEGIN
IF exists (Select Docentry from ORDR
where DocDuedate = (Select DocDuedate from ORDR Where Docentry = @list_of_cols_val_tab_del)
and Docentry != @list_of_cols_val_tab_del )
Begin
select @error =@object_type
select @error_message = N'Delivery Date already exist'
End
If you want to restrict not the full number of orders but only for per customer, you can use this:
if (@object_type = '17' and @transaction_type = 'A')
BEGIN
IF exists (Select Docentry from ORDR
where DocDuedate = (Select DocDuedate from ORDR Where Docentry = @list_of_cols_val_tab_del)
and CardCode = (Select CardCode from ORDR Where Docentry = @list_of_cols_val_tab_del)
and Docentry != @list_of_cols_val_tab_del )
Begin
select @error =@object_type
select @error_message = N'Delivery Date already exist'
End
END -
I want to pick up Schedule line Delivery date based on Sales Order of Mater
Hi Experts,
I have one scenario like,
I want to pick up Schedule line Delivery date based on Sales Order of Material.
For example :
Go to va03
Give the order no
Press the enter
Double click on material.
Go to Schedule line Tab
Then we can find out the Delivery date .
I want to pick up the that Delivery date. Could you please help on that.
Thanks,
Amjad.Hi,
schedule line dates are available in VBEP.
VBEP-VBELN = sales order number.
VBEP-EDATU = schedule line date.
REgards,
Raghavendra -
Default GL account upon goods issue to maintenance order based on activity
Hi all,
There's a scenario here in Plantation Industry that we require to default GL account upon goods issue to maintenance order based on activity type assigned in the order instead of only posting to consumption account, is there anyway in OBYC or user exit able to fulfill requirement mentioned?
Thanks as advanced.Hello
With help of general Modifier in combination of valuation class you can assign GL as per your wish for offset posting incase of GI to order/anything
Example
Transaction key-GBB
General modification- VBR
Valuaction Class - checked
Dr/CR- checked
Assign the general modifier to T code MIGO , through OMJJ
Regards
Dinabandhu -
Goods movement from Maintenance order
Hi Experts
I have the following scenario,
I have a component ( with Material master) in the maintenance order and i use Item category N to trigger a Purchase requisition. The Pur Req is converted to Purchase Order and then the GR is done directly to the order .
Now i have not used this Component and want to make a goods movement to place it in stock. So the requirement is to move the material from Maintenance Order to the Storage location .
How and which movement type can i use to do this ?
Please help
KKHi,
Click the below link for more information
http://sap-img.com/plant/in-pm-how-to-return-material-backflushed.htm
regards,
Venkatesan Anandan -
Automatic Reservation from Maintenance Order
Hi,
I have a problem. Generally from Maintenance Order type PM01 under Order Category 30, when we give some materials requirement, SAP automatically generate reservation for those materials and take the GL as Consumable Item.
But in my case, that GL has to be changed depending on what perpose we are using the material. But Manual reservation is not allowed for the order category 30 and no GL can be changed for automatic reservation.
Can anybody suggest any way-out so that we can give our desired GL No. for the reservation for Maintenance order (say Order type PM01 under category 30 which is SAP internal).
Thanks in advance,
SatadalThanks for your answer. Actually I found that place, it is determined from OBYC transaction with a combination of GBB (A/c Key) and VBR (A/c Modifier).
But for same movement type261, I need manual G/L allocation at runtime. i.e. depending upon case to case, the G/Ls will be different. So, different movement type perhaps would not serve the purpose.
Basically I need to over-write the G/L for automatic reservation created from PM in the PM01 order type with category 30 where manual reservation is not allowed.
Can you suggest any way out so that I can actually over-write the G/L for automatic reservation- through SPRO or some kind of development...
Thanks
Satadal
Maybe you are looking for
-
How to fetch null values from a table
Hi, This is a Attendance report Table Name : Attn_details ( Only 3 records stored in this table ) EDate Etype 04/03/2010 A 05/03/2010 C 06/03/2010 X user Enter From date : 01/03/2010 To date : 10/03/2010 I need the output 01/03/2010 to 10/03/2010 01/
-
Dear Experts, I'm in need of a clarification, there is a material available as free stock (not reserved for any project - ie., not a Project stock) At this situation, i've one WBS element, Is there the possibility to issue that free stock to WBS elem
-
Hello I've written a program to find a keyword in a file (or files). It compiles fine. When I run the program I get a FileNotFoundException. It is referencing the first argument in the command line, which is my keyword. I don't understand, since I se
-
RPUQSTC0 - Witholding tax update
Hi all, I need to update Swiss witholding tax information for 2007 and I find out that I can do it with the files from Cantonal Tax Office and the report RPUQSTC0. I have the files but I can't find documentation regarding the report. Where can I find
-
Quality Management - Usage Decision error
Hi all, My scenerio is - There is a material ABC which is procured from the supplier. The Quality of the material is 'below standards'. However, material ABC, in Tcode QA11 Usage decision was done as ACC1 (accepted). Since the material ABC is not mee