Pr& po -new release strategy? released/locked/incomplete

Dear MM experts,
I would like to understand what it is meaning of
released
locked
incomplete
while doing assignment of object class thru cl24n for new release strategies,
I am clear on released & locked, I would like to understand what is "incomplete" means as per SAP.
kindly clarify
thanks in advance
srihari

Incomplete means - When you go to CL02 or CT04
you are entering the statu for calss or char as locked or released
but when you are creating and that time if you have keep the status is in preparation  and without changing the status you start maintainig the data in CL24N than you will see the statu as incomplete.

Similar Messages

  • Scheduling agreement Release strategy release indicator

    Hi all
    For the Scheduling aggreement Release strategy is present & release indicator is 6 , Now the requirement is whenever user is changing the any value Scheduling agrrement it should go for rerelease. for any minor change in value even the value lies between the same Release strategy 
    Release strategy is configured on Purchase group & Value character
    Also what is the difference between release indicator 4 & 6. for any changes in the SLA release strategy will be reset in this two release indicator.
    Thanks & Regards,
    Rajesh

    Hi,
    This is a standard phenomena any change in value (increase)will reset the release stategy
    and indicator 4 & 6 are same only in case od indicator 6 if you have taken the oout also it will get affected

  • Old PR release strategy - release completed status change

    Dear Gurus,
    We have impletemented Item level release strategy for PR.
    There was old strategy exisitng only one level release, then we have implemented new release strategy which is multiple level release.
    Now the question, there are some PR are released completed for old strategy,. if we change the old PR with old strategy - which was release completed, the system triggeres new release strategy, which over writes the old strategy even though it was release completed status.
    Please advice
    Regards
    RS

    Hi,
    Check with T.Code OMGS (Define Release Strategy for Purchasing documents) , then go to release indicator --> then
    Check the value of Changeability of purchasing document during/after release  ( 1 - 6).
    Choose the appropriate value based on your req.
    Regards,
    Udayasankar Rajagopalan
    Edited by: Udayasankar.rajagopalan on Dec 9, 2009 1:07 PM

  • PO release strategy - release code

    Hi Experts,
    I have completed the release strategy and transported to production.
    However noticed that the release codes that has been configured earlier wasn't in the production.
    Is there a way to update the release codes in the production besides using SPRO (no authorisation for maintaining - only display) like using CL24N to update the characteristics?
    Thanks and regards

    Hi,
    Please first check the attached notes that refer to transport issues.
      365604   FAQ: Release strategies in purchasing
      186809   OMGQ/CL24: Inconsistency for release strategy class
       86900   Transport of Release strategies (OMGQ,OMGS)
       45951   Transporting class data: system / client
       10745   Copying classification data to another client
    The classification data must be sent over using ALE. It does not get
    transported directly.  Notes 45951, 86900 and note 365604 should help.
    Please follow the instructions in note 45951.
    You can obtain more information about how to set-up ALE in the Online
    Documentation CD (R/3 Library > CA - Cross Aplication Components >
    Business Framework Architecture > ALE Integration Technology > ALE Quick
    start).
    However, if you can't set-up ALE, you can re-create the classification
    data agin in your target system. For that you have to:
      1- assign new values to the characteristic master data (t-code CT02)
      2- assign the new data to the classification system (t-code CL30)
      3- verify the consistency with t-code CL24. Please see note 186809.
    For more information, please see note 365604.
    The transport of release procedure customizing data can only be done
    in a restricted manner. Please take a look at attached Note 86900 and
    follow the procedure described in this note, in order to correctly
    transport your release strategies.
    Classification data can only be transported via ALE as per note 45951.
    Note 45951 explains what class data for the release strategy will be
    distributed from one system to another. It does not describe how to
    implement as this involves a lot of explanation and is truely a
    consulting issue.
    There is another possibility that you could take into consideration for
    the classification is to import them via batch input:
    RCCTBI01 for creating characteristics
    RCCLBi01 for creating classes
    RCCLBI03 for classification
    Best Regards,
    Arminda Jack

  • PO Release strategy release procedure

    Hi
    Any body can suggest
    what is the procedure for release strategy transport to anther system means D to Q

    Hi,
    Release strtagy Configuration can be transported from one client to various client[Like creation Class,characterstic,Release code,release strtagy definations etc]
    Where as assignments of Objects / class  and  various parameter for release strategy has to be done in individual clients in -T-code: CL24N.
    Example : For Class -PO Release we need to assign -Values for Class -characteristic values has to assign in CL24N
    with regards
    Shrinivas Gangoor
    Edited by: Shrinivas Gangoor on May 22, 2009 3:06 PM

  • Pr& po -new release strategy?

    Hi Friends,
    My requirement is to add new release strategy for pr & po.
    Characteristics & Class are remain unchanged.
    Pl advise to how to proceed, i mean
    i have to set/create new release procedure, ie.,
    New release groups
    New release codes (bcos new codes are added & release levels remained same)
    New release strategies
    How i can retain the Old PRs & POs released with earlier release strategy/release codes?
    PRs & POs not released can be with new release strategy,  but i have to ensure the old prs & pos (released) were with earlier release strategy & release code.
    Also, I need ur advise, how the new release strategy works for workflow
    pl help
    thanks & regards
    Srihari

    Hi,
    First of all, if you would only like to create the new release strategies, then the only possible settings you should do are -
    1)   Create the new release code;
    2)   Create the new release strategy;
    3)   Assign the release characteristics values to your new release strategy in CL20N transaction.
    For those old PRs and POs (regardless of if they were released or pending for release), the same old release strategy remains unchanged (and therefore, you should be much careful if you wish to delete the outstanding release codes and/or release strategies through configuration).  Having said that if you would like to keep the same release strategy though changes are to be made to your old purchasing documents, then you will have to assign the proper value to the "Changeability" field of your "released" release indicator.
    In case of release strategy in support by workflow, basically, the workflow item will be triggered (in accordance with the pre-defined logics that you built in terms of task ID).  As soon as the approver determination is made in background, the workflow item will be then sent to such agent who will then take a proper decision (approve, reject or forward).
    Cheers,
    HT

  • How to setup a release strategy for store generated purchase order

    Hi there,
    Does anybody know how to setup a release strategy for store/plant generated purchase order? I have a request from our client, but I never cross this before. Please help and let me know the step with every single detail.
    Greatly thank for your help.
    Kind Regards,
    2tea

    Please go thru the below Release Procedure and check whether you have maintained all the settings properly.
    PO RELEASE STRATEGY
    The release code is a two-character ID allowing a person to release (clear, or approve) a requisition or an external purchasing document. The release codes is basically controlled via a system of authorizations (authorization object M_EINK_FRG).
    Use SE12, structure CEKKO to check all the fields available for controlling the Purchase Order.
    e.g. If the total value for the Purchase Order exceeds 10,000, release strategy 01 is assigned to the Purchase Order. There is only one characteristic created in this example. For controlling the Purchase Order type, create characteristic for CEKKO-BSTYP and the value NB.
    CT04 - Create Characteristic e.g. NETVALUE
    Click Additional data Table name CEKKO Field name GNETW and press enter
    (for currency dependent field, you are prompt to enter the currency which the system then converts the currency of the Purchasing document into this currency)
    In the Basic data (X refers to tick),
    X Mutliple values
    X Interval values
    In the Value data, in the Char. value column, type >10000 and press enter
    Save your data
    CL02 - Class
    Class - Create REL_PUR
    Class type - 032
    Click Create
    Description - Release Procedure for Purchase Order
    In the Same Classification section, click Check with error
    In the Char. (characteristic) tab, type NETVALUE to assign your characteristics to the class
    OMGS - Define Release Procedure for Purchase Order Type
    Release Group - New entries
    Rel.group Rel. Object Class Description
    02 REL_PUR Rel. Strategy for PO
    Release codes - New entries
    Grp Code
    02 01
    Release indicators
    Release indicators Release Description
    0 Blocked
    1 X Release
    Release Strategy
    Release group 02
    Rel.strategy 01
    Release codes 01
    Release status 01
    Classification Choose your check values
    OMGSCK - Check Release Strategies
    (make sure there are no error messages)
    Once the Purchase Order is not release, buyers will not be able to print the Purchase Order.
    Goods Receipts will be shown with Message no. ME 390 - Purchasing document XXXXXXX not yet released.
    In 4.6c, Purchase Order with Release Strategy have a tabs at the end of the Header. This allowed the buyers to check the release status of the Purchase Order.
    The person with the release authorization have to use ME28 to release the Purchase Order.
    Regards,
    Ashok

  • Purchase Order not subject to release strategy

    Good day everyone!
    I've created one release strategy for all my purchasing documents. The characteristic is net value, and the value of this characteristic is >=0.00. Meaning, ALL purchase orders are subject to release strategy.
    After I did the release strategy in SPRO, I created a few PO and when I tried to release them, I got this message: "Purchasing document 45xxxxxxxx not subject to release strategy".
    My question is: How to assign purchasing document to release strategy?
    Please help. Thank you in advance.
    Anisah

    hi
    yes you have to use table CEKKO for PO release strategy , now , in PO you can't create without clasification so it will be applicabe for whole PO not for line items ,
    now below i am giving u one by one steps , follow and let me know .
    The release code is a two-character ID allowing a person to release (clear, or approve) a requisition or an external purchasing document. The release codes is basically controlled via a system of authorizations (authorization object M_EINK_FRG).
    Use SE12, structure CEKKO to check all the fields available for controlling the Purchase Order.
    e.g. If the total value for the Purchase Order exceeds 10,000, release strategy 01 is assigned to the Purchase Order.  There is only one characteristic created in this example.  For controlling the Purchase Order type, create characteristic for CEKKO-BSTYP and the value NB.
    CT04 - Create Characteristic   e.g.  NETVALUE
    Click Additional data Table name CEKKO      Field name  GNETW    and press enter
    (for currency dependent field, you are prompt to enter the currency which the system then converts the currency of the Purchasing document into this currency)
    In the Basic data (X refers to tick),
    X    Mutliple values
    X    Interval values
    In the Value data, in the Char. value column, type >10000 and press enter
    Save your data
    CL02 - Class
    Class - Create REL_PUR
    Class type - 032
    Click Create
    Description - Release Procedure for Purchase Order
    In the Same Classification section, click Check with error
    In the Char. (characteristic) tab, type NETVALUE to assign your characteristics to the class
    OMGS - Define Release Procedure for Purchase Order Type
    Release Group - New entries
    Rel.group   Rel. Object   Class                 Description
      02                                 REL_PUR        Rel. Strategy for PO
    Release codes - New entries
    Grp         Code
    02           01
    Release indicators
    Release indicators           Release        Description
          0                                                        Blocked
          1                                     X                Release
    Release Strategy
    Release group   02
    Rel.strategy    01
    Release codes   01
    Release status   0
                            1
    Classification   Choose your check values
    OMGSCK - Check Release Strategies
    (make sure there are no error messages)
    Once the Purchase Order is not release, buyers will not be able to print the Purchase Order.
    Goods Receipts will be shown with Message no. ME 390 - Purchasing document XXXXXXX not yet released.
    In 4.6c, Purchase Order with Release Strategy have a tabs at the end of the Header.  This allowed the buyers to check the release status of the Purchase Order.
    The person with the release authorization have to use ME28 to release the Purchase Order. 
    regards
    ravikant dewangan

  • Retriggering Release strategy for PR with Document Type, Company Code and Price Range as Characaterstics

    Hi Friends,
    I have a issue to fix. The issue is releated to PR.
    There are some PR's in the system which has wrong release strategy picked up or wrong approvers picked up due to some congif change. now that the config changes are rectified correctly, we need to find a solution to correct the PR's which got affected due this.
    I have to retrigger the release strategy for all the affected PR's.
    The characterstics which we have consider for release strategy is Document Type, Company Code and Price Range.
    Can anyone suggest how can we retrigger the PR in bulk or individual to all the affected PR's, so that it picks up correct release strategy as per new config changes.
    Regards,
    Manjunath K

    Hi,
    Refer the discussion to triggers release again on release code addition/change in release strategy.
    release code is changed on PR release strategy - old PR can´t be approved
    Regards,
    Biju K

  • Mm pr-po release strategy : error

    Dear MM experts,
    We already having MM-rel strategy for PR & PO with classification procedure and working fine,
    Now business requirement is to change the MM-Rel PR& PO strategy,
    New mm-rel strategy for PR customised in class 032  (not to use existing release groups & release strategies) 
    After doing config settings in customising client, the request moved to another client for testing.
    Testing client, request moved successful, and while checking the settings in testing client,
    in Release Strategies - details mode
    Informatination is available at Release pre-requisites, Release Statuses without any error,
    but when we try for Classification, we are getting the following error
    "Error in classification (class PRREL class type 032)"
    Can u please suggest what needs to be done so that we can go ahead further.
    Kindly note while doing config setting client, we did not encounter the above error, it has accepted all the settings (copy existing rel group & having differnt rel strategies, etc)
    pl help
    Thanks in advance
    Srihari

    Hi Friends,
    My requirement is to add new release strategy for pr & po.
    Characteristics & Class are remain unchanged.
    Pl advise to how to proceed, i mean
    i have to set/create new release procedure, ie.,
    New release groups
    New release codes (bcos new codes are added & release levels remained same)
    New release strategies
    How i can retain the Old PRs & POs released with earlier release strategy/release codes?
    PRs & POs not released can be with new release strategy,  but i have to ensure the old prs & pos (released) were with earlier release strategy & release code.
    Also, I need ur advise, how the new release strategy works for workflow
    pl help
    thanks & regards
    Srihari

  • PR Release Strategy Re-determining due to Change in Text

    The PR release strategy was configured by a previous company.  There are existing PRs that are not completely approved (Release Indicator = 2).  The SAP instanced was transitioned to the company that broke away.
    The PR release has now been re-configured with new release strategies (groups, codes..etc).  What we are experiencing is that the existing PRs that are "released" do not show the new release strategy when the combination of release strategy/release group does not exist- This OK as well.
    When a user made a change to the Item Text and nothing else, SAP re-determined the release strategy and started the release process over again.  Is there a way to stop these PRs from re-determining and therefore restarting?

    Hi There
    Though the release strategy is different, i think all the classifications are same or old classification (even 4 or 5 parameters) may also part of your new full release strategy(You may be trimmed from old release).
    So when you do any changes or just go to the change mode and Check (F7) , system may find the new rel strategy.
    i have not tested the above scenario, i could recall some older posting based on that i did suggest the above
    Thanks Senthil P

  • PR Release Strategy work flow

    Hi Guys ,
    I have a work flow requirement , In Which i have to know in Purchase requisition items history . how to identify the new item and
    change items for triggering the work flow .
    Here i am using a badi to triger an event . ( BADI :  ME_REQ_POSTED )  
    Any idea , Plz share .
    THanks
    Nags

    Hi,
    First you set your all required configuration fro release strategy(Class,Char,Rel.Group,Release Strategy ,Release Indicator )
    For Work flow settings,You have to do follwoing configuration:
    MM - purchasing - purchase order - release procedure - Define Release Procedure for Purchase Orders - Work flow - Enter release code, group, user ID, object type as user.
    Creation of work flow object,activation of workflow and other related settings will be done by Techinical  work flow consulant.
    Thanks,
    AMIT

  • PR Release Strategy tab processor field is not getting displayed

    Hi Experts,
    While creating Purchase Requisition, In the Release Strategy tab processor field is not getting displayed which should be showing the name of the user id which has been configured in the SPRO.
    SPRO--> Rel Proc for PR > Rel Group> Rel Code--> Object type (US) and --> Agent (User id who has to approve the PR).
    release strategy - Release code  -work flow 1
    That processer name is not displaying
    Thanks
    chandoo

    This is the workflow forum.

  • Overall Purchase requisition Release strategy : Changed after Rejected

    Hi All,
        I have activated overall purchase requisition Release strategy (20000077) . And its working fine when PR is released at each level and saved.
      Problem I have is when PR is rejected .
    When PR is rejected , workitem is created for initiator with ME52 transaction. When initiator changes the contents of PR and saves , the release strategy should resume back from where it stopped. Thats means when Approver A rejects the PR, after initiator make changes , the workflow should trigger back with a workitem for release to approver A.
    But its not happening as expected. When Approver A rejected the PR and initiator changes the PR , Nothing is triggered, as there is no event raised at this point. 
    ME52 changes for PR is not trigerring any event which can trigger the WF.
    Is there any way we can trigger Workflow in this scenerio.
    Please suggest.

    Hi Subhashini,
    This all depend on release strategy. release should reset completely on tha change.
    For the increase of quantities or values you can maintain tolerance limits in the Customizing. When you increase the amount or value via the tolerance limit the system will reset the release.
    When you reduce quantities or values the system only resets the release if another release strategy is determined for the lower quantity or the lower value.
    If no other release strategy is determined by the reduction of the
    amount or value, the system will keep already existing releases.
    changeability in Release indicator also play a major role. You should set it to either 3 or 4. Now if you change any field, which is also used in any charecteristics in release, it will lead to reset of release startegy.
    Sanjeev

  • Work flow for release strategy for PO & PR

    Hi Gurus
    Can anybody explain workflow for release strategy for PO and PR
    Thanks in advance.
    Atul Kulkarni

    Hi,
    First you set your all required configuration fro release strategy(Class,Char,Rel.Group,Release Strategy ,Release Indicator )
    For Work flow settings,You have to do follwoing configuration:
    MM - purchasing - purchase order - release procedure - Define Release Procedure for Purchase Orders - Work flow - Enter release code, group, user ID, object type as user.
    Creation of work flow object,activation of workflow and other related settings will be done by Techinical  work flow consulant.
    Thanks,
    AMIT

  • FB60/FB65 Release Strategy

    Hi All,
    While processing the transaction code FB60 / FB65, we need the system to check a Ztable which contains the maximum tolerance limit for employees to process the invoice / credit memo. The system should give a warning message and send email to the supervisor about this.
    Though we could locate an user exit for this purpose, please advice if we have standard release strategy / release procedure / workflow which can be used for this purpose.
    Kindly revert back with your ideas as soon as possible.
    Regards,
    Sanjay.

    Sanjay,
    the process is present with tolerance groups in tcode OBA4
    you don't need a customer table and a "hidden sending of an e-mail"
    regards
    Andreas