Hi Guru's
My client is trying to set up their item-level Purchase Requisition Release Strategy to include Cost Centre (of which there are about 800), but they would also like to minimise the number of release strategies to cut down on maintenance of authorisation roles.
If we were to create a release strategy for each cost centre (or group of cost centres), that would result in an insane number of release strategies. So, if cost centre were removed as a criteria in the release procedure, is there any way of controlling the release authorisation based on the cost centre?
So, if a requisition line is created for a certain amount, it will have release strategy, say S1 and release code R1. Two approvers are authorised to release this combination. Is it at all possible to restrict the ability to release this line item to just one of them? Either by config or using a coding solution.
I hope that made some sense.
Thanks
Lyal

I hope the below link will help you:
http://www.sap123.com/showthread.php?t=59

Similar Messages

  • Regarding the Release Strategies not getting picked up for PR

    Hi Gurus,
    1 ) I have configured a new Release strategy with Plant,Total Value,AAC and Doc.type as the Characteristics.I have assigned that to a release class and assigned values to the characteristics.
    I have configured 6 release codes and 6 different Value Intervals for 6 release strategies and assigned it accordingly. But whenever i am trying to release the PR, it is picking the first strategy only. its not picking the other strategies even it is of differnet values. Please advice what needs to be done on this.
    with Regards,
    Saakithyan

    1st of all check whether you defined release strategy for Item level or header level.
    If you defined item level check the individual item has all the 6 characteristics you defined.If any characteristic is missing then it will not pick. Provided you defined all the characteristics for classification view or CL20N.
    Thanks & Regards
    Sudhansu

  • Release strategies to PO

    Dear friends !
    we will use release strategies to Purchase orders with standard workflow only to send a message to user (into tcode SBWP).
    I have configured release strategies and put it on field " Workflow"  the value " 1"Role resolution with group, code, and plant (T16FW) and  also put at the " Workflow " specific  , the Object Type = US and the userid = BRAZILA(logon to SAP).
    But after we save the PO no message has been sent to Users.
    does anyone knows if are necessary others customizing settings ?
    Which settings and tcodes are theses ?
    I´m looking for more details inside SDN but no specific transactions were available and easy to understand until now.
    Best regards,
    Ale

    Dear friend Thx for your answer
    Do you have any BPP to config this ?
    Any documentation general about this configuration!
    best regards
    ale

  • Restrcuturing of PR and PO release strategies - corporate policies

    Hello,
    I´m in a proyect where a multinational company wants to restructure its PR and PO release strategies.
    We are in the fase of defining corporate policies as guidelines for the new structure.
    The multinational Holding contains Productive companies, distribution companies and other type of companies like investigation companies.
    I would like to have some feedback about how to guide the company management in this process off defining corporate policies.
    How does one or can one estandardize the release levels, release codes and amounts which separate the levels, in a diverse multinational.
    Are there any paradigmas, methods to acomplish this.?
    If anyone has experience with these kind of processes, please give me some feedback on how they tackled these issues.
    Thanks,
    Aart

    Hi,
    Normally when a company is coming into the sap , which have many business at various locations / countries , a structure will be defined in the SAP for the company as company code under which the plant and below the structure will be defined .
    However when comes to purchasing and for PRs POs , SAP give a communication strusture called CBAN for PRs and CEKKO for POs which can be viewed at SE16 . Thease tables contains the fields upon which the release strategies can be made .
    For example , say for one of your productive company , the company code created is XXXX and the plant under which is YYYY say , the policy can be for a groups of buyers which comes under the plant for a PO level , who can be the approver . Here for differrant PO/PR values differrant approvers can be added as strategies and based upon which the approval can be happened . and the approvers be the release codes .
    There are no standard paradisms rather , prior come into purchasing the organization structure be made.
    After that based upon the business/product , with in that company code defined , the levels can be defined in that perticular business .for purchases .
    In purchasing , to fhe plant / purchase group / storage location etc plays important and normally for a set of buyers/p grps , in that plant or group of plants in that company code , the levels of the PO/PR values can be defined for differrant strategies .
    Once at corporate level , the company code / plant is defined and under that the release strategy is easy to define .
    Regards,

  • RCCLBI01 and Purchase Requisition Release Strategies

    I'm trying to use RCCLBI01 to load Release Strategies.  I've found a few threads on it but they don't tell you what you can and can't do with it.  I know I can load the characteristic values for an already existing Release Strategy, but I have hundreds of Release Strategies that I need to create. 
    Will this load the strategies as well, or do I really have to go create them by hand in SPRO first then run it?  Or is there another program that will load strategies and the codes and the characteristics?

    Kris,
    RCCLDI01 is now used. However Here's my view:
    1. You will have to create chracteristics to begin with. I hope the number is not huge as it will narrow down the functionality otherwise.
    2. The class-- How many would you create?? I don't believe you would need a Batch input program to create a class as I believe there could not be more than a handful, unless necessary
    3.Now the classification.. the buggest task of all, where you could run in to hundreds.. Maintaining them is a nightmare and you'd have to have your strategies first.. I do not know of any input program to create Release strategies. So my answer is "a manual task"
    4. RCCLBI02  is of no help here for release strategies.
    5. I would rather use TCODE: CLMM to do the mass changes.. it makes life a lot easier.
    6. The last option is for some one technical to help you create a script to load the data.

  • To know release codes and strategies

    Dear Gurus,
    I want to view release codes & strategies for relevant material in contract...For this what is the T code or any other simple way is there..
    Thanks in advance.

    u can get the release codes from table T16FC and release strategies from T16FS thru SE11/SE16.
    u can also try out thru ME3M,here after running the report by giving all the required input and placing Scope of list as ALV,choose change layout (shift+f8) bring release strategy from hidden column to displayed column and choose enter.......
    regards,
    indranil

  • Release Strategies - Integration with users

    Hi All
    How to integrate users with release strategies for a PO?
    i.e., I have 3 Level release strategy and 3 users(Purchase executive, Purchase Manager, Finance Manager)
    Regards
    Jagadish

    Hi
    You need to assign the Rlease codes to the users, in the authorisation profiles.
    In the role for authprization of transaction ME28, you have the authorisation object , in which you assign the release codes to the user
    please take help of basis consultant in role creation
    Thanks & Regards
    Kishore

  • PO release strategies with Contract

    Hi,
    implementing a PO release strategy (SAP-MM module)I need to consider the case in which a PO is assigned to a Contract.
    If so, different release strategies should be selected according to the PO value.
    Possible cases:
    S0-strategy 0: Contract does not exist, PO value>=0eur
    S1-strategy 1: Contract exists, PO value>=100eur
    S2-strategy 2: Contract exists, PO value>=200eur
    Is someone aware if it is possible to activate such release strategy without defining manually in the characteristic for CEKKO-KONNR field all possible contract single values (entire range)?
    Thanks a lot for helping!
    Regards,
    Elisabetta Rizza
    Please contact me at following mail addresses:
    [email protected]
    [email protected]
    Hi Elisabetta,
    I've moved this here because it is a more appropriate thread.  BPX is the place for discussing the role of the buisness process expert.  This is a MM question
    Message was edited by: Marilyn Pratt

    Dear Amit,
    Requirement: If GR posting date exceeded 45 days than delivery date set in PO, then delivery date in PO has to be changed to current system date and at the same time New Release Strategy (B1) has to be triggered with one release code (02) automatically.
    So in that case the values in Release Strategy (A1) and (B1) would remain same,,, as you suggested we will assign the value 01 u2013 USRC1 to Rel Strategy (A1) and 02 u2013 USRC1 to Rel Strategy (B1) and the same we will try to incorporate in the coding of Exit u2018'M06E0004'
    We will check the process and confirm the same.
    Thanks for your suggestion.
    regards,
    Urendra Kumar

  • Release Strategies in Purchase Order - possible values of caracteristics

    Hello,
    I have the following situation at hand.
    We use in a company code a release strategy for POs. One of the caracteristics is the "plant" (CEKKO-WERKS, multiple values). Strategy is working fine.
    Now I have to implement in another company code- in the same Client - the PO release strategy but this company code has about 800 Plants asociated! moreover, the release strategies in this new company are not dependent on the "plant"!
    I can not change the caracteristics in the Release strateg because this would affect the already working strategies  and SAP does not allow to asign another Class to the PO release groups.
    Is there any way I can prevent that I have to create release strategies with each of them 800 Plants in the caracteristics "Plant" ?
    Can I use something generic in the caracteristics field of the strategy?
    Thanks for any help. It would save me a lot of time!
    Aart

    Note 493900 - FAQ: Release Strategy
    1. Question :
    Why is the release strategy not determined?
    Answer :
    Please check the following points :
    You can not use Release without classification and Release with classification.
    If there is an entry present in Release Group table (T16FG-FRGOT) only release with classification can be used.
    If you use version management, the determination of the release strategy starts when the version is completed.
    You complete a version by setting the "version completed" indicator in the version tab.
    Cost Center values (CEBAN-KOSTL) and Vendor values (CEBAN-LIFNR) in the release strategy characteristics should be entered with leading zeros.
    This is true for the other structures as well (CEKKO and CESSR). See note 52225.
    For OVERALL RELEASE (purchase order and purchase requisition) the item fields such as Plant and Material Group will be aggregated to header level.
    For example you use Plant as one of your characteristics. If all items do not belong to the same plant then the relase strategy will not be found unless you have maintained a blank value as one of your allowed values for the characteristic Plant. If all items belong to the same plant then that plant is aggregated to the header; if one or more is different then a blank is aggregated to the header. See note 47089.

  • Purchase Order Release Strategies for Changed Amount

    Hi Gurus,
    We have a unique request from the business to set the release strategies for POs based on the Still to Deliver amount, not the Net Total Amount of the PO.
    Example: Configuration is PO total amount <$5K requires only L1 approval.  PO total amount >$5K requires L1 and L2 approval.  PO was created for $8K and was release using L1 and L2 approvals.  Receipts were posted to PO in the amount of $7K.  Now the buyer has added an additional line item for $1K.  The PO total amount now shows $9K ($8K + $1K), the Still to Deliver field shows only $2K ($1K from original remaining amount + $1K from new line item).  Business wants the release strategy for this change order to go through L1 only since the Still to Deliver amount is <$5K.
    Has anyone done this before?  Any ideas??
    Thanks,
    Gabe

    from http://help.sap.com/saphelp_40b/helpdata/fr/dd/2d547bb435d1118b3f0060b03ca329/content.htm
    User exit M06E0004 is provided to enable you to adapt the release strategy determination process to meet your requirements.
    This user exit allows you to change the communication structure for determining the release strategy for purchasing documents.
    The following user fields are available:
    USRC1
    USRC2
    USRN1
    USRN2
    In addition, communication structure CEKKOZZ is available, allowing you to use your own fields.

  • Are these requisition release strategies common?

    All,
    I’m designing new requisition release strategies for indirect requisitions at a chemical industry client.  I’d like to know how often you have seen the following sorts of design before:
    Existing design: Item-based release with workflow, with three dollar levels.  At the lowest levels, two strategies for each cost center approver (the one used is based on whether the desired vendor is foreign or domestic).  Characteristics assign several cost centers to each approver.  Strategies and codes are named for users, so we change configuration whenever someone changes jobs.  The codes are linked to positions, which are attached to user IDs.  Result: about 80 release codes and 140 strategies, taking a lot of time to maintain.
    Current redesign: Overall release, using 6 strategies and 6 codes based on dollar level and foreign vs. domestic.  A user exit selects the approver for each code from a custom table that stores the user IDs for each cost center, with a custom maintenance transaction for the table.
    Now the client wants both individual approval by cost center owner and items with different cost centers on a single requisition combined with approval of the overall purchase.  I’m considering item-based approval of requisitions, with the user exit and custom table, and adding overall approval of indirect POs with the overall approvers.
    Thanks for your help!

    Hi,
    No-Requisition release strategies are not common, one need to design release strategies based on business requirement. Release strategies looks simple after designing but its design needs creating thought to it.
    In your case, you can go for designing redesigning release strategies for Overall release with using 6 strategies and 6 release codes. Considering you have configured release strategies with all release values for PO document type ,PO value and Purchasing group. Now design a custom table and go for followings:
    Client---Pur Group--Rel Code1-- Rel Code2-- Rel Code3-- Rel Code4-- Rel Code5-- Rel Code6
    The search help is required to pull in purchasing group details from T024 table and SAP user ID from Table USR01
    Concept: Create Purchasing Group (OME4) as Department & assign the Department name to Cost center (KS01).
    For more refer a discussion:
    PR release: place holder for Cost center and Material grp
    NOTE: User training required crate requisition for one department only where only one cost center involved- No requisition creation allowed for multiple cost center.
    You can also go for other concept designing of your Requisition release strategies
    Regards,
    Biju K

  • Transport of Number range and release proceure and split valuation

    Dear Gurus,
    Can we transport number ranges from PRD server to Quality Server?
    Also, how will we trasport split valuation and release procedure?
    Kindly suggest..

    Hi
    Number ranges you have to create directly as it is not transportable.
    For release Strategy details, all your Release config details are transported Except for the below details
    1. Characteristics &  values assigned to it ( master data)
    2. Class & assigned characteristics to it (master data)
    3. Values/ranges inside the Release strategies ( classification details).
    These three details are to be recreated/assigned in the client you intend to work upon.
    Regards
    SAM

  • Release Strategies not works - When multiple material group in a single P.O

    Hai,
    This related to Release Strategies in SAP- IS -Retail.
    The Material group was one of the character in the Rel Strgy. 
    1) If i create a P.O for the item which is related to " X" material group , Rel Strgy been set to P.O
    2) If i create a P.O for the item which is related to " Y" material group ,  Rel Strgy been set to P.O
    If I combine material group "X' & "y" in a same Purchase order , then RELEASE STRATGY NOT BEEN SET TO P.O .
    How to make this as possible in SAP -IS-Retail - Version 6.0
    Thanks,
    PS

    Hi,
    Generally it is not advisable to use item level characteristics for overall release . Please refer the sap note 493900
    Cost Center values (CEBAN-KOSTL) and Vendor values (CEBAN-LIFNR) in the release strategy characteristics should be entered with leading zeros.
    This is true for the other structures as well (CEKKO and CESSR). See note 52225.
    For OVERALL RELEASE (purchase order and purchase requisition) the item fields such as Plant and Material Group will be aggregated to header level.
    For example you use Plant as one of your characteristics. If all items do not belong to the same plant then the relase strategy will not be found unless you have maintained a blank value as one of your allowed values for the characteristic Plant. If all items belong to the same plant then that plant is aggregated to the header; if one or more is different then a blank is aggregated to the header. See note 47089.
    you have to maintain blank value in CT04 for material group and the same thing must be maintained for all strategies.
    The release procedure for purchasing documents is carried out on header level. For this, the following values are aggregated from the items on header level:
    item value
    plant
    material group
    Example WERK:
    The plant is only aggregated on header level if all items contain the same plant. If only one alternative plant exists, ' ' is aggregated on header level.
    A release strategy is then searched for with this value.
    Of course, a corresponding strategy is only found if the value ' ' was maintained for the characteristic 'Value' as an object value.
    The same functionality applies to the  plant

  • Purchase requisition : problem with check release Strategies

    Hi all,
    i created a new class, new release group, new release codes etc. I think all is ok but when i launch the transaction OMGQCK for check release Strategies the system give me an error in node 'Check re release indicators' : Define a release indicator for the status "released".
    But how can i do that, i created two release indicator : 'X' for blocked and 'V' for launched but what are the options for purchase requisition ?
    Is there a special value to give the release indicator 'released' ?
    Thanks for your help.
    Edited by: ToraTora on Mar 31, 2011 5:46 PM

    Hi,
    Goto SPRO -> Materials Management -> Purchasing -> Purchase Requisition -> Release Procedure -> Procedure with classification -> Setup Procedure with Classification
    select release indicator
    by default, you will be having the following release indicators in the system,
    1     Request for quotation
    2     RFQ/purchase order
    3     RFQ/PO no change of date
    4     RFQ/PO no changes
    A     Fixed RFQ
    B     Fixed RFQ/purchase order
    X     Blocked
    please check whether you have got these or else create and then assign them to the release strategies.

  • Tables for Release strategies

    Hi ...
    I was referring to MM table doc , in that it is mentioned table EBELN & EBELP are for Purchase Order header / Line and BANFN & BNFPO are for PR header/ Line.
    But for release strategy ...people told me to refer CEKKO for PO and CEBAN for PR.
    does it mean that release strategy refers to different tables for execution ( and I believe these tables are used for release strategy purpose only and if Yes then at what point PO / PR data gets updated in these tables)
    Regards
    Suresh

    Hi,
    Please find release tables used in MM.
    EKAB       Release Documentation 
    EKEH        Scheduling Agreement Release Documentation 
    EKEK        Header Data for Scheduling Agreement Releases 
    T161E       Release Codes 
    T161F       Release Point Assignment for Purchase Requisition
    T161G       Release Prerequisite, Purchase Requisition 
    T161H       Fields for Release Procedure, Purchase Requisitio
    T161I        Determination of Release Strategy 
    T161S       Release Indicator, Purchase Requisition 
    T161U      Texts for Release Indicator 
    T163P        Release Creation Profile 
    T163S        Description for Release Creation Profile 
    T16FB        Release Indicators: Purchasing Document 
    T16FC        Release Codes 
    T16FD        Description of Release Codes 
    T16FE        Descriptions of Release Indicators: Purchasing Do 
    T16FG        Release Groups 
    T16FH        Descriptions of Release Groups 
    T16FK        Release Statuses 
    T16FS        Release Strategies 
    I think, it will help u.
    Ishu

Maybe you are looking for

  • Cinema display screen fault

    My 24" Apple aluminium cinema display, is suffering from numerous horizontal white blocky type lines all over the screen. This has just appeared today and the unit is approx 6 years old. The programmes can just about still be seen in the background a

  • Is there any way to password protect a file/document in  Pages?

    Is there anyway to password protect a file/document in  "pages" ?

  • RSS screensaver + WordPress

    Hello forum. Here is my issue. I have a photo blog based on WordPress. I'm used to post photos on it very often. I'd like to use those pictures for my screensaver. It looks obvious to use the RSS screensaver, but with the feed provided by WordPress,

  • Quicktime problem on windows 7

    while trying to install itunes 10 a message popped up telling me that a newer version of quicktime has already been installed quicktime is not in the uninstall list in the control panel any suggestions

  • Problems opening a mov file on quicktime

    Hey guys, i just purchased a mac and im having some problems opening a MOV. file on quicktime. FOr some reason im just getting sound and no video. Can anyone please help me out? Is there some extensions i have to download? Please let me know thanks.