Hi All
Is there any data base table in which Release strategy characteristic values are stored.
Gobinathan G

Hi Gobinathan,
Go through the following link for complete procedure for PR Release.
http://www.sapstudymaterials.com/2008/08/purchase-requisition-pr-release.html
Check table CAWN.
Regards,
Nani.

Similar Messages

  • Release Strategy Characteristic Upload through LSMW.

    Release Strategy Characteristic Upload through LSMW.
    Introduction:
    In case of Purchase order, we need to maintain Release Strategy each year. This is due to organizational changes. Due to huge organization, this is around one week activity for us. Reason, we need to maintain characteristics for around 300 different release strategies. Since, we can't transport "Characteristics" from one system to other, we need to maintain them in Quality as well as in Production system.
    Issue: We tried to use option of LSMW to maintain these "Characteristics". But, system is giving error as "Logical Path is not available".
    Question: Who is responsible to create this "Logical Path" and where it can be done?

    Hi,
    I think you moved LSMW from test to production and this might be happening due to this fact. Please redo steps in LSMW for:
    Specify Files
    Assign Files
    Read Data
    Create completely new paths, and allow system to recreate (you need the right authorization). This might help I hope.
    Regards,
    Tomek

  • PO Release Strategy on Value Based

    Dear All My Friends,
    i want to define the following Release Strategy, please advice how it will be done
    Person A will Release PO  value <=50,000/-
    Person B will Release PO Value >50000 and <=100000
    Person C will Release PO Value >100000
    please help me
    Thanks and Regards,
    Rajesh G

    Hi,
    SPRO -> Material Management -> Purchasing -> Purchase Order -> Release Procedure for Purchase Orders.
    Three steps involved in release process of purchase order.
    1) Edit Characteristic: -
    Create characteristic for release purchase order. If you want to release purchase order on total value. So you can create characteristic for Total net value. Take reference of CEKKO structure and GNETW field for Total net value in additional data of characteristic. E.g :- Total net value u2013 GNETWu2026Click on intervals allowed check box ..
    2) Edit Class: -
    After creation of characteristic, create class for release purchase order. In which you can take reference of
    Class Type: - 032,
    Status: - Release,
    Class group: - Release strategy class,
    And put reference of your characteristic, which are created by you in first step.
    E.g: - Class u2013 REL_PO
    3)Define Release Procedure of purchase order: -
    In this step four processes involved.
    1) Release Groups
    2) Release Codes
    3) Release indicator
    4) Release Strategies
    1) Release Group: - In which you can define release strategy group
    For Exa.: - Release group : - 01,Release object: - 01, Class: - REL_PO.
    2) Release code: - In which you can define release code. Enter value as
    Release group: - 01,release code: -01 u2013 Purchase Head,
    Release group: -01, release code: - 02 u2013 Auditor.
    3) Release indicator: - In this step you have to define release indicator.
    Like X u2013 Blocked, I u2013 Under process, S u2013 Release.
    4) Release Strategy: - This is the final step for release strategy.
    Assign release code 01, 02.
    Click on release prerequisites, select 02 u2013 check box and click on continue.
    Click on release status button, enter release indicator X, I, S and click continue
    Click on classification button, Enter values of Total net value for which you want to created release strategy.
    Person A will Release PO value <=50,000/-
    Person B will Release PO Value >50000 and <=100000
    Person C will Release PO Value >100000
    Utsav

  • PR Release Strategy-Characteristic Z_GSWRT must be linked with CEBAN-GFWRT

    Dear Experts,
    I did a simple config for PR Release strategy. using Plant(Z_WERKS) and Item values(Z_GSWRT )
    chose overall PR Release. During simulate release
    the second level release its not able to simulate and it says check Prerequistie for second level
    Can somebody expain why the system is giving me this below message.
    Characteristic Z_GSWRT must be linked with CEBAN-GFWRT
    Message no. ME_RELCHK056
    Thank you
    Imraan

    Thanks for the solution that helped me to understand PR Release much better.
    Values: Plant (WERKS)& Itemvalue (GSWRT) & Now I created (GFWRT) For another class for Overall PR release.
    In my PR Release strategy with 2 levels I have these below things:
    Rel Groups : 1 Group with name AA
    Rel Codes: For AA is A1, For another AA is A2.
    Rel Indicator: nothing is selected, am not sure what to do in this step.
    Rel Strategy : For AA is S1, For another AA is S2.
    I created class Z_GFWRT but am not sure which group I should assign  it AA or I have to create another new group for Overall release.
    After I checked the release strategy the system is giving me this below message.
    No release group exists
    Message no. ME_RELCHK014
    Please can you walkme through in this process. This is first time I am creating a PR Release.
    Thank you Very Much
    Imraan

  • PR Release Strategy Characteristic Changes

    I created several characteristics for a purchase req. release strategy. I added an incorrect value and then deleted it on one of the characteristics. Is there anything else that needs to be done to ensure that value is really deleted?
    I'm receiveing an error when I ALE that I have documents that won't post for the error:
    REQ_PURCH_ORG : Value "Structure Exists " not found
    Structure exists is not a value associated with this characteristic.

    Thanks for the solution that helped me to understand PR Release much better.
    Values: Plant (WERKS)& Itemvalue (GSWRT) & Now I created (GFWRT) For another class for Overall PR release.
    In my PR Release strategy with 2 levels I have these below things:
    Rel Groups : 1 Group with name AA
    Rel Codes: For AA is A1, For another AA is A2.
    Rel Indicator: nothing is selected, am not sure what to do in this step.
    Rel Strategy : For AA is S1, For another AA is S2.
    I created class Z_GFWRT but am not sure which group I should assign  it AA or I have to create another new group for Overall release.
    After I checked the release strategy the system is giving me this below message.
    No release group exists
    Message no. ME_RELCHK014
    Please can you walkme through in this process. This is first time I am creating a PR Release.
    Thank you Very Much
    Imraan

  • Po release strategy - if value decreased

    Dears,
    If the Po value is decreased, I need the release strategy to be re triggered. As I know in standard its not possible. But can you help Is there any BADI or user exits can be used to accomplish this task.
    Regards
    Kamesh

    Hi,
    Use release indicator '4' or '6" during designing of release strategy.
    And
    If you want PO release strategy should trigger for reduced value ,then you can for User exit EXIT_SAPLEBND_002 or check to modify standard function module ME_REL_STRATEGIE_EKKO which help to reset existing release strategy for reduced/increased and/or values.
    For more check the SAP note:493900
    Regards,
    Biju K

  • Change in Purchase Order Release Strategy Values

    Dear All,
    I am in process of changing Purchase Order release strategy values.
    I have following release strategy -
                           Current Value                  (Proposed Value)
    Level 1 -         Upto INR 0.1 Mn               (Proposed value - Upto 1.0 Mn)
    Level 2 -         From 0.11 Mn to 0.5 Mn   (Proposed Value - From 1.01 Mn to 5.00 Mn)
    Level 3 -         From 0.51 Mn to 1.0 Mn   (Proposed Value - From 5.01 Mn to 10.0 Mn)
    Level 4 -         Above 1.0 Mn                  (Proposed Value - Above 10.0 Mn)
    My questions are -
    1) Will this change affect the existing Purchase Orders (already created) which are not yet released?
    2) Will this change affect the existing Purchase Orders (already created) which are released?
    3) Are there any risk factors?
    Can you pl. put light on above questions?
    Regards,
    Prashant Kolhatkar

    Hi,
    Actually, what you had given is not enough to determine if the existing PO will be impacted or not
    If you are just changing the classification but not changing the number of release level of the release code in the release strategy, the partial released PO will not be impacted unless there's PO changes. PO that are released will definitely not be impacted unless there are changed.
    In general, after a release strategy is determined for PO, SAP will retrieve the latest list of release code of that release strategy for display for that PO. If this list never change (mean you only change classification of the release strategy), then they will not be apparent to the user. But if this list change (you add new release code, replace existing release code or remove release code), then you will see some discrepency on screen as you will only see the modified list of release code and not the old list of release code
    Hope this help

  • Release strategy values

    Dear All,
    Is there any table to find the change documents for release strategy characteristics values. Or how to find who has changed the CL20N values
    Regards
    Kamesh

    Check in Table AUSP.

  • PR Old Release Strategy - triggering NEW Release strategy any change OLD PR

    Dear Gurus,
    We have implement item level PR release strategy,
    characteristic used:  1. Document type, 2. PR item Value, 3. Material Group, 4. Change date & 5. Account Assignment Category.
    BEfore the above implementation, there is a OLD PR release Strategy existing in the system at one level release.
    Now the issue, the OLD release Strategy status is release completed, now the user goes and change the PURCHASING GROUP in old PR, new release gets triggered. How to Stop this, system should not trigger NEW STRATEGY,
    Please advice
    REgards
    RS

    HI,
    If i use date created as a characteristic, then Old release strategy get reset and the no release strategy will be trigger henceforth, the status of the PR will be INACTIVE.
    ANy charateristic we use, there will be only 2 options for old released PRs, 1) It will reset the strategy to new one or 2) the old strategy will be reset and make the PR status as INACTIVE.
    Is this is standard behaviour? pleae advice
    Regards
    RS

  • Inconsistent characteristic value assignment

    Hi
    When I am trying to change the value of the characteristic for relase strategy  ; the system is giving me error
    "Inconsistent characteristic value assignment"
    Kindly reply me

    Check this answered link:
    Inconsistent characteristic value assignment
    Re: PO Release Strategy on Value Based

  • PR Release Strategy for MRP & Manually created PR

    There is a scenario in which it's required when,
    PR is generated automaticaly through MRP then Release strategt should be applicable and when
    PR is created manually then release strategy won't be applicale.
    Please suggest about this..........
                                                           Thanks in advance.

    Hi,
    You should have two document types ( as required by you here), MRP PR document type  & Manual PR document type.Link plant, MRP group and the default order types as MRP PR document type  in OMDT t.code.
    You should create release characteristics (CT04) with the table & field and add all release characteristics in release class. For document type release characteristics with CEBAN & BSART and do not keep value ZNB which you do not want, just keep value ZMNB. During design of release strategy keep value only for document type ZMNB with other character values.
    Regards,
    Biju K

  • Release strategy H8 Update

    Hi Experts,
    We wanted to know who changed the release strategy H8 value  in our SAP system.
    Found that PRD System release strategy GT value has been updated somehow with in six months.
    please let us know how to check find out who updated value?.
    Thanks
    Malai

    Hello Malai,
    I think that for "Release Strategy" questions you should opan a thread under category SAP Community Network Forums » SAP Solutions » ERP - Logistics Materials Management (MM).
    Please, go to  and formulate your question.
    Best regards,
    Rafa

  • Purchase order release strategy with a characteristic value as a variable

    Hi all,
    We have Purchase order release strategy based on the following characteristics:
    Total Net Order Value
    Purchasing Organization
    a few other custom fields
    We would like to add a characteristic based on the creator of the PO. In the purchasing department there are two person which have the authorization to create an release POs. The goal is now to check if the actual user, who release the PO, is different from the PO creator. The value of this characteristic may not be a fix value, it must be contain the name of the actual user name.
    Is there are a possibility to insert the characteristic value as a variable such as SY-UNAME instead a fix value?
    Thanks,
    Charles

    this is verymuch possible.  You can use unsed fields user1, user2 etc in CEKKO or (ii) insert a new field in CEKKOZZ and use the new field.  You need to build up logic in user-exit such that this field will take the value of person who had logged in. This can be done by ABAPer.
    Hope this resolves ur problem

  • Release strategy determination for PO item level characteristic value

    Hi Experts
    I have user material group as release characterstic for PO.
    I have created two line items with two different material groups.
    How the release strategy determination occurs when the two different material groups are linked to two different strategies?
    regards
    ramSiva

    Hi,
    in this case system is NOT able to find the release startegy.
    Please take care of the following explanation (see note 365604)
    o  For OVERALL RELEASE (purchase order and purchase requisition) the
       item fields such as Plant and Material Group will be aggregated
       to header level.
       For example you use Plant/material group
    as one of your characteristics. If all
    items do not belong to the same plant/material group
    then
    *******the relase strategy will not be found***********
    unless you have maintained a blank value as one
    of your allowed values for the characteristic Plant/material group
    . If all items
    belong to the same plant7material group
    then that plant is aggregated to the
    header; if one or more is different then a blank is aggregated to
    the header.
    If you use an overall release strategy all
    characteristics which you have defined in the customizing (CEKKO-MATKL
    must have the same value. If one item has material class x and the
    other y the system does not know with which material class it should
    look for a release strategy. Now the system sets the material class
    to 'blank' and tries to find a release strategy. If you do not have
    defined a blank entry in the customizing (Transaction: OMGS
    : OLME >release procedure for PO > rel. strategy ) the
    system won't find a release strategy.
    you need
    to add a blank value to your allowed characteristic values in your
    release strategy.  To do this you can define a blank value in your
    characteristic (CT04).  On the values screen leave the char.value
    blank and add a description and save.  Now in OMGS you can select
    this value as an allowed value for the characteristic.
    (Example:
    To avoid this you can do the following:
    - go into transaction CT04
    - enter the characteristic 'CEKKO-MATKL'
    - click on the tab 'values'
    - set a flag in 'additional values'
    - in the column 'Char. value' do not enter anything
    - in the column 'Description' enter a text like 'no material class'
    - save this setting
    Now
    - go into transaction OMGS -> button 'release strategy'
    -> button 'classification'
    - double click on CEKKO-MATKL' and set a flag in 'no material class' )
    Please also have a look into the attached note 365604 point  2d).
    BR
    Nadia Orlandi

  • Extracting values for characteristic on release strategy of Preq

    hello
    we have Preq release strategy based on classification and the release is based on amount. in the class, one of the characteristics contains the amount above which the strategy is being triggered: how can I extract all the values for all the strategies from this characteristic? is there a table for it?

    Hi,
    Please check the AUSP table for release strtegies and CAWN table for characteristics. Please check below link for additional information. Thanking you.
    Release strategy tables

Maybe you are looking for

  • Problema com Lançamento de Custos Complementares na MIGO

    Boa Tarde pessoal, tudo bom? Estou escrevendo aqui no Grupos para ver se alguem pode me ajudar. Aqui na empresa onde estou trabalhando estamos com um caso muito estranho acontecendo em alguns pedidos. E o pior o caso acontece de forma intrmitente, ou

  • External display problems

    For about a year I have been using a mini-dvi to hdmi adapter to hook up my MacBook (white, early 2008) to my tv without difficulty. Recently, I tried to watch a movie on my tv. The screen flashed on the MacBook end, as it usually does, but nothing c

  • CS4 install problem "you cannot run...architecture not supported" error

    Just received my copy of CS4 (Mac) from amazon.com. Installed it. But could not get it to run. Got a "You cannot run....architecture not supported" error message. Can't understand why? This is my first version of Photoshop CS. Didn't install CS3...et

  • HT1414 what to pick? ipod or ipad? i am also tempted by the amazon kindle fire hd.

    Hey, I am very confused. For a present, my relatives asked me to pick whatver i want, and i really want an apple device of my own. What do i pick? i really dont need a phone, i alredy have a samsung galaxy.

  • SAP BW 7.3: RSTRAN018 after adding attribute to an infoobject

    Hello, i added an attribute to an infoobject and tried to activate this. In the log messages i received the message RSTRAN018 "Generation status of transformation XY will be reset". I never got this message in SAP BW 7.0. Is this just a kind of infor