Preliminary cost and std cost estimate

Hi all,
I tried to find out the reason behind the material price difference I am getting by clicking *COST ESTIMATE* in KKF6N and the price in CK11N . In KKF6N I am getting the price 500 and while doing CK11N I am getting 2000. please let me know how price is being calculated in both the screens.
Material is -- HALB
STD Price in Material master -- 200
moving price -- 50
stock -- 20
Costing variant in CK11N --- PPC1
Costing variant in KKF6N --- YPRM Premilinary PCC
Regards
Kumar

Hi,
check both costing variants used. Looks like the valuation variant within the costing variant uses moving averagre price in KKF6N and standard price in CK11N to valuate the material quantity.
Best regards, Christian

Similar Messages

  • Current PO cost and std cost :------ in which table this will be present

    current PO cost and std cost :------ in which table this will be present

    Hi
    For PO cost check it in tcode SE16
    Table name EKBE field Name WRBTR
    For Std price u can check it in Table MBEW - VERPR, STPRS
    Check it out.
    Regards,
    Raman

  • Preliminary costing and Simultaneous costing

    hello gurus,
                  can any one explain the difference between Preliminary costing and Simultaneous costing in Product cost by Period.
    Regards
    rihana

    In product cost by period you are generally using product cost collectors.  The preliminary cost estimate is the estimated cost for the product cost collector prior to manufacturing.  The cost estimate is calculated when the product cost collector is saved and the estimate is based on the costing variant that is assigned.  Simultaneous costing happens as a result of manufanufacturing and the confirmation process.  It represents the cost of the materials, activitities, and overhead that are actually charged to the product cost collector.  Typically, with product cost collectors materials and activities are backflushed.  The amount of the backflush can be based on the preliminary product cost estimate or a standard cost estimate.  Simultaneous costing uses a different costing variant then preliminary costing, so valuation strategies for materials, activities, and overhead can be different for both as well.
    thanks,

  • Target cost and planned cost

    What is the difference between Target cost and planned cost in discrete production orders? Please advise.

    Dear
    Planned costs will be updated after creation of production order.
    Target costs will be updated after delivery of the production order.
    Plan cost    = Plan qty X Planned price (std. cost estimate)
    Actual cost = Actual qty X Actual price
    Target Cost = Actual qty X Planned price (std. cost estimate)

  • Target cost and actual cost not picking in production order

    Hello,
    The target cost and actual cost is not updating in production order when I display it in CO03 in cost analysis.
    Even though we have maintained planned price in KP26.
    Please suggest how it can be populated.
    Best Regards,
    Tapan

    Hi Tapan
    For Target cost
    1. Your std cost must be released before Goods Receipt
    2. There must be goods receipt posted on the prod order
    3. You must calculate variances in KKS1/2
    For Actual Cost
    1. Post Goods receipt and Goods issues
    2. See if any mat movements are pending in COGI
    3. Ensure that operation is confirmed in PP and no entry is lying in COFC
    Regards
    Ajay M

  • Target Cost and Actual Cost

    Hi All,
    When is the target cost and actual cost gets populated and from where does the data comes from liek labour,machine,overhead cost comes?
    Thanks in advance

    Dear Friend,
    speaking from controlling point of view, target and actual costs will be flown from "costing variant planned" and "costing variant actual" respectively.In above mentioned varinats, whats the process has to be followed to calculate  material costs,activty costs,overhead costs etc will be defined. These variants will be assigned in order type dependent parameters OPL8.
    Target Costs - In standard cost estimate(ck11n),target cost will be calculated  in the following way
                              -material cost from material master and BOM
                              - activity costs from routing( for this u need to plan the activity costs in KP26)
                              - other costs from the definitions of planned costing variant.
                       - after running the standard cost estimate,u need to mark n release(ck24).
    Actual Costs - material costs frm goods issues (via goods mvmts thru MBIA,MB1B etc) against
                          production/process order.
                              - activity costs(as per the price u plannned in KP26)through  operation confirmation in
                                COR6N/CO11N.
                              - any other costs like overheads,cost center issues etc as per the process defined
                                in 'actual costing variant'.
    Hope this will clear your doubt.
    Rams.

  • Costing  include inhose production cost and subcontractign cost

    Dear Friends,
    my requirement is my material is producing house and giving subcontracting so cost should include in house cost and subcontracting cost also , is it possible? please tell me how to do , what is parameter is required.
    Regards,
    Nagesh

    Dear friends,
    in material master in mrp2 we have maintained procurement "X", here if we maintain -special procument -30, it will take only sub contracting cost, it is removed, it will take inhouse cost, i removed 30, while using PP02 in routing it showing error that is maintain purchase info record but we have maintain sub contracting purchase info recored - why it is not taking in routing
    we want to calculate internal and external cost in cost estimate.
    reg
    nagesh

  • Diff erence between  target cost  and plan cost

    what is the diffenece between target cost and plan cost , in product cost controlling?

    Hi
    Plan cost is some thing anticipated cost i.e cost estimates here we can say the standard cost.
    Target cost is the cost of (yeild) of the production at plan cost.
    Ex: Standard cost for X product is 10
          production lot size is 100
          production yeild is 90
    then your plan cost will be = 1000
    and target cost will be       =   900
    and the variance of 100 of 10 units will be as variance.
    Regards
    Laxmiprasad

  • In which table production order planned cost and actual cost i can see?

    Dear PP Guru,s,
    from which table i can see productuion order planned and actaul cost. i checked following tables AUFK, AFVC, AFVV, CAUFV, AFRU, AFKO, AFPO. but i did not found planned cost and actual cost field. is there any other way to get this data with respect production order?
    Regards,
    sree

    Dear,
    Planned and actual costs of prod order from COEP, COSS, COSP  S027 tables
    production order shows the planned cost based on the quantity structure.
    Please refer my reply in this thread for details,
    Re: Actual Halb Material Cost
    Regards,
    R.Brahmankar

  • Function Module to find Planned Costs and Actual Costs against WBS element

    Dear All,
    We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
    Are there any function modules to retrieve this value?
    Thanks for the help.
    Warm Regards,
    Judith

    Hi,
    The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
    Please let me know if this helps.
    jibat

  • Estimated Cost and Actual Cost

    Hi Friends,
               Can someone tell me, which MM tables(logically database) has these fields stored?? Estimated cost and Actual cost??
    Note : Where and How can I find the logical data base??
    Thanks alot in advance,

    Yes thank so much for your quick help.
    I see here we can get 1- Plan cots , 4 Actual cost, But in PMCO, how can we get the estimated cost, I see that WRTTP = 1 also contain the value for estimated cost but not plan cost . Please help me.
    Thanks

  • IW32  needed Plan Cost and Actual Cost table name

    Hello ,
    In IW32 transaction Plan Cost and Actual cost in cost tab ---Table Name.
    Req: needed  plan cost & actual cost table names  for particular order number.( For New Report )
    Can you please let me know where Plan cost & actual cost get stored in IW32 in Cost tab ( table name / function module name ) or how its get calcualted for particular order number.
    Thanks in advance !
    Regards
    Rahul

    hi ,
    i too had same issue , i wrote following FS for that :
    Actual and planned cost  from PMCO-WRT00 to WRT12(the sum of values should be considered for actual as well as planned ) for  PMCO-OBJNR taken from CAUFV -OBJNR for order number  AFIH-AUFNR  and also currency from CAUFV-WAERS .
    Actual cost will have valuation type PMCO-WRTTP = 4 and planned cost will have valuation type  PMCO-WRTTP = 1 , which will be placed in different column
    hope this helps
    regards
    satish

  • Costs and settled costs layout in standard reports

    Hello guys !
    what needs to be done in order to have a report, for example, S_ALR_87013543 , splitted by costs and settled costs (debit/credit) ? I can't find a layout or smth.
    Thanks guys.
    Laimonas

    Hi
    Include this ZPP2 in a separate report group (GR51)... After that,
    1. Create the transaction code,say, ZF01_TCODE from Se93
    2. Choose "Transaction with parameters".. Press enter
    3. Enter START_REPORT in the Transaction field and press Enter
    4. Select the Skip initial screen and Inherit GUI attributes check boxes
    5. On the same screen, scroll down to the Default Values table and select parameters D_SREPOVARI-REPORTTYPE and
    D_SREPOVARI-REPORT.
    6. Enter RW for the report type and your report group ZCC8 as the report value
    7. Now you can save your transaction and transport it to other systems
    Regards
    Ajay M

  • Huge Variance between Target cost and Actual Cost

    Hi,
    In Product Costing,I am getting Huge variance between Target cost and Actual Cost.It is showing the Target Cost as ZERO.Why i am getting this target cost as Zero? what could be the reason? Kindly help me in fix this issue.
    Thanks
    Supriya

    Dear,
    First do the GR final DEV for Production order
    You need to do the variance calculation in KKS2, then when you save the variance, the target cost is calculated.
    Target cost appear after GR.  And you will get the Variance also right.
    Please try and come back.
    Regards,
    R.Brahmankar

  • Function Module to Find Actual costs and Total Cost Commitments

    Hi PS Experts ,
    Please let me know if there  is any function module to  find Acutal costs and Total cost commitments by passing WBS element as Input .
    Regards,
    Karan

    Hi Karan,
    I think for actual cost - there is definately one FM availbale. Try to find it out.
    Just ensure - if you are using Network Activity then you may have to pass NWA OBJNR into this FM to get actual cost. As some entry posting happens against NWA like Timesheet. Hope it will give you some idea to get rid on your issue.

Maybe you are looking for

  • Font upload in SAP

    Can you please provide me with the steps required to upload a true type font in SAP. I have tried using transaction SE73 but somehow i do not get the desired effect of the fonts when viewed through the output of a smart form. A document detailing thi

  • Sales requirement report using ALV

    Sales Register Requirement Specifications:---- 1.Fields on selection screen (input screen) : Plant Code From to , Distributional Channel  from to , Division from to , Customer Code from to , Period From to , Material Code (can be used using *) . 2.Fi

  • ORA-00600:  arguments: [srsale_2], [0], [147], [], [], [], [], []

    Hi, I'm using Oracle Database 9.0.1.1.1 on MS NT SP6. Error: ORA-00600: arguments: [srsale_2], [0], [147], [], [], [], [], [] This error happens when I create a Materialized View or a Table with a query, selecting data on more than one partition of a

  • Editable records in list output.

    dear gurus, i have a small query regarding lists. how can we make the list output entries editable and once i edit a field it has to be updated in the internal table and a new list should be shown with the changes made in the list. any sort of help i

  • Changing from EPG to HTTP...

    Hi We have had speed issues running apex on epg so decided to migrate to using the Oracle HTTP server. I have donwloaded and installed the webtier software and finally discovered which dads.conf file I should be editing.... Now we get the following e