Hi,
While doing Cost Estimate at step  Marking-- price it showing in future price,   after releasing its getting updated as current price in Material Master upto this fine.  But it should show previos price also in Material Master.. I have verified Price Change document its showing old price and new price also..
my question why its not getting update in previous planned price field in material master costing-2 view? I think its standard behavour..no additional confg required for this..
Appreciate your inputs!
Thnks
Srinu

HI,
yes this is standard functionality. Check if there is no previous released plan cost estimate (eg due to deletion using CKR1) so there is nothing to move to the previous price field in material master.
Best regards, Christian

Similar Messages

  • ME31K Net Price not Update

    Dear All,
    In a service contract ME31K net price(ESLL- NETWR) of service not updated.its shown zero value in gray field on every time.
    We are using standard procedure for service contract :MS0000".and also i have check PRS condition but it doesn't work.
    I have also read many thought relelated to same issue but not getting proper answer.
    Please help on priority basis.
    Thanks & Regards,
    Dishant Mistry

    Dear Dishant,
    Just a clarification, are you sure that you are talking about ESLL- NETWR, since usually we maintain price for service contracts in ESLL-TBTWR (Service level), so that automatically it calculates the net value for the respective service and updates in ESLL- NETWR.
    Note: Once you maintain the value in ESLL-TBTWR, the program would some up all the service value for the item and displays in EKPO-NETPR.
    Please find the below screenshots for your reference.
    Please let me know, if you require any clarification.
    Thanks & Regards,
    Narayana N

  • Valuation Type Price not updating in the PR

    We are using two valuation types for a material.
    Valuation type(New)in Material master has some price value in it Ex: 50 dollars per unit and Valuation type (Expense) is with Zero value.
    While creating a Purchase Requisition,default valuation type(New) gets updated and if we change the valuation type to (Expense) in the PR,there is no change in the Price.Actually the price should be Zero as defined in Material Master.
    Why the price is not updating ????
    Apperciating ur immediate response.

    Hi,
    During PR creation, Valuation Price is to be maintained derogatorily and generally it gets defaulted from Material Master.
    Once the Valuation Type "NEW" is getting defaulted in PR then it is copying the price from this and after changing the valuation type it doesn't change the Price since the valuation price obligation has already been fulfilled.
    So if you will stop defaulting the Valuation Type "NEW" for the material then it will ask Valuation type in PR and then it will pick up the price for that Valuation type.
    Default Valuation Type is maintained in OMWC
    Go to OMWC, there click on "Global Categories", here position cursor on the Valuation category (Maintained for Material Master) and click on "Change" button, here check have you entered any Valuation type "NEW" in field "Default: val.type ext.procure."

  • Last Evaluated Price not updating

    Hi,
    I have a very wierd issue which I have never seen before as explained below. The system is 8.82 PL 6.
    Problem: The Last Evaluated price (LEP) is not updating on Item Master Data (IMD) under certain conditions.
    Explanations:
    1. All items have a valuation method of FIFO
    2. For a particular item let us call it 101381, if I open the IMD, select LEP, the price shows up as 516.80
    3. There are definitely Goods Receipts for this item with a lower price than 516.80
    4. I run the 'Inventory Valuation Simulation Report' with blank From-Item and To-Item, i.e. for all items, calc. method as moving average, Posting date blank and WHs checked off
    5. There are thousands of items in our IMD but obviously, the report that comes up just shows the first item on our IMD 100000, and if we want to see 101381, we need to click the green right arrow 1381 times. So instead of scrolling over, I simply click OK to close this report, assuming that the LEP for 101381 has been updated
    6. I once again open the IMD for 101381 and choose LEP. Strangely, the LEP price still shows as 516.80!
    7. Then I run the report for a block of Items say from 101380 to 101390, keeping all other criteria the same as before
    8. This time, I click the green arrow 10 times to scroll from 101380 to 101390 and then clck OK to close the report.
    9. Now if I open the Item 101381 and check the LEP, it has been updated to 510.78!!!
    10. The same thing happens, i.e. the LEP gets updated if I simply select just 1 item i.e. FROM 101381 TO 101381.
    Why does the LEP not get updated automatically when all Items are taken at once? There is no way the users are going to click the green right arrow 20000 times just to refresh the LEP on all 20000 items. I am not sure if this is a bug in this PL?
    I have tested this extensively and any positive suggestions will be greatly appreciated.
    Thanks,
    Ajay Audich

    Hi,
    Please refer SAP note:
    1952446 - Inventory audit report updates item's last evaluated
    price
    Thanks & Regards,
    Nagarajan

  • Actual activity price not updating in production order

    Hi All,
    I am facing one problem, that actual price for activities are not updating in production order while plan price are updated. Earlier both plan and activity prices were getting upadated but now actual price is not updating for any material. I have tried at the same material also but it is not getting updated. Actual hours are updated in confirmation of production order but not price. If somebody could suggest the reason it will be great.

    Dear Nitin,
    Thanx to all for valuable input. Problem is solved.
    Nice to see That your problem is solved
    But Can you let the Forum Members know
    where was the exact problem & how it is solved
    Regards
    Madhu Kumar

  • Periodic Unit Price not update/release to Standard Price

    Dear Gurus,
    We have a problem, when closing period is done the PUP (closing period) not update/relase to Standard price (in future period).  We have checked all the steps during the closing period, and all seems to be right.
    The closing period is not more than 2 period, we closing April 2014.
    I have checked note 666681.
    Maybe Gurus can tell me something that i missed.
    Please help
    Regards,
    Beto

    Hi Szymon,
    So the OSS note saying that PUP from April 2014 cannot update to May 2014, the earliest is in June 2014?
    I tested the same scenario in testing server and it work.  The PUP get update to standard price in period May.
    It just doesn't make sense, the PUP is an average price within April transactions and it needs to update Standard price in May.
    Now it makes me more confuse..
    This is period 4
    This is period 5 (this is what we expecting), PUP period 4 = Standard price period 5
    Can you help me
    Thanks in advance
    Regards,
    Beto

  • Net Price not Updating Using BAPI : BAPI_CONTRACT_CREATE

    Dear Experts,
    I am facing an issue while creating CONTRACT using the bapi: BAPI_CONTRACT_CREATE. I am creating the Contract based on data from my excel sheet. And we are maintaining the INFO RECORDS for the same materials.
    In the excel sheet we are providing the NetPrice (NETPR) and creating the Contract. My issue is " instead of taking the Net Price from the excel it is taking the Net Price from Info Records". For Example, if for a Particular material the Net Price in our excel file is 125, after bapi execution, the net price is updating as 100 instead of 125 in Contract Creation( ME31k-ME33K). In the Info Records we are maintaining this net price(100) for that material.
    Thanks in Advance for your response.
    Regards,
    Prasad

    you can use BAPI_CONTRACT_CREATEFROMDATA
    * Create Contract Order Number [BAPI_CONTRACT_CREATEFROMDATA]
      CALL FUNCTION 'BAPI_CONTRACT_CREATEFROMDATA'
           EXPORTING
             contract_header_in      = header
             convert                 = 'X'
           IMPORTING
             salesdocument           = v_order
           TABLES
             return                  = t_return
             contract_items_in       = itab_item
             contract_items_inx      = itemx
             contract_partners       = t_partners
             contract_conditions_in  = t_conds
             contract_conditions_inx = t_condsx
             contract_data_in        = t_contract
             contract_text           = t_texts.

  • Line item net price not updated in overview screen net price&line item

    Hi ,
    We have down payment order with 10 line items
    In orders with billing plan, the sales line item net price, if we entered manual condition price (ZPNP) ,gets updated in item condition net value. But it does not simultaneously gets updated at once in 1) Sales order overview screen net value 2) Billing plan header 3)Sales order overview screen line item condition  net value. Updation at these three places happens only after clicked on header conditions.
    However, in case of the last item in the sales order, the updation happens simultaneously in all the 3 places i.e. 1)    item condition net value. 2) Sales order overview screen net value 3) Billing plan header 4) Sales order overview screen line item condition net value.
    This is also true for the order with only single line item. We are faced a information popup message every time we change the item net price u201CItem 000100(100 is last line item number in sales order) exists already; the entry ignored u201C. This happens in case of all line items except the last line item. Also this does not happen in case where there is a single line item in order.
    Our requirement: The moment the net price of an item is change manually, it should get updated at all the 4 places mentioned above like it does in case of the last line item.
    Kindly help me to fix this problem.
    Regards,
    Adikesav

    Hi,
    Can u elaborate ur query ?
    By this FM you cannot create a SO . Use FM --> BAPI_SALESORDER_CREATEFROMDAT2
    Regards,
    MAdhukar Shetty

  • Std price not updating

    Hi,
    When I am doing cost/mark/relaese for a material. The planned price in the mat master is being updated. But, the std price remains the same. Please help.
    Regards,
    Umesh

    Hi Umesh...,
    Check where Posting period/fiscal year for your company code. if posting period/fiscal year is not same as the costing run then you can't update the std price.
    To check it go to T.cod CK24 give the period and fiscal year the Click Mark allowance then you will directed to "Price update:organisational measure screen"
    check whethere any error is there against your company code if so then click on your company code and then select corresponding costing variant and costing verions in the popup scren and same.
    error mark will go. now you can update price for material.
    regards.

  • Cost Component Structure Price Not updating

    Hi,
    I have run cost estimate and successfully Mark and Released(CK40N). But when I see the cost estimate in CK13N its updating Ram Material cost (Overall and Lower level) but rest of the items not getting updated e.g. Mfg. Machine Time, Mfg Operter Labor, Quality Test Labour etc...
    I have checked in Routings each acitivity is assigned and checked. In log  "Mat xxxx, Routing does not match selection ID. ZC"
    Please advise how can will get update fields(mach cost, labour cost) with values in cost componenst strucure in cost estimate..
    Thanks
    Srinu

    Hi ,
    About why routing not match. Please inform your PP consultant as below :
    It could be your order type and plant selection id that assign are different. Please Check in OTD in OPL8 under routing tab also check in OPEB for automatic selection of routing also check the status of routing .
    If above cannot slove , please goto
    Goto OKKN->select the Costing variant that you have used in CK11N and under control tab goto quantity structure control
    -check the value or ID assigned for routing selection.
    As per this your routing gets selected in CK11N or CK40N.
    Thank you.

  • Price not updating through MR21

    Hi experts,
    While updating the  price through MR21. the system throws the error " ACurrent & future standard price exists for material "
    Can you explain how to rectify and update the new price.
    Thanks and Regards
    J.Francis

    Hi
    If Costing for the material is active , you cannot change the Price of the material using MR21.
    If you would like to change the material price, you need to first delete the Cost estimate of the material using T.code CKR1.
    You can check in the test run & then carryout the deletion of the cost estimate.
    Then do MR21 for material price changing.
    Hope it helps..
    regards,

  • Prices not updated automatically

    I have created a Pricing procedure MP0000 & condition records have been mainatained for the condition types,the price reflects in VA01 for document type-OR,but it is not reflecting while using VA31,can u pls let me know what adjustments to be done in order make price reflect in VA31.

    The document pricing procedure is assigned to sales document types in VOV8. By the way you should not modify SAP supplied document types like 'OR' and always should copy and create new document types from standard doc types like 'OR'.
    The customer pricing procedure along with document pricing procedure along with sales area is used to determine pricing procedure in a sales document in transaction OVKK

  • Net Price in PO Item not updating for Item Category "D"

    In purchase order with line item category "D" Service, upon first input of gross price in Service tab, Net Price in line item was updated successfully, but upon changing the gross price again in service tab, Net Price in line item is not updating anymore.
    I am using the condition type MWVS for tax calculation and a custom condition type ZPBX for the computation of Net Price = Gross Price - Tax. For ZPBX I used the calculation routine 82 (xkwert = komp-kzwi2 - xworkg.). For other item category, this is working fine. I am only having a problem in item category "D".
    I tried to debug and found out that upon entering a new gross price in service tab, the system is calculating the routine 82 first before even the gross price from service tab was transferred to the condition in line item. Because of that the routine 82 is calculating with the previous or old value in table KOMP since the gross price from service tab is not yet transfered to this table.
    Can anyone help me with this? What am I doing wrong?
    Thanks!

    Hi,
    Check which condition type used for Service PO pricing. Now use t. code: M/06 and enter that condition type and select check boxes of Amount/percent, Value, Qty Relation in Changes which can be made segment and save.
    Also select check box of u201CQty Conversionu201D in Control-2 segment and save.
    Now create service PO, change Price in service item level and see how NET PRICE changing.
    Regards,
    Biju K

  • Price and Tax info is not update in the Order Repository

    Hi All,
    I just try to complete a check out flow with all details and submit the order .
    But It's not updating  few details like Price and Tax information in the Order repository.That's reason my order shows Incomplete status.
    Can any help me to complete this flow.?
    Regards,
    Raj Jaiswal

    Hi,
    Yes I am extending CreateCreditFormHandler and adding this code getPaymentGroupManager().addPaymentGroupToOrder(order, creditCardPaymentGroup); As you said previously.
    This is the code I have written In my template.
    User is filling credit card details from the UI.
    Please validate the following approach.
    <br>FirstName:<dsp:input bean="CreateCreditCardFormHandler.creditCard.billingAddress.firstName" beanvalue="Profile.billingAddress.firstName" size="30" type="text"/>
    <br>MiddleName:<dsp:input bean="CreateCreditCardFormHandler.creditCard.billingAddress.middleName" beanvalue="Profile.billingAddress.middleName" size="30" type="text"/>
    <br>LastName:<dsp:input bean="CreateCreditCardFormHandler.creditCard.billingAddress.lastName" beanvalue="Profile.billingAddress.lastName" size="30" type="text"/>
    <br>EmailAddress:<dsp:input bean="CreateCreditCardFormHandler.creditCard.billingAddress.email" beanvalue="Profile.email" size="30" type="text"/>
    <br>PhoneNumber:<dsp:input bean="CreateCreditCardFormHandler.creditCard.billingAddress.phoneNumber" beanvalue="Profile.billingAddress.phoneNumber" size="30" type="text"/>
    <br>Address:<dsp:input bean="CreateCreditCardFormHandler.creditCard.billingAddress.address1" beanvalue="Profile.billingAddress.address1" size="30" type="text"/>
    <br>Address (line 2):<dsp:input bean="CreateCreditCardFormHandler.creditCard.billingAddress.address2" beanvalue="Profile.billingAddress.address2" size="30" type="text"/>
                 <dsp:input bean="CreateCreditCardFormHandler.newCreditCardSuccessURL" type="hidden" value="co_confirm.jsp"/>
                <dsp:input bean="CreateCreditCardFormHandler.newCreditCardErrorURL" type="hidden" value="co_confirm.jsp"/>
                <dsp:input bean="CreateCreditCardFormHandler.newCreditCard" type="hidden" value="Enter Credit Card"/>
                  <dsp:input bean="AuctionPaymentGroup.order1" type="hidden" beanvalue="ShoppingCart.current.Id"/>
                <dsp:input bean="AuctionPaymentGroup.AddPaymentDetailsToOrder" type="submit" value=" Continue -->"/>
                <dsp:input bean="AuctionPaymentGroup.paymentGroupSuccessURL" type="hidden" value="co_confirm.jsp"/>
                <dsp:input bean="AuctionPaymentGroup.paymentGroupErrorURL" type="hidden" value="error.jsp"/>
    I have customized CreateCreditCardFormHandler and added below code.
    public boolean handleAddPaymentDetailsToOrder(DynamoHttpServletRequest pRequest,DynamoHttpServletResponse pResponse) throws ServletException,
                IOException {
             String pOrder=getOrder1();
            try{
                OrderManager orderManager=(OrderManager)pRequest.resolveName("/atg/commerce/order/OrderManager");
                Order order = orderManager.loadOrder(pOrder);
                System.out.println("orderManager----"+order.getId());
                PaymentGroupManager paymentGroupManager=(PaymentGroupManager)pRequest.resolveName("/atg/commerce/order/PaymentGroupManager");
                System.out.println("paymentGroupManager----"+paymentGroupManager.getAbsoluteName());
                //Create the PaymentGroup
                PaymentGroup paymentGroup = paymentGroupManager.createPaymentGroup();
                //Add the PaymentGroup to the Order
                paymentGroupManager.addPaymentGroupToOrder(order, paymentGroup);
            }catch(Exception ex)
                ex.printStackTrace();
            return true;
    In the next templates I just want to display  billing details which added by the user .
    regards,
    Raj jaiswal

  • Previous figures before updating the price list

    Dear all,
    How do you get a previous price in the price list that is updated recently?.  i.e. the status of a price list on a given date?
    thanks
    SV Reddy

    You can try the AIT1 table. But it does not contain the date of the price change.