We have a scenario that due to some engineering changes some materials are to be modified in shape & size.So we send it to the vendor.But when we take it back we want to add the cost charged by vendor on material,Till now we were doing service PO for it.
How can we handle this in SAP right from taking the material out from plant & getting it back.
541 movement cannot be used as it has no valuation.
Regards,
Nandan.

Dear Nanadan,
1)First change the price in Material Master through Transaction code MR21 so that your valuation of material will be ok in future.
2) The material which is already sent & GR of finished product is already done , the financial impact can be setteled through " subsequent Debit " in the MIRO so that supplier will get the corrected price.
3)Subsequently change the PO conditions so that subsequent debit/credit will be avoided.
If useful reward points,
Vivek Maitra

Similar Messages

  • Price unit field in material master

    Hi all,
    Could you please tell me the use of price unit field in accounting view of material master? I know that it is the unit in terms of which standard price is maintained in material master. I also know that it should be equal or less than costing lot size. But i wanted to know if there is any other impact/use of this field like impact on per unit price etc.
    Regards
    Suresh

    Hi
    You have understood it correct...
    Just to add one more point, SAP recommends Price Unit to be higher i.e. 100 or 1000 in order to avoid rounding differences in Product Costing, variance calculation
    Br, Ajay M

  • When I sync my ipod to add new material, sometimes itunes will automatically rearrange the song order of my pre-existing albums by number of plays. Why does it do this? And is there a way to stop it?

    When I add an album to itunes and subsequently to my ipod, everything is arranged by track number of the album. Sometimes when I sync in order to add new material to my ipod, itunes for some reason automatically rearranges some of my pre-existing material by songs with the greatest number of plays to least (though sometimes it seems to be completely random). When I check itunes on my computer, everything still appears to be in order but the way it appears on the device often is in the previously mentioned disorder. Why does it do this? Is there any setting that I can adjust to make it stop because the only way I've found so far is to delete the rearranged material and re-import the cd and then re-sync. It might sound picky, but I prefer that my music be in order by track number as the artists themselves intended for various reasons the foremost being that I often listen to whole albums from start to finish and this glitch makes such problematic. I have found some settings in preferences that focus on how material is arranged but this seemed to be focused on the actual folders where the music is located on my hard drive and not the way it appears on the ipod. If anyone knows the reason it does this or has suggestions on fixing it, I would be greatly appreciative. Thanks.

    Did the original songs that do not appear on the car player play in the Music app on the iPod? Sometimes glitches happen and they do not. Also, If y ohave a 5G iPod/iOS 7, purchase songs  will show with an cloud icon by them if they are not downloaded if Shall All is turned on in Settings>iTunes and App Store

  • Price change for a material

    Hi Experts,
    Need ur help urgently,
    i have made a PO taking a material with std. price say 1 rs. but before doing GRN i changed the price to 4 rs. Now, when iam
    doing GRN , system post the document taking the old price (1rs.) of the material.
    I want that system should calculate the cost with the new price defined for the material ( 4rs.)
    In Accounting 1 tab of the material display MM03 :
    price control for valuation data for prevoius period is S
    and, price control for valuation data for prevoius year is also S
    Need ur assistance as I am new to MM
    Thanks.
    Dhruv

    Hi Experts,
    Need ur help urgently,
    i have made a PO taking a material with std. price say 1 rs. but before doing GRN i changed the price to 4 rs. Now, when iam
    doing GRN , system post the document taking the old price (1rs.) of the material.
    I want that system should calculate the cost with the new price defined for the material ( 4rs.)
    In Accounting 1 tab of the material display MM03 :
    price control for valuation data for prevoius period is S
    and, price control for valuation data for prevoius year is also S
    Need ur assistance as I am new to MM
    Hi,
    Dhruv,
    Whenever you create purchase order price is suggested from info records (if valid conditions are maintained) , if not from your last purchase order. If info record doesnt exists you have enter the prive manually in the item overview of purchase order. The price mechanism whether Moving average or standard is used basically for valuation purposes only. They are never suggested in purchase order.
    If you have updated your material master record with standard price and has changed it. Then it should be valuated at new standard price during good receipt
    It is always with standard price valuation that good receipt is always valuated at standard price and not purchase order price.
    Kindly check your material master record details.
    Also which transaction you have used for changing the standard price in material master record.Use MM02 Tcode and change the standard price as you like.
    I hope this is useful
    Regards,
    Tushar Patankar

  • How to create a Platinum,Gold and Silver Customer and how to set different price for a single material based on customer?

    Hi All,
    How to create a Platinum,Gold and Silver Customer and how to set different price for a single material based on customer?
    Assume Material is Pen.
    While creating Sales Order in VA01 how to bring different price for the same material for Platinum,Gold and Silver Customers.
    Kindly help me out.
    Thanks,
    Renjith Jose

    A good place to start is http://www.javaworld.com/javaworld/javatips/jw-javatip34.html
    Also, do a search in this forum on HttpURLConnection. That class allows you to use POST method to send form data to a web server.
    "Hidden" variables are only hidden in HTML. The HTTP that gets POSTed to the web server doesn't distinguish between hidden and not hidden. That is, the content you would write to the HttpURLConnection.getOutputStream() would be something like:
    hidden=1&submit=ok(Of course, the variable names would depend on what the web server was expecting from the form.)
    Also, be sure to set the Content-Type request parameter to "application/x-www-form-urlencoded"

  • Moving average price calculation logic of material with Price Control "S"

    Dear Gurus,
    As you know that there is a Moving price and standard price icon in the material master.
    I want to understand the calculation logic of the moving average price of the materials having price control "S"
    How the system calculates the MAP for standard price materials? The receipt from the process order I suppose is valuated at the process order cost after settlement, but if the issue has hapened for the material does the system recalculate the issue price also?
    Below is the sample process order receipt and issue scenario:
    Receipt from process order 161000000223
    300 kg and GR at standard cost value is Rs 5892
    Issue to process order 162000000294
    250 kg and GI at standard cost value is Rs 4910.
    Thus the balance at period end is 50 kg and balance at standard cost value is Rs 982.
    Here in process order 161000000223 the actual cost is 10 Rs. Then how will the system calculate the MAP?
    Thanking You,
    Amit Dhanurdhari

    Hi
    Try the following calculations,
    One of them will work depending upon your version and support pack
    Expected MAP calculation ( As with price control V)
    = ((Qty before transaction*MAP + Transaction Qty * transaction
    Price)) / quantity after transaction
    New Method ( when price control is S)
    = Old MAP + (Price Variance w.r.t Standard Price/Qty after transaction)
    Also go through the following notes,
    Note 1225167
    1253944
    518485 FAQ: Valuation of goods movements
    212286 Overview note: Valuation during goods movements
    209864 Moving average price is disproportionately large
    202166 Collective note: Statistical moving average price
    185961 Moving Average Price Calculation
    I have done extensive research on this, let me know if you need to know something specific.

  • Excise Value and Freight value should be add to material cost in the depot

    Hi,
    Can any one help me on my scenario?
    We have depot concept my client requirement is excise Value and Freight value should be add to material cost (inventories at depot) in the depot
    Thanks & Regards
    KMR

    Hi All,
       In Depot Sale. This are the Excise Duty Passed on to the Customer BED, AED ECS, SHECS, Other then that its added to the material cost. Define a Pricing procedure for value added to the material cost in both Procurement & Sales base your problem will be solved.
    Regards,
    Pherasath

  • Function Module for calculation of the net price of a configurable material

    Hi,
    I would like to know if a function module allows to calculate the purchasing /net price of a configurable material at a vendor and at a requested delivery date before the creation of a purchasing order.
    For configurable materials, we have no PIR and no moving / standard price thus the valuation price in the PR is blank.
    I would like to fill in the field "valuation price" in the PR with the net price we can find in the PO.
    However the PR is created before the PO.
    Thanks a lot in advance for yours reply.
    regards,

    hi Pravenn,
    I don't know about these functions, but u can try anything like this:
    data:
    strdate like sy-datum value '20070901',
          enddate like sy-datum value '20070909',
          date(10),
          moddate(1).
    date = enddate - strdate + 1.
    moddate = date mod 7.
    date = date div 7.
    if moddate <> 0.
      date = date + 1.
    endif.
    write: / date.
    Regards
    Allan Cristian
    Message was edited by:
            Allan Cristian

  • Simulate Price change in raw material

    Dear All.
    How can I simulate the new cost of all my FERT materials, if we have a price increase in a RAW material that is used in almost all FERT's.
    please help.

    Hi,
    create a costing variant using a valuation variant that valuates materials with priority 1 the new price from a "planned price field" in controlling 2 in material master (were you've maintained the new price for this specific material) and as priority 2 the price as in your old variant (for the materials where the price remains unchanged). Do not allow any price update for this costing variant to avoid erroneous use of this variant.
    Create a plan cost estimate for the same (reference) material(s) with your old and the new costing varinat, compare the same.
    Use report RKKBCAL2 do compare the results of 2 costing runs (again one with the old costing variant one with the new).
    best regards, Christian

  • Price update from Original Material to copied Material Master

    I have a scenario,
    We are selling Raw materials to outside companies who have shortage of materials on Loan Basis. Once they have materials, they will return the materials within a time period. If they don't have the materials and unable to return within the said time, they will make the payment.
    We will follow the normal sales process to sell the item to the customer.
    1. creating sales order,
    2. Outbound Delivery, and
    3. Billing
    Return process when receiving the materials from the company.
    1. Billing Cancellation
    2. PGI Cancellation
    Since this is not an actual sale, hence we need to maintain selling price same as the purchase price.
    We are planning to extend the Raw Materials to Sales View in the material master. However, we came to know that this will be Violation of Act. Hence we are planning to create a new material by copying the existing Raw Material master but the Material type will be Issue on Loan. This material will have sales view and purchase view.
    This material will have a separate Valuation Class. Price control indicator will be V, since the item should be valuated at Purchase Price and the purchase price will keep changing as and when the price changes. This moving average price will be used as selling price.
    The same price needs to be updated in the Sales Order automatically from the Loan Material Master when selling the Loan Material.
    Now, the problem we are facing is, if we create a new Loan Material by copying Raw Material master with ROH material type, how will the price update in New Loan Material since, we will not purchase the Loan Material. We are purchasing the original item as raw material. Hence, this will not update the Loan Material Price automatically and the price will remain unchanged.
    Please suggest a work around?

    Hi,
    Let me explain to you how I am proceeding.
    Step 1:
    Create new material master by copying existing Raw Material with Issue on Loan material type. I am assigning a new Valuation Class in this material master. Also, we keep the pricing
    Step 2:
    Transfer stock from old material to new material in MB1B with movement type 309.
    Step 3: Issue of Loan Material to Customer on loan basis.
    Creating Sales Order, PGI and Billing
    Step 4: Receipt of Item back from Customer
    Sales Return process.
    Step 5: In case Customer does not return goods, then we will collect payment from them
    In the entire process we need to maintain the selling price at purchase price of the original material. Can you suggest any work around, in case this process is not advisable.

  • How to get net price of a given material(Just like in VA01)

    Hello Experts,
    How do I get the net price of a given material? Just like when entering a
    material in VA01(sales order creation). Hope you can help me guys.
    Thank you and take care!

    This is a million dollar question.
    It depends on how the pricing have been configured in your system and only your SD consultant can answer it correctly. Price in VA01 could be determined by using the pricing conditions or, if allowed, a manual user entry (i.e. when users just type in the price). Discounts, taxes, etc. are calculated in a similar way, also based on the configuration.
    Pricing conditions are displayed in transaction VK13. You might want to take a look at an order in VA03 -> double-click on a line and go to Conditions tab. There are buttons Analysis and Condition Rec. that might be useful for your research. It is possible to configure different price for the same material and different customer, distribution channel, etc., so you will have to ask your SD consultant how to get the correct number in each case.
    Just FYI the net price on the order/contract is in VBAP-NETWR and condition are stored in the tables Annn, e.g. A901, etc. The tables are generated according to the configuration and are different in each system.

  • Effective price is 0.00 $, material price is 30.00 $

    Hi,
    When I created PO in ME21N transaction, I am getting the message
    Effective price is 0.00 $, material price is 30.00 $.
    I have entered the same price from Material master as Net price in PO, still I am getting the same message.
    Please help me to overcome this message.
    thanks and regards
    Murugesan

    Dear,
    The effective price in purchase order 0.00$ and material price (either starndard or moving)in material master is 30.00 $.
    Change the messgae to warning.
    Regards,
    Syed Hussain.

  • Price changes of a material

    Hi all,
    I need to list the whole price changes of a material that we purchased from suplliers.
    How can i get these data, ie from which tables?
    Thanks in advance.
    deniz.

    Hi friend,
    Try FM
    CKML_MATVAL_PRICE_CHANGE
    Also check the tables : 
    CKMLHD  - Material Ledger: Header Record
    CKMLCR   Material Ledger: Period Totals Records
    CKMLPR Material Ledger: Prices
    Regards
    kanishak

  • Freight value to  add in material cost

    HI.
    I have freight condition FRA1 i which i ticked Accrual key in M/06,I have assigned FR6 account key to it in pricing.I don't want to calculate the tax on freight ,so i ticked statistics key in Pricing for Freight cond.(FRA1)
    Then also freight value is not adding in material cost .
    What would be the reason?
    Please provide suitable solution.
    Thanx & Regards

    Hi,
    Normally if you mention statistics for a condition, then the value will not add to material cost. You remove the statistics for the condition.
    Also check for that condition type, have you maintained accrual check box.(tick mark for accrual inside condition type).
    If you dont want to add frieght value for tax calculation, then give the step number accordingly.
    Regards,
    Prabu

  • Add Competitor Material via MMW1 but material number exists

    Master Data Experts:
    1. We are adding material type WETT competitor materials via tcode MMW1. However, we have many cases where our competitor number is the same as one of our own existing physically different material numbers. When we try to add the material, we get the hard error message "Specified material already assigned to material type xxxx" and cannot add the competitor material number.
    2. Similarly, we have many cases where more than one of our competitors use the same material number, so we cannot add more than one as a competitor number.
    3. Lastly, we have some competitor material numbers that are more than 18 characters long, and due to the SAP limitation of 18 characters we cannot add these competitor numbers via MMW1.
    These scenarios have never worked before, there is no ABAP related user exits, etc, and no changes done before the problem occurred. We understand that under the single instance system you cannot add the same material number more than once, and we have a company policy system in place so our businesses will not have these material number collisions. However, we cannot control what material numbers our competitors use, so we need some way to remedy this so we can add competitor numbers even though they may already exist.
    Any help that can be given would be appreciated,
    David Bruhn
    Hubbell, Inc.

    Hello James and happy new year.
    Thank you for your answer.
    In fact, I already tried to leave the matnr field with blanks and for a material type which use internal numbers range. I hoped/thought it would have worked as you said but it wouldn't.
    About the external old numbers I keep, I think I don't have to use the field external_number of the E1MARA1 segment, because some of my tests showed me that it works good. Moreover, I don't really understand the reason why this field exists because the field matnr is here for.
    I presume that the external_number is maybe for another use I don't know, aren't you ?
    I've never used this segment for data take over.
    Do you know if the principle you described in your previous mail is also the same to apply to customers & vendors idocs ?
    Best regards.